Lean Proj. Mgmt Flashcards

1
Q

What is Supply Chain Management?

A

Supply Chain Management (SCM) is the practice of a group of companies and individuals working [collaboratively] in a network of [relationships] structured to optimize the supply chain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

2 ways to optimize the supply system

A

(1) Reliable and (2) Economic supply chain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Typical SCM Practices

A
  1. Rebar Supply Chain
  2. Façade (e.g., Curtain Wall) Supply Chain
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Rebar Supply Chain

A

[a] Select a low-bid supplier

[b] Order in a bulk (e.g. 20 days supply)

[c] A supplier not involved in a contractor’s schedule

[d] Inventory on site for 20-30 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • Façade (e.g., Curtain Wall) Supply Chain
A

[a] Select a low-bid supplier

[b] A supplier not involved in a contractor’s schedule

[c] A contractor frequently changes its delivery schedule

[d] A supplier’s holding excessive inventory

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Is inventory good or bad? Why?

A

(Answer varies: Good for availability, bad for cost/storage waste.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why does the contractor frequently change delivery schedules in the façade supply system?

A

(Answer: Lack of plan reliability/order variability.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Relationship Between Contractor and Supplier

A

Can be

[1] Competitive (bidding focus)

or

[2] Partnership (collaborative focus).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Supply Chain Coordination/Integration Types

A

[A] Merge & Acquisition (Hierarchical)

[B] Long-Term Alliance (Collaborative: Network/Licensing, Single-Sourcing, Preferred Suppliers)

[C] Contract Coordination (Competitive).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Supply Chain Coordination Problems

A

[Contractual] Risks of order variability transferred to supplier.

[Production] Contractor’s lack of plan reliability causes order variability; less

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Types of Construction Materials

A

[1] Bulk Material (standard, purchased in quantity)

[2] MTO (Make-to-Order, e.g., chiller, catalog-specified)

[3] ETO (Engineered-to-Order, e.g., rebar, requires engineering).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Factors in Material Management

A

[1] Supplier’s lead time (length & reliability: Engineering + Fabrication + Shipment + Waiting)

[2] Planning reliability (probability of changing order)

[3] Storage area size.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Push System

A

Schedules work release based on demand prediction (predetermined schedule). Example: BBQ platter as the only menu.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

PULL System

A

Authorizes work release based on system status (triggered by internal customer demand). Prevents overproduction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Bulk Material Planning Tips

A

Purchased in uniform lots, no shop drawings required, needs a safety level of inventory.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Kanban & Pull

A

A replenishment system to control production quantities. Parts are taken/replenished only when needed and in the right amount.

17
Q

Kanban Strategy Benefit

A

Prevents overproduction while maintaining a tightly-bound inventory between supplier and customer processes.

18
Q

ETO Product Planning Tips

A

Requires shop drawings (submittal). Examples: rebar, curtain wall. Lead time = Engineering + Fabrication + Shipment.

19
Q

ETO Order Release

A

[1] Engineering Order = Shop Drawing (Eng) [2] Delivery Order = Fabrication + Delivery.

20
Q

Pull in Supply Chain (Delivery Order)

A

Involves

[1] Reliable Short-term Planning (RSP)

[2] Adaptive Production Schedule (APS)

[3] Supply Chain Coordination. Updated via Supply Chain Platform.

21
Q

Mechanics/Requirements for Pull

A

Lead time < Look-ahead Window. Strategies:

[1] Decrease supplier lead time

[2] Increase reliable look-ahead window.