Tell me about the property?
3 units totalling 100,000 sq ft
1 hanger unit - 1940s with barrel configuration, steel lined concrete, recently reclad
2 attached units - 2010s, steel portal frame, modern design
Eaves between 7 - 9M
Large site (16% coverage) with poor surface in part
How did you determine covenant strength?
Assess financial creditworthiness for the bank
Commission Dun & Bradstreet report
Why does covenant strength assist with loan security decisions?
Shows how reliable a borrower is
Assessment of risk for a lender
What did the D&B report include?
Snapshot of company account and creditworthiness
Operational information
Company details
Payment history
D&B Score
What is a D&B score?
Two digit score
Strength - - based on tangible net worth
Risk - derived from D&B failure score
What is a good D&B score
5A 1
What was the D&B sore?
N 4
Negative Net worth
Significant Risk
How did you assess the covenant to be for loan security purposes?
I deemed this to be risky, and therefore reflected this in my yield profile which affected MV
What was your MV?
£3,000,000
How did you form your MV?
Assumed a MR based on comparable evidence
Yield of 10% based on comparbales and specification
Capitalised rent at 10%, assuming longer letting and void periods on the hanger unit
Void costsW
What were the letting assumptions?
Hanger - 18 months letting period, 6 months rent free
Modern - 6 months letting period, 3 months rent free
What was MR?
£2.95 overall
£2.50 Hanger
£4.50 Modern
What adjustments did you make to form 10% yield?
Based on Comparables
hanger component
poor tenant covenant
non-modern specification of hanger
Location being sub-prime
Scrub land in part
Tell me about your valuation in Llandow
Point 1 – I valued a old hanger unit and two modern units on a large site in south wales
Point 2 – I obtained a D&B report to understand the tenant covenant for MV, which proved to be a poor covenant