Lecture 3 Flashcards

1
Q

Project network is a flow chart that…

A

Depicts the sequence, interdependencies and start of finish times of project activities
Shows critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Aspects to consider when project planning (6)

A

Methods used to place the work
Skills needed for the work
Crafts involved
Critical activities
Administrative actions
Deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Scheduling is used to establish: (6)

A

Timing objectives
Sequence of activities
Cash flow requirements
Benchmarks
Basis for performance
Early warning system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What logical decisions can scheduling help us make? (4)

A

Continuation
Acceleration
Redirection
Changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are milestone schedules

A

Can be at the management level or project milestones

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What types of bar charts are there

A

Plan focus
Performance focus

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Plan focus bar chart

A

Created on a time line to show the schedule for starting, execution and completing each project item

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Work/performance focus bar chart

A

Graphical representation of actual performance towards completion
Shows percent complete of each item instead of time scale

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Steps of project scheduling (4)

A

Overall sequence of work
Sequential time diagram indicating order
Detailed planning and breakdown (resources, manpower needed, etc.)
Detailed and expanded project model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you choose activity duration?

A

Consult field personal
Depends on productivity, resources available, crew size
Determine minimum duration possible and how long an activity can be delayed without impacting minimum project length

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does ES stand for

A

Early start - earliest time a particular project can begin

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Bar chart pros

A

Easy to read
Shows major work activities
Clearly and quickly shows project progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Bar chart cons

A

Difficult to produce complex schedules
Typically no relationships shown

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What shape do we want of a graph showing resources per day/period

A

Relatively steady throughout project duration, ramps up at beginning and ramps down at the end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What do we want to avoid in cumulative s-curve graph?

A

Steep areas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Three ways to show critical path method CPN

A

Activity on arrows network
Activity on nodes network
Planning/project evaluation and review technique networks

17
Q

Activity

A

An element of the project that requires time

18
Q

Merge activity

A

An activity that depends on two or more preceding activities

19
Q

Parallel (concurrent) activities

A

Activities that can occur independently, and if desired at different times

20
Q

Path

A

Sequence of dependent, connected activities

21
Q

Critical path

A

The shortest expected time in which the entire project can be completed

22
Q

How to denote activity for an AOA diagram

A

The numbers on the nodes immediately preceding and coming after the activity

23
Q

AOA Mistake

A

Activities can’t both begin and end at the same nodes because they will have the same numbers for the identifier. Use a dummy node for one activity so that they have different identifiers

24
Q

Predecessor

A

A predecessor comes before a given activity

25
Q

Successors

A

Successors are the activities following a given activity

26
Q

Forward pass

A

Earliest times:
- ES early start, how soon can the activity start
- EF early finish, how soon can the activity finish

27
Q

Backward pass

A

Latest times
- LS late start, how late can it start
-LF late finish, how late can it finish

28
Q

Slack/Float

A

How long an activity can be delayed

29
Q

Total float

A

Total amount of time an activity can be delayed without causing an extension of the project duration
TF = LF - EF

30
Q

Free Float

A

Amount of time an activity can be delayed without affecting any subsequent activities’ early start times

31
Q

Interfering Float

A

Amount of total float utilized that interferes with the following activities
INTF = TF - FF

32
Q

Hammock activity

A

An activity that spans over a segment of a project
Duration is determined after the network plan is drawn
Used to aggregate sections of the project

33
Q

NTP

A

Notice to proceed
Pseudo dummy to show start of project when there’s more than one activity with no dependencies

34
Q

PC

A

Project completion
Pseudo dummy for end of project when there is more than one end point

35
Q

Optimistic duration

A

All conditions are favorable

36
Q

Most likely duration

A

What the most likely duration is

37
Q

Pessimistic duration

A

All conditions are unfavourable

38
Q

Quality assurance vs control

A

Assurance is evaluating as a part of the project is ongoing to make sure once it’s done it will meet standards while control is evaluating a part of the project once it is completed to make sure it meets standards