L1: CONSTRUCTION ESTIMATES Flashcards

1
Q

It is the approximation of the
cost of a program, project, or operation.

A

Cost Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

It is the product of the cost estimating process.

A

Cost Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

It has a single total value and may have identifiable component values

A

Cost Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

It is the process of forecasting the costs of building a structure.

A

Estimation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Costs and expenses that are
accountable directly for a specific
activity in construction work.

A

Direct Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

These are expenses of items that are not allocated directly for specific construction activities.

A

Indirect Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the examples of Indirect costs?

A
  1. Quality control
  2. Security costs
  3. Utilities
  4. Administrative costs
  5. Temporary structures
  6. Legal fees and permits
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the basic approaches in Construction estimates?

A
  1. Production of Function
  2. Empirical Cost Inference
  3. Unit Costs for Bill of Quantities
  4. Allocation of Joint Costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In microeconomics, the relationship
between the output of a process and the
necessary resources is referred to as?

A

Production of Function

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

It requires statistical techniques which relate the cost of constructing or operating a facility
to a few important characteristics or attributes of the system.

A

Empirical Cost Inference

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A unit cost is assigned to each of the facility components or tasks as represented by the bill of quantities.

A

Unit Costs for Bill of Quantities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Allocations of cost from existing
accounts may be used to develop a
cost function of an operation.

A

Allocation of Joint Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the types Construction Cost Estimates?

A
  1. Design Estimates
  2. Bid Estimates
  3. Control Estimates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In preparing these estimates, the design professional will include expected amounts for
contractors’ overhead and profits.

A

Design Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Types of cost estimates encountered run parallel with the planning and design.

A
  1. Screening estimates or order of magnitude estimates
  2. Preliminary estimates or conceptual estimates
  3. Detailed estimates or definitive estimates
  4. Engineer’s estimates based on plans and
    specifications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Usually made before the facility is
designed, and must therefore rely on
the cost data of similar facilities built in
the past

A

Screening Estimate or Order of Magnitude Estimate

17
Q

Based on the conceptual design of the facility at the state when the basic technologies for the design are known

A

Preliminary Estimate or Conceptual Estimate

18
Q

Made when the scope of work is clearly defined and the detailed design is in progress so that the essential features of the facility are identifiable.

A

Detailed Estimate or Definitive Estimate

19
Q

Based on the completed plans and
specifications when they are ready for
the owner to solicit bids from
construction contractors.

A

Engineer’s Estimate

20
Q

Often reflect the desire of the contractor to secure the job as well as the estimating tools at its disposal

A

Bid Estimates

21
Q

Bid Estimates include?

A
  1. Subcontractor quotations
  2. Quantity takeoffs
  3. Construction procedures
22
Q

Refer to the price estimates provided
by subcontractors for specific parts of a
construction project.

A

Subcontractor Quotations

23
Q

Crucial process in the construction
industry that involves quantifying
the materials, equipment, and
labor required for a project.

A

Quantity Takeoffs

24
Q

The contractor may want to assess the actual cost of construction by considering the actual construction procedures to be used and the
associated costs if the project is deemed to be different from typical designs.

A

Construction Procedures

25
Both the owner and the contractor must adopt some base line for cost control during the construction.
Control Estimates
26
Control Estimate is derived from?
1. Budget estimate for financing 2. Budgeted cost after contracting but prior to construction 3. Estimated cost to completion during the progress of construction
27
Principles of Concrete Mixing
1. Workability 2. Strength 3. Durability 4. Economy
28
Proportioning concrete mixture is done in two different ways, such as?
1. Weight Method 2. Volume Method
29
Estimating materials for Post and Footing can be done through?
1. Volume Method 2. Area and Linear Meter Method combined for post and footing
30
It is the unit of measure used in computing the volume of lumber.
Board foot
31
One board foot simply means, one square foot by width and thickness of commercial lumber or an equivalent of ?
144 cubic inches
32
In determining the materials for square and rectangular column forms, one has to consider the following:
1. Thickness of the board to be used. 2. Size of the frame 3. Types of frameworks to be adopted