Level 3 - Procurement & Tendering Flashcards

1
Q

If your client was building a hotel and quality of finish and programme were the most important factors what procurement route would you advise, and why?

A

Two stage tender

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Where would you look to for procurement and tendering guidelines?

A

Tendering strategies 1st edition - RICS guidance note

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What tendering strategies are available?

A
  • Single stage - Two stage - Negotiated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the difference between tendering and procurement?

A

There is often confusion in the industry about the differences between tendering and procurement. The terms are sometimes used interchangeably without thought given to their actual meaning. They are distinct activities in the construction process and it is necessary to properly understand them to be able to explain the differences. • Procurement is the overall act of obtaining goods and services from external sources (i.e. a building contractor) and includes deciding the strategy on how those goods are to be acquired by reviewing the client’s requirements (i.e. time, quality and cost) and their attitude to risk. • Tendering is an important phase in the procurement strategy but procurement involves much more than simply obtaining a price. Tendering is: • the bidding process, to obtain a price; and • how a contractor is actually appointed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is single stage tendering?

A

The most common type of tendering strategy is the single-stage competitive tender for obtaining a price for the whole of the construction works. Invitation to tender documents are issued to a number of competing contractors who are all given the chance to bid for the project based on identical tender documentation. This is usually done at RIBA Stage 4 so that the tendering contractors receive the most detailed information to base their bid on. The bidding contractors are given a predetermined amount of time to submit their tenders. These are then analysed, in terms of cost and quality, before a single contractor is declared the preferred contractor. They then ultimately enter into a building contract with the client to deliver the tendered works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is two stage tendering?

A

Two-stage tendering has become more common in recent years and is often used where time is constrained (as it enables design and tendering to overlap). It is also used if the design process would benefit from the technical input of a contractor in the later design stages. In this sense it is used to obtain the early appointment of a contractor. The process involves first-stage tender enquiry documentation being issued to bidding contractors at RIBA Stage 2 or 3. Rather than requesting a bid for constructing the entire project (which is still in the process of being designed), the preferred contractor is chosen on the basis of the quality of their bid, the quality of their team and their preliminaries price and overhead and profits allowances. The preferred contractor then joins the design team on a consultancy basis using a pre-construction services agreement (PCSA). The preferred contractor then works with the professional team to complete the design, usually to RIBA Stage 4, before presenting a bid for the works at this stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is negotiated tendering?

A

A negotiated tender is effectively a single-stage tender with a single contractor who returns with an initial price. This is then negotiated with the client’s professional team (usually the professional quantity surveyor (PQS)). The benefit of this route is the speed with which a price can be obtained for the works. However, the competitive advantage of a formal bidding process is compromised. Also, many public bodies and government departments will not allow negotiated tenders except in exceptional circumstances as it is difficult to prove that value for money in the current market has been achieved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Can you provide me with an example of tender scoring?

A

Assessments might consider some of the following criteria: Price. Relevant experience. Understanding of the requirements. Past performance. Technical skills. Resource availability. Management skills and systems. Proposed methodology (this might include mobilisation plans, design proposals, and non-compliant proposals if these have been allowed). Compliance with the requirements set out in the invitation to tender.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Please provide an example of some procurement routes?

A

1 Traditional contract 2 Design and build 3 Management contracting 4 Construction management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is traditional procurement including the pro’s and con’s of this method?

A

Good for: Quality – full design pre tender Design flexibility – variations & instructions Specialist subcontractors – Named specialist update to standard building contract sbc11 Design control – through the architect / contract administrator Contractor’s Designed Portion – such as mechanical and electrical engineering Cost – there may be lump sum cost benefits unless are multiple changes made Not suited for: Time – require full detailed pack pre tender Cost – not a benefit if many changes made Incomplete drawings – lead to delay, costs and claims of negligence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is D&B procurement including the pro’s and con’s of this method?

A

Good for: Time – Fast track, overlap of design and construction Cost – lump sum / Guaranteed maximum price Single point of responsibility – Contractor design and build responsibility Has good price certainty Easy to arrange changes in the design Novation – can benefit quality. Low risk for the client Variations can be accurately valued Not suited for: Quality – cheapest route to meet contract specification can lead to low quality products/ build quality. Design flexibility – request for changes will have cost/time implications Contractor carries risk for construction Client exposed to claims for buildability Design could affect the buildability of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Management contracting procurement including the pro’s and con’s of this method?

A

Good for: Complex / specialist projects – individually appointed packages to best suited sub-contractor Potential cost saving – competitive tender Time - it is possible to overlap design and construction Quality – each package subcontracted to specialist Design flexibility – changes can be made throughout construction, although there are potential cost implications. Not suited for: Inexperienced clients – risk high Fixed cost - Prime cost basis per package. Lack of available specialists – would leave gaps in work to be undertaken.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Construction Management procurement including the pro’s and con’s of this method?

A

Good for: Complex / specialist projects – individually appointed packages to best suited sub-contractor Time - It is possible to overlap design and construction Design flexibility – changes can be made throughout construction, although there are potential cost implications. Potential cost saving – competitive tender Quality – each package subcontracted to specialist All building types Efficiency – Early appointment of the construction manager to aid programme Inexperienced client – risk high as appointing trade contractors Fixed cost - Prime cost basis per package. Lack of available specialists

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a Lump sum and what is it priced with?

A

• A lump sum contract = a single ‘lump sum’ price for all the works is agreed before the works begin. • Lump Sum contract with quantities: Priced on the basis of drawings and BoQ. Items that can’t be accurately quantified = provisional sum. • Lump sum without quantities: Drawings and Specifications. • If lump sum not itemised, schedule of rates will be required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does a Lump Sum contract require:

A

• Defined Scope • Stable market conditions and absence of major economic of political uncertainty • Minimal Scope change • Time for scope definition and building process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Lump Sum Characteristics:

A
  • Well defined Scope - Less appropriate when speed is important (need time to define scope) - Client some certainty around cost - More risk to the Contractor – fewer mechanisms to vary price  Variations (Change to nature of works)  Provisional Sums - Better defined works = less opportunity for variation - True fixed cost, not necessarily best interest of Client. Less opportunity to vary design/requirements.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Measurement Pricing Definition

A

contract sum is determined on completion and in accordance after re-measurement in accordance with predetermined method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Measurement Characteristics

A
  • Early start before design is complete - Uncertainty of works(refurb/Excavation) - Client Change relatively easy - Risk to Client, as cost of works is ‘unknown - Scope of work defined amount not (no bOQ) - Sufficient detail scope to allow contractor to calculate unit rates - Based on drawings and schedule of Rates - Best confined to small projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Cost Reimbursement Pricing

A

Contract sum is arrived on the basis of actual costs for labour, plant and material. Additional fee to cover management, overheads and profit.

20
Q

Characteristics Cost Reimbursement (Cost Plus):

A
  • Minimal pre-determined scope definition - Clear and explicit of what constitutes reimbursement costs - Cooperative atmosphere, competence trust - If fixed, sufficient scope definition for control and estimating the extent of services required
21
Q

What is design bid build?

A
  • Traditional procurement - Design separates from Construction - Client appoints design Team consultants (engineer, architect, surveyor) - Contractor responsible for carrying out of the works (including subconsultant and suppliers)
22
Q

Advantages and Disadvantages of Traditional Procurement

A

1) Competitive tender – all bid on same basis – lower price. 2) Client direct influence design = greater quality and functionality 3) Price certainty 4) Tried/Tested procurement Route 5) Design responsibility with Client 6) Client direct influence design = greater quality and functionality 7) Risk of delay, cost over run – incomplete information 8) Hinges on the quality of information provided to Contractor

23
Q

What is a single Stage Tender

A

An invitation to tender is issued to prospective suppliers (perhaps following completion of a pre-qualification questionnaire and/or a pre-tender interview). Tenders are prepared and returned by prospective suppliers (this may involve questions and answers and a mid-tender interview to clarify the client’s requirements). Submitted tenders are then assessed and compared (this may involve further interviews). The preferred tenderer is selected and negotiations opened. Subject to the outcome of those negotiations the preferred tenderer may then be appointed.

24
Q

What is a Tender

A

A tender is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods or services.

25
Q

Why a Two Stage Tender?

A

Employers requirements are not sufficiently developed Allow Early Contractor Engagement Client Transfer Risk to Contractor Tends to include fewer variations and fewer claims

26
Q

Describes First Stage of Two Stage Tender

A
  • Contractor engaged on an Initial Scope of Work via PSCA, bespoke agremeent - Contractor assists with the final development of design and tender documents, against which tenders for construction works - Tenderer has opportunity to negotiate for the second stage
27
Q

What is the PCSA

A
  • Contractor helps develop the design - Develop methodology should improve buildability and cost certainty - opportunity to challenge and interrogate the functionality of the design - Integrated team less likely disputes - Embedded - less competition for contractor
28
Q

Traditional Procurement Characteristics

A

Small/Med Projects Focus on quality over Time Design Risk with Client Separate Contract Design/Construct Consultant prepare design specifications and drawings for Contractor Contractor engage sub-consultants Lowest Bid Sequential Time Frame

29
Q

Explain the advantages of Traditional Approach

A

Widely Used Competitive Tender Certainty around Price Architectural Freedom Quality – full design pre tender Client Design flexibility

30
Q

Explain the disadvantages of a Traditional Approach

A

Design Responsibility with Client Adversarial Contract relationship - Blame culture Hinges on quality of information provided Time – require full detailed pack pre-tender Cost – not a benefit if many changes made Incomplete error/omission drawings – lead to delay, costs and claims of negligence

31
Q

Explain the disadvantages of a Traditional Approach

A

Design Responsibility with Client Adversarial Contract relationship - Blame culture Hinges on quality of information provided Time – require full detailed pack pre-tender Cost – not a benefit if many changes made Incomplete error/omission drawings – lead to delay, costs and claims of negligence Problems of build ability Sequential and fragmented

32
Q

What is competitive Tendering?

A

Invites contractors to submit the lowest price for which they are willing to carry out a project Relies on the information contained in drawings, specifications and bills of quantities prepared on behalf of the Client. Types - Open, Selective (1/2 Stages)

33
Q

What is Open Tendering

A

Any contractor is allowed to submit a Tender to advertised project

34
Q

What is the Process of Open Tendering

A
  1. Client Advertises openly in the press inviting contractors to apply 2. Contractor requests a ‘Request for Tender document’ 3. Contractor may be requested to put down a bona fide deposit, to show they are genuine
35
Q

What are the Advantages and Disadvantages of Open tendering?

A

Advantage - Maximum Competion, lowest price obtained Dis - Waste effort, too many tendering. Client inclined to accept the lowest Tender irrespective of reputation

36
Q

What is Selective Tendering

A

When contractors of known reputation are selected to submit a Tender. Most common method of tendering

37
Q

What is the process of Selective Tendering

A
  1. Design Team selects known Contractors and Invites them to Tender. 2. Contractors tenders are usually based on a complete design 3. Project awarded for the Lowest Tender.
38
Q

What are the Advantages and Disadvantages of Selective tendering?

A

Adv - Tenders known, cheapest bid not as high of a risk as an open tender. Dis - Limitations exclude new bidders who may offer more innovative ideas or solutions

39
Q

What is the Aim of Two Stage Tendering

A
  1. Speed up process (Early integration of Architect and Contractor) 2. Improve Buildability
40
Q

What are the Advantages and Disadvantages of Two Stage tendering?

A

ADV: Contractor input into methodology and buildability Speed of construction Fast Tendering DIS: Architect and Contractor may not agree lead to time suffering.

41
Q

Describe the two stages of Tender Evaluation

A

Pre-Tender/Pre=Qualification. Ensure that Contractors = Reputable, Capable and Experienced. Pre-Contract Ensure that Contractors = Understand the project, realistic Bid, Proposed resources are adequate.

42
Q

What is the fundamental difference between procurement and tendering?

A

Procurement is the strategy of delivery and Tendering is how you award the contract

43
Q

What are the Advantages of Design Bid Build procurement (think Client perspective)

A
  • Main reason is to take control of the design and contract out the build to ensure quality.
  • Development of the design will be finalised before contractors offer tenders for the build: Clearer version of end-product
  • Cost fixed from the start - Client retails control of the Design throughout.
  • Costs associated with a premium - quantities are dictated in the design and the control has little flexibility to manage the price
  • Used when design is important to the Client - TIME NOT AN ISSUE
44
Q

Disadvantages to Traditional (design-bid-build) procurement for the Client

A

TIME

  • Front end of the development is front loaded - large design element.
  • Cost premium might be higher as quantities are dictated in the design and the contractor has little flexibility to manage the price.
45
Q
A