Legislation Flashcards
What year was the WIA implemented
1991
Section 159
Section 163 purpose?
Connect, lay, inspect works
Section 159 notice timeframe?
New work 3 months existing alterations 42 days/6wks
Section 168?
Power for inspection prior to works
Section 169
Likied access anticipating cp
Schedule 6
Warrant for entry
Schedule 12
Compensation on basis of 1. Depreciation 2. Damage for disturbance 3. Damge/injurious affection
Schedule 13
Protected provisions. Cannot carry out works without consent of Trust. Works subject to reasonable conditions not to be unreasonably withheld. Disputes to arbitration.
Section 160
Access for sewage works
Water co’s can acquire an easement by what legislation?
- CP 1965
- Acquisition of land act 1981
- Land Compensation Act 1961 part 5
Levels of payment for wayleaves, undertakers like them
50% of MV land value as depreciated by 50%. Also costs for disturbance, engineer and surveyor
Water companies can go to what to determine
Arbitration
Section 155
Compulsory purchase powers
LCA 1961, case law as to area subject to compensation?
St John’s college v Thames Water, full area not just easement strip