- Which of the following strategies CANNOT be included as alternative transportation strategies?*
- Choose 2*
- Motorbike
- Single occupant car
A project is analyzing alternative transportation strategies. Under what conditions can a ride-share be counted as alternative transportation?
If the ride-share is used by both regular occupants & visitors; NON - US Projects only
Alternative transportation as it applies to LT Credit 1 includes all but which of the following:
Expanded workweeks
A Project team has decided to conduct an on-location, in-person transportation survey. Which of the following will help the project team yield better response rate and results?
Surveyors should be present at all project building entrance points
When conducting a survey as part of the calculations for LT Credit 1 Alternative transportation, which dates/times are the best?
A survey conducted each day starting on Monday and ending on Friday
A project building has a total 200 regular building occupants & visitors. What minimum response rate is needed for a valid transportation survey?
10 total regular building occupants & visitors
The office project has achieved 40% alternative transportation rate. How many points can the project attain under LT Credit-Alternative Transportation?
9
In an existing city transportation office, number of visitors during the typical peak hours outnumbered the regular building occupants. The city office is planning to conduct a transportation survey. Should the visitor be surveyed under LT Credit- Alternative Transportation?
Yes, visitor should be included
A school has attained 85% reduction compared to conventional commuting baseline. How many points can it earn under LT credit 1 - Alternative Transportation?
16
What is extrapolation factor if the survey rate is 50% under LT Credit 1- Alternative Transportation?
0.8
A vehicle can be counted as a green vehicle under what conditions?
The vehicle achieves a minimum green score of 45 on the ACEEE annual vehicle rating guide
A project team analyzed the survey results for regular occupants to calculate the alternative transportation rate and found only a 25% survey response rate. What should the project team do next?
All non-responders are assumed to commute in single-occupancy vehicles
An occupant commute survey with an 80% response rate revealed 50% of respondents take alternative transportation to work. What is true about the non-responders?
Half of the non-responders are assumed to take alternative transportation to work
What is the maximum number of points that the project earn under LT Credit- Alternative credit including the exemplary performance credit?
16 points
The owner of an office building is considering the best way to conduct a transportation survey to achieve Location and Transportation credit Alternative Transportation. The owner understands that several of the tenants allow employees to telework, and therefore, has chosen to distributean electronic survey. Tenant “A” occupies 57% of the building, Tenant “B” occupies 32% of the building, Tenant “C” occupies 6% of the building, and the remainder is occupied by Tenant “D”. The building includes 972 regular occupants. In order to correctly distribute surveys to randomized sample of each tenant, the owner must allocate how many of the surveys to each tenant?
Tenant “A”-163 surveys, Tenant “B”-92 surveys, Tenant “C”-17 surveys, Tenant “D”-14 surveys
A Core and Shell Project in Santa Monica, California is pursuing Regional Priority credits and searching the USGBC database to explore the 6 available credits to choose 4 credits. Which RP group should the project download?
RP credits applicable for Core and Shell Project types
A hospitality project team is considering LEED certification under LEED O+M. Which of the following credits must the project implement in order to earn LEED Platinum level certification?
Choose 3
- SS Prerequisite Site Management Policy
- EA Prerequisite Building-Level Energy Metering
- EQ Prerequisite Green Cleaning Policy
A hospitality project team member finds an area not addressed in the LEED reference guide regarding WE Credit Outdoor Water Use Reduction. The team implements the credit and submits a suggested approach for the credit during the preliminary LEED review process. Which of the following is true regarding this project team’s approach?
The project team will receive a determination in the comments at the discretion of the USGBC or GBCI reviewer assigned to the project
A LEED Existing Building project receives notification from GBCI when the preliminary review is complete. The review consists of clarifications and technical advice on a few design credits. Which of the following should the project team or LEED Administrator do?
The project team should respond to the technical advice and clarification through LEED online and re-submit credits if required
A new construction project was registered in December of 2013, In May, 2014 USGBC publish Addenda for a credit the project pursuing. What statements are true regarding this project?
Choose 2
- The project team can choose to follow any addenda published after May, 2014
- The project team must follow any addenda published prior to December, 2013
A project in Oklahoma is analyzing various credits for exemplary performance. Which of the following credits would qualify for the project to earn an exemplary performance point under IN Credit Innovation option 3 Additional Strategies? Choose 2
- LT Credit Alternative Transportation
- EA Credit Renewable Energy and carbon offsets
A project in Raleigh, North Carolina was originally registered under BD+C: New Construction. Later during the pre-design stage, the owner finds 3 tenants to occupy the building space upon completion and hence wants to change the rating system to Core & Shell. Which action should be taken by the project team?
Contact LEED technical customer service
A project team after careful research identified 2 innovative ideas for successful innovation credits that were implemented in past LEED projects and awarded innovative credits for. Which of the following actions should the project team take for successful implementation of the innovative ideas?
Seek formal pre-approval from USGBC by submitting CIR
A project team is evaluating different project locations and sites for a potential LEED ND project. Which of the following must be true in order for the site to qualify for LEED certification under the LEED ND rating system?
Choose 2
- The site should have at least 2 habitable buildings
- The site should be NO LARGER than 1500 acres
A project team is exploring full range of innovative opportunities in their project building by referring to the online Innovation database for examples of successful innovation credits. Which of the following actions should the project team take if the project team seeks formal pre-approval of an innovation strategy?
Submit a CIR
A project team member is very active in his community. He is working with the owner to devise a program that fosters the growth of green buildings by showcasing the project building as an example. Which of the following instructional initiatives would satisfy the requirements of an education program for innovation for IN Credit Innovation?
choose 2
- A comprehensive signage program throughout the project to educate occupants and visitors about the benefits of sustainable buildings
- Weekly guided tours on sustainable and building green using the project as an example
Following variables affect LEED Registration cost?
Choose 2
- Time when the project team decides to register
- Project’s rating system
How does USGBC encourage project teams to focus on their local environmental priorities in the project’s region?
Regional priority credits
How is the LEED boundary determined for multi-building development especially when each building in the property will be a separate LEED project
The project team should determine the LEED boundary for each LEED project
How many points can a project earn for RP credits?
4
How many points can a project earn under innovation?
4
The question asked for “innovation” under innovation credit NOT innovation credit in general
How many RP Credits are identified for every location?
6
The LEED project boundary may not include land that is not owned by the project owner unless:
The land is associated with the LEED project and supports it’s normal building operations
The project team for a Core & Shell building in India is considering a composting program. Which statement is true regarding the IN Credit Innovation for a composting program?
IN Credit Innovation for Core & Shell can only be earned if all occupants including tenants of the building are allowed to participate in the program
The project team for a mixed use project located in Washington D.C. has more than 50% of it’s space for retail and remaining 40% or less for office space. How should the project team decide which rating system to use?
The project should use the 40/60 rule to decide on a rating system
The project team for a potential LEED project in Phoenix, Arizona submits a summary of early design stage submittal materials for GBCI review to pursue LEED Pre-certification. Which of the following statements must be true of the project?
The project must be registered under Core and Shell
The project team for an Existing Building office in Dubai is considering different Innovative strategies for IN credit Innovation. Which of the following criteria should be met for the IN credit?
Choose 3
- The strategy must be significantly better than standard sustainable design practices
- Strategies should be comprehensive
- Strategies must demonstrate a quantitative improvement
What best defines LEED project boundary?
Platted property line of the project defining land and water with in
What options within LEED credits address different geographic areas and climatic regions while providing solutions to challenges faced by projects at a regional level?
Alternative Compliance Paths (ACPs)
Which design decisions can earn a project IN Credit Option 1 Innovation in a new construction project?
Implementing a credit from LEED BD+C
Which of calculations is NOT provided by LEED for implementing commissioning changes?
Time value of money
Which of the following actions should the project team take if the project boundary is not clear?
Review the MPR
Which of the following are perks for a company that receives LEED Platinum awards for it’s HQ project?
Branding and public relations (PR)
Which of the following calculations are referenced under LEED Commissioning credits?
Choose 3
- Return on Investment (ROI)
- Simple payback period
- Cost-benefit ratio
Which of the following credits does have exemplary performance opportunities? choose 3
- Green Cleaning - Products and Materials
- Green Cleaning - Equipment
- Enhanced Indoor Air Quality Strategies
Which of the following defines substantial project completion for LEED certification?
Date on which the building receives a certificate of occupancy or similar official indication that it is fit and ready for use
Which of the following defines the LEED boundary for a single building development?
The entire project scope - generally limited to the site boundary
Which of the following elements of the LEED v4 development cycle is utilized for streamlining the approach to unique needs, constraints, and opportunities of different project types?
Adaptations
Which of the following fees is only applicable for LEED Core & Shell projects?
Pre-Certification Fees
Which of the following is true about Credit Interpretation Request (CIRs)?
CIRs can be submitted for prerequisites
Which of the following is true for innovations that are no addressed by existing LEED credits?
Choose 3
- Points can also be earned by achieving selected credits from other LEED rating systems
- The strategy must significantly better than standard sustainable design practices
- The project must demonstrate a quantitative improvement in environmental performance by identifying OR establishing a baseline of standard performance
Which of the following may earn a project IN Credit Innovation under option 1 - Innovation?
Select 2
- Designing and implementing a green housekeeping program
- Designing and implementing a green education program
Which of the following must be true of the project site, location and size in order to be eligible for LEED certification?
Choose 3
- The project boundary must include all contiguous land that is associated with the project and supports its typical operation
- The project should be constructed and operated on a permanent location on existing land
- The project building should be a minimum of 1,000 sq ft
Which of the following project strategies would earn an exemplary performance point under IN Credit Innovation Option 3 Additional strategies?
Choose 2
- Attain 97% threshold for the project using Energy Star Portfolio Manager Tool
- Meet at least 10% of total energy use with onsite renewable energy
Which of the following resources should be used to identify RP credits for a project?
USGBC website RP credit library
Which of the following special considerations would be part of the LEED project scope?
Choose 2
- An off-site facility or amenity
- A shared facility that may be used by the project occupants
Which of the following variables affect LEED Certification cost?
Choose 3
- Time when the project team submits documentation for review in LEED Online
- Projects’s size
- Project’s rating system
The school project is planning to earn site development-protect and restore habitat credit. The team has identified a certified land trust who will be providing financial support to the project. How often should financial support be offered?
Annually
The total site for a retail project is 45,000 sq. ft. How much should be the minimum financial contribution to earn SS credit 1-site development?
$2,250
Within how many days of inspection should the maintenance, repairs and stabilization be done under SS Credit-Rainwater Management?
60 days
A hospital project has 2,500 sq. ft of total roof area, of which 300 sq. ft is covered by mechanical equipment’s, making a total applicable area 2,200 sq. ft. The following heat island mitigation strategies have been included in the project design: - 1,250 sq. ft vegetated roof - 950 sq. ft of high reflectance roof with a three-year aged SRI of 90 Can the hospital earn SS credit-heat island reduction?
Yes
The illumination level measured with the lights on must no be more than _______% above the level measured with lights off for light pollution reduction credit.
20%
Which of the following are required documents for SS prerequisite 1 - Site Management Policy?
Choose 2
- Justification for operational elements not included in policy
- Site Management Policy document
Which of the following Does Not employ best management practices for site management policy?
Choose 2
- Diverting waste to landfills
- Use of high emission maintenance equipment
Which of the following must be considered by projects attempting to earn Site Development-Protect & restore Open habitat in an urban area?
Diversity of roof top vegetation to support local wildlife
A school is planning to vegetate 3% of total site area. It has also implemented few capitol cost measures to improve the site. Can this school earn credit for exemplary performance under SS credit-Site improvement plan?
No
Which of the following defines maximum illuminance values for outdoor lighting zones?
IESNA RP-33
What percentage of non-roof hardscape must be covered with a heat island reduction strategy for projects to be eligible for credit?
50%
Which of the following is a strategy for complying with the requirements of Heat Island Reduction Non-Roof?
Provide shade with solar panels
Can a school project earn exemplary performance for SS credit-light pollution reduction by shielding all exterior fixtures in order to avoid emitting light at vertical angle more than 90 degree from straight down?
No
The project is planning to earn light pollution reduction credit using perimeter measurement option. How many measurements are required and with how much spacing between them?
8 Measurements, 100 ft spacing
How often must high-reflectance surfaces be cleaned to maintain their heat island reduction potential?
At least every 3 years
For projects with exterior lights over 50 watts, which of the following strategies must be taken to comply with the requirements of light pollution reduction
Provide either full or partial shield
A project site includes a flat roof. Given that mechanical equipment, photovoltaic panels, and skylights are excluded, an innovation in Operations point can be awarded for SS Credit Heat Island Reduction: Roof if:
95% of the project roof area is a green roof system
Which of the following is a strategy to reduce light pollution?
Minimize upward illumination
A projects roof must be covered at least _______ by vegetation for the project to earn Heat Island Reduction Roof
50%
Which of the following would help with the exterior lighting requirements of SS Credit Light Pollution Reduction?
Night illumination levels less than 20% above the level measured when the lights are off
Eight measurements is the minimum number required for what?
Light levels along the perimeter for compliance with light pollution reduction
Why is light pollution a problem?
It disrupts nocturnal ecosystems
What best defines open-grid pavement systems according to LEED for achieving SS Credit Heat Island Reduction - Non roof?
Pavement that is less than 50% impervious and accommodates vegetation in the open cells
What types of fixtures are exempt from the interior lighting requirements of SS Credit Light Pollution Reduction?
Choose 2
- Emergency lighting
- Desk lamp with a plug load
Under Site Development for on-site restoration. What is the minimum amount of native/adapted vegetation the side should have in-place to promote diversity?
5,000 sq ft
In order to earn exemplary performance under SS credit-Heat Island Reduction, a vegetated roof system is installed for 95% of the project’s roof area. Can mechanical equipment’s and PV panels be included in the calculation?
No
A retail store is planning to earn heat island reduction credit by using combination of roof and non-roof option. What should the minimum initial solar reflectance (SR) value for a low-sloped roof structure?
82
Which of the two referenced standards are related SS credit-Heat Island Reduction?
Choose 2
- ASTM Standards E903 and E892
- Cool Roof Rating Council Standard
The project is a 10 story building in suburbs of Denver. The total site area is 45,000 sq ft. The site has 5,000 sq ft of impervious area. How much water has to be captured and treated using GI and LID practices in order to earn exemplary performance under SS credit-rainwater management?
2,500 sq ft
The project has 4,000 sq ft of hardscape. The following heat island mitigation strategies have been included in the project design: - 400 sq ft with a three year aged SR of 0.30 - 600 sq ft of parking with initial SR of 0.34 - 1,200 sq ft of shading with tree canopy. Can the project earn SS credit-heat island reduction?
Yes
What should minimum percentage of parking located undercover to earn exemplary performance credit under SS Credit-Heat Island Reduction?
95%
A campus project has five buildings with landscape irrigation. The buildings get their potable water from public water supply. How many total meters are needed for the buildings and water sources to comply with WE Prerequisite Building Level Water Metering?
5
A mixed use building has restaurants on 1st floors and offices on 2nd and 3rd floors. Which of the following must be true when calculating indoor water use?
Calculate each occupant group separately
A project is using metering faucets. The project team member measured the flow in gallons (liters) per cycle (gpc, lpc). What should the project team do before performing indoor water use reduction calculations?
The flow rate must be converted to a flow rate in gallons (liters) per minute (gpm, lpm)
A project is using metering faucets. The project team member measured the flow in gallons (liters) per cycle (gpc, lpc). Convert 0.2 gpc metering faucet with 12 seconds cycles duration, yo calculate faucet flow rate?
0.2 gpc x 60 sc / 12 sc = 1 gpm
A project pursuing WE Outdoor Water Use Reduction credit using option 3 - Irrigation Meter Installed is able to demonstrate 50% reduction in outdoor water use over the most recent 12 months compared with the established baseline. How many points can the project earn?
2 points
A project team is performing the ASHRAE energy use analysis to comply with EA Prerequisite Energy Efficiency Best Management Practices. As part of the analysis, the team collected three years of utility bills and examined average and peak utility costs. Which of the following should the project team develop to establish a baseline for building performance?
Choose 3
- Energy use index
- Energy demand index
- Energy cost index
A school project in Iowa is pursuing WE Credit Cooling Tower Water Use. In addition to attaining a minimum number of cooling tower cycles, what the minimum percentage requirement for recycled non-potable water use in order to earn 3 points for a school project?
20%
An existing building project includes a building addition and the original building is not metered. Which of the following must be true in order for the building to earn LEED Certification?
The project needs to install meters to cover only the entirety of the addition’s energy use
How can a LEED O+M project share building - level watering data with USGBC? Choose 2
- Through Energy Star’s Portfolio Manager
- Through a third party data source
How many points can a retail project earn with 12% reduction in water use beyond the prerequisite level under WE Credit Indoor Water Use Reduction under option 2 metered water use?
3 points
How many points can a school project earn with 24% reduction in water use beyond the prerequisite level under WE Credit Indoor Water Use Reduction under option 1 calculated water use?
3 points
If an entire plumbing system was completed after 1994, A baseline water use of __________ is needed
120%
If sub-meters DO NOT exist or the project DOES NOT have 12 months of data, what should a project do in order to comply with WE Prerequisite Indoor Water Use Reduction - Option 2 metered water use?
The project team may choose to install sub-meters for 80% of fixtures OR begin recording data
In case of Indoor Water Use reduction, what is the existing buildings water use baseline for building with a certificate of occupancy dated 2000?
120%
In order to receive the maximum points for EA Credit Renewable Energy and Carbon Offsets what percent of energy consumed during the performance period must be renewable?
Points from renewable energy = (% Renewable energy) / 1.5% 5 X 1.5% = 7.5%
Meters installed to measure usage for water metering must be?
Permanently installed
The water efficiency credits can provide the most significant savings to:
Energy costs
What is a site’s water budget?
How the site expects to use water and when that water will be needed
What is the existing building water use baseline, for building with a certificate of occupancy dated 1950 in case of Indoor Water Use Reduction?
150%
What is the maximum establishment period beyond which the landscape should NOT be irrigated if the project pursue WE Credit Outdoor Water Use Reduction using Option 1. No irrigation Required?
2 years
What is the maximum number of points that a data center project can earn under indoor water use reduction credit excluding the exemplary performance?
4 points
What is the maximum points that a data center project can earn using cooling tower water use credit?
4 points
What is the minimum percentage reduction required to earn exemplary performance using metered water use option under WE credit indoor water use reduction?
25%
What plumbing fixture standard(s) will yield the greatest water savings for private lavatory and aerators?
EPA Water Sense Standard
What should be the minimum percentage of fixtures and fittings that need to be metered in order to comply with WE Prerequisite Indoor Water Use Reduction - Option 2 metered water used?
80%
What type of water should be avoided for makeup water?
Stormwater runoff from the ground surface
Which of the following are Non-Potable water sources that could be used for cooling tower?
- Drinking water
- Naturally occurring surface water
Which of the following can have a WaterSense label?
Choose 2
- Private lavatory faucets
- Water-using urinals
Which of the following credits under water efficiency has a potential to earn maximum number of points?
Indoor Water Use Reduction
Which of the following credits will benefit from ASHRAE level 1 energy audit?
MR Credit: Purchasing - Lamps
Which of the following does NOT need to be commissioned?
All interior finishes are installed after occupancy
Which of the following is true respect to metering water use for a project that has an addition to an existing facility to comply with WE Prerequisite Building Level Water Metering?
A single meter that covers both old and new portions of the building may be installed
Which of the following must be true for a project that decides to meter alternative water sources to comply with WE Prerequisite Indoor Water Use Reduction - Option 2 metered water use
The project team may choose to install submeters for 80% of fixtures OR begin recording data
Which of the following statements DOES NOT describes the requirements for water metering credit?
Must be owned by the utility or government
Which of the following water subsystems must have 100% of the source sub-metered for WE Credit Water Metering?
Choose 2
- Cooling towers
- Reclaimed water
Which of the following WE Credit has a potential to earn exemplary performance?
Indoor Water Use Reduction