Components and Functions - what constitutes the contract documents?

A

The agreement.
Drawings.
Specifications.
Addenda (Changes issued prior to the bid).
Modifications (changes issued after the bid).
Any documents incorporated by reference.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Developing Contract Documents for a Project

A

Standard forms: AIA, CMAA, other organizations forms.
Customized forms: County government.
Combination of both.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Standard Form Contracts - Advantages

A

Increase the predictability of project outcomes.
Increase the consistency of pricing.
Simplify management.
Regularly updated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Standard Form Contracts - Most Common

A

AIA - American Institute of Architects.
AGC - Associated General Contractors.
CMAA - Construction Management Assoc. of America.
DBIA - Design Build Institute of America.
Owner specifc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Standard Form Modifications - When making modifications consider:

A

Seeking advice of legal counsel.
Assuring modifications are properly coordinated with other project documents.
Thinking ahead: How will modifications be received?
Placing responsibility and authority with the party best able to perform duties and control the risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CMAA Contracts - intent to provide documents that:

A

Provide contractually specified duties.
Avoid concurrent or undefined responsibilities.
Minimize conflicts between the CM, designer and contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CMAA Contracts: Agency (A) Series

A

Document A-1: Agreement between owner and CM.
Document A-2: Agreement between owner and Contractor.
Document A-3: General conditions of the contract.
Document A-4: Agreement between owner and Designer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CMAA Contracts: CM at Risk (CMAR) Series

A

Document CMAR-1: Agreement between owner and CM.
Document CMAR-2: Agreement between CM and Contractor.
Document CMAR-3: General conditions of the contract.
Document CMAR-4: Agreement between owner and Designer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

AIA Contracts Comparable to CMAA Agency Series

A

A101-2007: Owner and Contractor
A201-2007: General Conditions
B132-2009: Owner and architect; Cm as agent of the owner.
C132-2009: Owner and CM as agent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

AIA Contracts Comparable to CMAA CM at Risk Series

A

B132-2009

A132-2009

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

CMAA and AIA Agency Contract comparison (CMAA A1-A4 vs. AIAB141,B801)

A

= 1 or more construction contracts
= Designer handles design
- CM is the owner’s principal agent / designer is the owner’s principal agent
- CM handles contract Admin / Designer handles contract Admin

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

CMAA Agency Series Key Points 1 of 2

A

The CM is employed prior to the designer.
CM is owner’s principal agent.
CM helps select the designers.
CM and designer agree to cooperate.
CM does a PM plan.
CM and designer can rely on each others work, products and services.
Owner approves the plan, designer may comment or suggest revisions.
CM prepares cost estimates of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

CMAA Agency Series Key Points 2 of 2

A

Designer has sole responsibility for design and specifications for materials/equipment.
Designer’s basic services during construction are relatively limited.
The CM determines the contractor’s compliance with the contract docs.
Designers additional services: site visits, review of progress payments, design change.
CM approves contractor’s request for payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

CMAA CM at Risk CMAR 1-4

A

CM’s extensive professional services during design.
Self-performed work only if low bid>owner approves>separate GMP contract is signed.
Owner may reject GMP, CM may contnue as agent.
Owner may require additional services after GMP is signed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

AIA CM at Risk AIAB141, B121

A

CM’s limited professional services during design.
CM may self-perform work at their own discretion without submitting bids.
No option for owner to reject GMP and continue CM’s services.
No option for owner to require additional services after GMP is signed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

CMAA CMAR Series Key Points

A

Prior to GMP, the CM functions as the agent of the
owner.
If owner accepts the GMP:
-CM assumes role of contractor
-CM is responsible for the project.
-CM must bid (and be low bidder) on work to be self-performed, must sign separate contract.
-The project team concept is to be maintained.
If owner rejects the GMP the owner can:
-Terminate the contract “for convenience”.
-Continues with the designer and CM as agents, has to modify the agreements.
-Procure construction services through a re-bid (or negotiation) of the work to third parties.

17
Q

Detailed contents of CMAA Agency Series General Conditions

A

Inspection, testing, and rejection of non-conforming work.
Provide a vehicle for making changes to the contract price and time.
Insurance requirements for the contractor and owner.
Avenues for contract termination: convenience, default.
Defining a mechanism for dispute resolution.
Responsibilities of the owner, CM, designer, contractor.
Site safety.
Monitoring time and progress of the work.
Responsibilities/duties to subcontractors and suppliers.
Owner’s right to perform work / issue separate contracts.
Procedures for progress payments, withholding payments, and issuing final payment.