Demolition planning work
A
1) preliminary investigation
2) pre-demolition audit
3) design for demolition
4) tendering
2
Q
Design for demolition (6)
A
- Assessment of work methodologies
- Change of infrastructure
- CDW management
- Environment managment
- Health and safety management
- Information management
3
Q
Selective demolition - Procedure
A
1) Preliminary work
2) Removal of permanent installations
(stripping)
3) Demolition of shell structure
4) Removal of containers and general cleanup
4
Q
Demolition of concrete (7)
A
- Crane and ball
- Breaking and hammering
- Crushing
- Wedging/bursting
- Blasting/explosive demolition
- Abrasive drilling and cutting