Lecture 1 Flashcards

1
Q

What is Slippage

A

risk of not doing things on time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the responsibilities?

A

Project Board, Board members providing senior insight, Manage project managers

Day to day basis, Operational. Role of a project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a reporting Hierarchy

A

Tell someone what you have been doing, communication.

Bottom, Doing majority of the work
Next..
They report to the team leader.

Team leaders report to a project manager.

Project manager reports to the board

Board reports to client

Reporting increases from Board to Workers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

An Alternative View (Scrum)

A

No Pyramid structure in a Scrum Team.

Product Owner- Vision and Knowledge

Scrum Master- Scrum master leads the team, their specialisim is the process and not the project.

Development team- different experts working together

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do we monitor?

A

Checkpoints

Ensure that products are compatible, they support project monitoring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Two Type of Checkpoints

A

Event Driven: Check takes place when a particular event has been Achieved

Time Driven Checkpoint: date of check is predetermined in between different sprints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Collecting progress details

A

Dealing with partial completions is a problem

Estimates are effected by the 99% completion Syndrome

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Using Gantt Charts to track project process

A

shows you where you are right now

if you have a monthly Gantt chart, it is more realistic Shade activity bars to reflect reported progress by adding today cursor you can indicate expected process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Limitations Of Gantt Charts

A

Only give us a snap shot of right now
to overcome this have multiple Gantt charts

they don’t allow analysis of project trends

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Timeline Representation

A

P.g 102, 11/11/24

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cost Monitoring

A

cost monitoring is an important concept of project control in itself but also as an
- indicator of the effort that has gone into the project

-A project could be late due to staff originally commited have not been deployed, but will still be under budget

-A project could be on time but because additional resources have been added so could be over budget

-Needs to be monitoring of achievements and costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Partly completed Task

A

0/100 technique:
-the earned value of a task is 0 until completed then will be 100%

-50/50 half of the planned Value is allocated at the start and the other half is on completion

the milestone Technique:
-the earned value of a task is the planned value of the last milestone achieved.

the percentage technique
-works only if there is a means of assessing the percentage of the task that was completed (what percentage of 500 data records have been manually typed intoa database.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Earned Value approach

A
  • popular approach to cost monitoring
  • each task is assigned a value based on original cost estimate, could be cost or effort
  • attribute of a task is termed the task planned value

Earned Value, calculated based on state of task:

  • A task which work has not started has an earned value of zero
  • A completed task has an earned value equal to the planned value
    -The earned valuenof a project is the sum of the earned values for all its tasks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Exception Planning

A

The project manager typically allwed ti change project plan as long as the agreed project outcomes are produced on time without budget…

However changes to… Delivery date, scope or cost of project can affect users

in these cases and exception report is needed
- written by the product manager to explain the reasons that justify such a deviation from the existing plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

An alternative view (Scrum)

A

Positive:
No documentation, save time
Negative:
No Documentation, High turnover, lack of communication

Product backlog and sprint backlog

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Prioritising Monitoring

A

Monitoring takes time and uses resources, should be applied with different levels of detail effort

want to focus on monitoring critical path activities
Activities with no free float, if delated later dependant activities, not whole project
Activities with less than a specified amount of float

13
Q

Getting the project back on track, Options?

A

Most projects experience experience

-renegotiate deadline, reduce chance of repeat business
-Shorten the critical path
-reconsider activity dependencies
-Overlap activates, split activities.

14
Q
A
14
Q
A
14
Q
A
15
Q
A
16
Q
A