Lecture 3 Flashcards
What is the basic formula for unit costs?
Unit cost = Total manufacturing cost/Total units produced
Whats the equation for predeterminded overhead rate (POHR) ?
POHR =
Estimated total manufacturing overhead cost for the coming period
Estimated total units in theallocation base for the coming period
whats the equation for overhead applied?
Overhead applied = POHR × Actual activity
Actual activity means the Actual amount of allocation base used to do overhead allocation (e.g., direct labour hours, machine hours)
what is over applied overhead?
Over-applied overhead (or over-absorbed overhead) occurs when the overhead cost recovered or applied (using a predetermined overhead cost rate) is greater than the actual overhead cost of the period.
what is over absorbed overhead?
Over-applied overhead (or over-absorbed overhead) occurs when the overhead cost recovered or applied (using a predetermined overhead cost rate) is greater than the actual overhead cost of the period.
what is under applied overhead?
Under-applied overhead (or under-absorbed overhead) occurs when the overhead cost recovered or applied (using a predetermined overhead cost rate) is less than the actual overhead cost of the period.
what is or under-absorbed overhead overhead?
Under-applied overhead (or under-absorbed overhead) occurs when the overhead cost recovered or applied (using a predetermined overhead cost rate) is less than the actual overhead cost of the period.