Lesson 5: Executing a Program Increment Flashcards

1
Q

What are the key team iteration events?

A

Iteration planning
Daily standup
iteration review
iteration retrospective

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the key PI execution events

A

Scrum of Scrums
PO Sync
ART Sync
System Demo

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are some metrics used to measure PI execution?

A

PI Burndown Chart

Cumulative Flow Diagram (CFD)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Map PDCA to key team iteration events

A

Plan - Iteration Planning
Do - Daily Standup
Check - Team Demo/Iteration Review
Adjust - Iteration Retrospective

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

At the end of each iteration, what is the RTE supposed to do?

A

The RTE collects and aggregates ART metrics to understand PI progress and ART health. (Feature Progress/completion)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The RTE facilitates the escalation of _____ further if it cannot be solved with the ART.

A

impediments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why is the Scrum of Scrums important for the RTE?

A

to determine if we will meet our PI commitments and to uncover any impediments that may need to be escalated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why is the PO sync important to the RTE?

A

to have visibility into progress, scope, and priority adjustments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the ART sync and its primary focus?

A

It is a SoS/PO Sync combo and its focus is on “Will we meet our PI commitments?”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How often is a full system demo to be held?

A

every sprint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When is a final system demo to be held?

A

in the Inspect & Adapt

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A Program Kanban Board is a powerful tool to visualize the flow of ____ and ____ through the ART

A

Features and Enablers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does a cumulative flow diagram show?

A

the amount of work in the different Kanban states.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly