Legan & Regulatory Compliance - Flash Cards - Level 2
HDP, WSCC - What type of planning application was submitted for this project?
Full plans, replacements were of a different design following therefore they did not fall under permitted development.
HDP, WSCC - Why did a planning application need to be submitted for the replacement windows & doors?
The window and door fenestrations were to be changed from those existing, requiring full plans.
HDP, WSCC - What information did you refer to determine a planning application was to be submitted?
Review requirements of development in Town & Country Planning Act 1990. Whether work falls under permitted development. LA planning policy / design guidance. Planning portal.
HDP, WSCC - Where would you find information on what documents need to be provided as part of the planning application?
Review to the national requirements on the planning portal and local list of requirements provided by the local planning authority.
HDP, WSCC - What documents did you submit with the planning application?
Application form, covering letter, fee if applicable, site location plan, site boundary plan, layout plan, elevations including existing and proposed.
HDP, WSCC - What is a design and access statement?
Sets out design principles and steps taken to account for development context, access to the development and community engagement.
HDP, WSCC - Was a design and access statement needed on this project?
No, did not meet the requirements. Conservation area, floor space of 100m2 or more, listed building consent, major development.
HDP, WSCC - What drawings were provided as part of the application?
Site location plan, site boundary plan, layout plan, elevations including existing and proposed.
HDP, WSCC - How long does a planning application take to be decided?
8 - 12 weeks.
HDP, WSCC - What is the process of validation within the planning application process?
When the planning authority reviews the information submitted to ensure that meet the national and local requirements.
Planning, Childrens Home, WSCC - Where would you find a planning condition?
Detailed within the approval letter provided by the planning authority. Not all conditions require discharge.
Planning, Childrens Home, WSCC - Where does it stipulate the deadline for discharge?
With the condition that requires discharging, commonly before the start of the development or before the use or completion of the development.
Planning, Childrens Home, WSCC - What is the process of condition discharge?
Identify condition when approval is provided, consolidate information required, complete application for condition discharge, await approval.
Planning, Childrens Home, WSCC - What type of planning applications do condition discharges arise?
Full plans.
Planning, Childrens Home, WSCC - What was the discharge requirement on the project?
Construction Management Plan - vehicles, access, parking, plan, storage, security. Prior to commencement of the project.
Planning, Childrens Home, WSCC - What information was required to be submitted?
I requested the contractor provided a suitable construction management plan once the tender was awarded so that the condition discharge could be submitted. Required document, application and fee if applicable.
Planning, Childrens Home, WSCC - What are the consequences of not discharging a condition?
Enforcement action for unlawful development, breach of condition which can result in prosecution.
Planning, Childrens Home, WSCC - What is the timeline in which the authority provides approval?
8 weeks.
Planning, Childrens Home, WSCC - What happens if the condition is not applicable any longer?
An application can be made for the removal or variation of conditions.
CDM, Childrens Home, WSCC - What were your duties under the CDM regulations 2015?
My duties as a designer are to take in to account PCI, design with risk elimination, reduction and control in mind and review designs in the same manner.
CDM, Childrens Home, WSCC - What were the PD’s duties under the CDM Regulations 2015?
Plan, manage and monitor H&S in pre construction. Advise client on bringing together PCI. Work with designers to eliminate, reduce and control risk. Liaise with PC.
CDM, Childrens Home, WSCC - How did you review risks throughout the project?
The PD utilised a design risk register, and held monthly design risk meetings throughout the project to review designs to eliminate, reduce or control foreseeable risks.
CDM, Childrens Home, WSCC - Provide an example of a risk highlighted and how it was reduced or eliminated?
Relocation of PVs from a flat roof to a pitched roof making them more accessible to clean from the ground rather than having to work at height.
CDM, Childrens Home, WSCC - Who is responsible for raising an F10?
The client, however the PD raised this on behalf of the client in this case.