Lecture Five Flashcards

1
Q

Present Value (PV) def

A

is the value today of a future value (or
cash flow)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PV for single cash flow formula

A

PV= C * DF
-df = discount fctor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

PV Annutiy formula

A

PV = C * AF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

PV perpuity formula

A

PV= C/r = C*1/r

-r is interest r

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

NPV stands for

A

Net Present Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

NPV defintion

A

Present value of the cash inflows minus the present
value of the cash outflows

-NPV is the sum of all cash inflows (money coming in) minus the sum of all cash outflows (money going out), adjusted for time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost of capital

A

The required annual rate of return on an
investment project.

A.k.a. discount rate, required rate of
return, hurdle rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why does npv matters

A

It tells us if an investment will make money or lose money.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

NPV decison rules

A

If NPV ≥ 0, accept the project (it will increase shareholder wealth).

If NPV < 0, reject the project (it will lose money).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what is npv based off

A

NPV is based on cash flows (not profits)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

another name for cost of capital

A

Discount rate
Required rate of return
Hurdle rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

how to know if projectis a good investment

A

If the NPV calculation shows a positive value after discounting with the cost of capital, the project is likely to be a good investment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what happens if the cost of capital is high

A

The higher the discount rate, the lower the present value of future cash flows.

This is why companies with high-risk investments require a higher cost of capital—because their money loses value faster over time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

npv formula

A

NPV= C/(1+r)^t - Co

C = cash flow in year t (money received or paid)

r = discount rate (cost of capital)

t = year number

C_0 = initial investment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

example question for npv:
A construction company is considering buying land and building houses.

Costs:
Land cost = $1 million
Construction cost = $3 million
Total initial investment = $4 million (at t=0)

Future cash inflow: The houses can be sold in one year for $5 million.

Cost of capital = 10%.

A

PV =5,000,000/(1.10)^1
=4,545,455

NPV= inflow+outflow
(-1,000,000)+(-3,000,000)+4,545,455(pv)

=545,455
.NPV is positive= the project is a good investment and should be accepted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Mutually Exclusive Projects

A

When you must choose only one investment out of multiple options.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

example of a mutually exclusive prokect

A

A company can open only one new store, either in Location A or Location B.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

what do u chose with a mutually exclusive project

A

Decision Rule: Choose the project with the highest NPV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Investment Timing Decisions def

A

Sometimes, you can delay an investment and start it later

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

example of an investment timing decision

A

A company needs a new IT system but can install it now or next year.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

key idea for investment timing decision

A

Even if you delay, you must discount all cash flows to time 0 (today) to compare fairly.

22
Q

decision rule for investment timing decision

A

Choose the option with the highest NPV at time 0.

23
Q

EAA Stands for

A

Equivalent Annual Annuity

24
Q

formula for EAA

25
descion rule for EAA
Decision Rule: Choose the equipment with the lowest EAA.
26
PP stands for
Payback Period
27
PP defintion
The time required for a project’s cash inflows to recover its initial investment.
28
PP formula
PP= initial investment/annual cash inflow
29
decison rule for pp
Decision Rule: Accept the project if PP < than the target payback period.
30
PP issues
Does not consider the time value of money . Ignores cash flows after the payback period. Not a reliable indicator for project selection. Provides no indicator as to the projects worth
31
DPP stands for
Discounted Payback Period
32
Discounted Payback Period def
Time for project PV of cash inflows = initial investment
33
discounted payback period dpp decison rule
Decision Rule: Accept if DPP is less than the target DPP
34
what would be accepted for dpp
projects with negative NPV would not be accepted as it would be impossible to compute a DPP.
35
negatives of dpp
Remains an unreliable indicator when choosing between projects and still fails to provide an indication of a project’s worth
36
IRR stands for
internal rate of return
37
irr meaning
The discount rate at which NPV = 0. OR IRR is the projects annual rate of retur
38
decison rule for IRR
If IRR > Cost of Capital, accept the project. -positive NPV If IRR < Cost of Capital, reject the project. -negative NPV
39
how are returns expressed
Returns are usually expressed as an annual % (but this doesn’t consider time value of money)
40
return equation
return%=profit/investment
41
Multiple IRRs:
If a project has both positive and negative cash flows, there can be more than one IRR.
42
Linear Interpolation for IRR Calculation: formula
IRR = A+(B-A)* NPV_A/NPV_A-NPV_B A = Discount rate used to find NPV_A B = Discount rate used to find NPV_B NPV_A AND NPV_B are the NPVs at respective discount rates.
43
what does IRR lead to
wealth maximisation
44
Capital Rationing
refers to a shortage of funds available for investment projects.
45
two types of capital rationing
soft and hard
46
Soft Capital Rationing –
Internal restrictions by management.
47
Hard Capital Rationing
External funding limits. due to an actual shortage of funds available for investment.
48
Profitability index
ensures the best ‘bang for the buck’ when investing
49
Profitability index formula
PI= NPV Project/Inital Investment
50
PI Decision rule
Choose projects with the highest PI. PI>0- proect is worthwhile
51
what is PI used in e.g
used to rank the projects when capital is rationed