Key Lists Flashcards
Tender Report sections?
Tender Background;
Tender Returns;
Tender Analysis (high level);
Tender Scores
Recommendation
Appendices: -
Tender Analysis (detailed);
Tender Comparison;
Quality Matrix;
Post Tender Clarifications Log.
Cost Report sections?
a) Executive Summary (inc Key Report Analysis - CSUM; pay to date; AFA..)
o b) Authorised Expenditure
o c) Summary table of costs
o d) PSUMs and Contingency
o e) Instructions
o e) Anticipated Instructions
o f) Claims/Anticipated Claims (inc EoT costs)
g) Cash Flow Forecast
Order of Cost Estimate sections?
Constituents of an order of cost estimate
The key constituents of an order of cost estimate are shown in Table 2.1.
# Constituent Cross reference
1 Facilitating works estimate See section 2.5
2 Building works estimate See section 2.6
3 Main contractor’s preliminaries estimate See section 2.11
4 Subtotal = 1 + 2 + 3
5 Main contractor’s overheads and profit estimate See section 2.12
6 Works cost estimate = 4 + 5
7 Project and design team fees estimate = 7a + 7b + 7c, where:
* 7a = consultant’s fees
* 7b = main contractor’s pre-construction fee estimate (if
applicable) and
* 7c = main contractor’s design fees estimate (if applicable.
See section 2.13
8 Subtotal = 6 + 7
9 Other project costs estimate See section 2.14
10 Base cost estimate = 8 + 9
11 Risk allowances estimate = 11a + 11b + 11c + 11d, where:
* 11a = design development risks estimate
* 11b = construction risks estimate
* 11c = employer change risks estimate and
* 11d = employer other risks estimate.
See section 2.15
12 Cost limit (excluding inflation) = 10 + 11
13 Tender inflation estimate See section 2.16
14 Cost limit (excluding construction inflation) = 12 + 13
15 Construction inflation estimate See section 2.16
16 Cost limit (including inflation) = 14 + 15
17 VAT assessment See section 2.17
Cost Plan sections? (Document and Breakdown of costs)
The Report: (taken from Ridge template)
-Executive Summary (concise high level presentation)
-Introduction and background (brief, previous, further considerations)
-Design Basis of Report (info, drawings, used)
-Financial Basis of Report (NRM, cost sources, risks)
-Schedule of Accommodation (rooms and GIFA areas)
-Exclusions and Qualifications (lists)
-Estimate of Project Costs
-Documents Register
Name the main elements of an elemental estimate (taken from Ridge template):
*Facilitating Works
* Substructure:
o Excavation.
o Disposal.
o Foundations.
* Superstructure:
o Frame.
o Upper floors.
o External walls.
o Roof.
* Internal finishes.
* FFE
*Services.
*Complete Buildings and Building Units
*Works to Existing Buildings
*External works.
*Statutory Services
*Preliminaries
*OHP
*Project and Design Team Fees
*Other Development and Project Costs
*Risks
*Inflation
*VAT (excluded)
What is usually excluded from a cost estimate? [COST OF CONSTRUCTION ONLY WORKS?] - ‘Works Cost Estimate’]
* Professional fees.
* VAT.
* Client decant costs.
* Loose fixtures and fittings.?????
* Inflation.
* Site acquisition costs.
* Section 106 Agreement.
* Removal of asbestos.
Briefing Items? (this is worked up between client and consultant with a resulting scope of works and cost limit defined ie finalised on completion of RIBA Stage 1) (think of a BCIS Cost Model)
Building Location.
* The type of building.
* Floor area or number of functional units.
* Storey height.
* Whether raised access floors or deep suspended ceiling are envisaged.
* Initial floor plans, roof plans, elevations and sections.
* Requirements for refurbishment to existing buildings and enabling works.
* Indication of specification and quality.
* Indicative programme, procurement and contract strategy.
* Budget & cashflow constraints.
* Site conditions, probable ground conditions.
* Indicative M&E design intent, availability of utility services and the sustainability strategy.
* Details of professional fees, development costs, VAT and treatment of inflation.
Tender Pack documents?
In accordance with JCT practice note 2017 I would include:-
o ITT (Invitation to tender letter)
o Instruction to tenderers with:-
The date and time for return, to whom, site visits, programme, errors procedures,
scoring matrix.
Conditions of proposed contract.[preliminaries document?]
Pricing documentation.
Specifications.
Drawings.
Employers requirements.[further info on the works? further info on working conditions? further info on standards? CDP requirements?- ie FEEDS INTO PRELIMINARIES DOCUMENT, CDP??]
Pre-construction H&S information.
Form of tender.
Contract Pack documents?
JCT Contract and Amendments Document
Contractor’s Proposals
Qualitative Submission
Clarifications and Adjustments
Priced Document/Contract Sum Analysis
Contract Drawings and Specifications (tender doc)
Employer’s Requirements (tender doc)
Client Working Policies (tender doc)
Pre-Construction Information (tender doc)
CDP Requirements (tender doc)
Preliminaries document (tender doc)
Schedule of Payments Doc?
Valuation date (this is the date in Particulars - date for contractor submission)
Due date (7 days later)
Date of Certificate (5 days later)
Date for final payment (14 days later if not amended)
Pay less notice date (at least 5 days before payment date)
Set out in a monthly basis
Valuation Submission/Assessment doc?
- Summary of Valuation (gross costs; previous costs; previous payment; retention; net recommended payment)
*Preliminaries.
*PSUMS/Contingency/Dayworks
* Measured work.
*Advance Payments?
* Materials on site.
* Materials off site.
*Variations
* Claims/Loss and expense.
Final Account List of items?
As Valuation Submission ie:
- Summary (gross costs; previous costs; previous payment; retention; net recommended payment)
*Preliminaries. - Measured work.
- Variations.
- Materials on site. - NO!!!
- Materials off site. - NO!!!
- Claims/Loss and expense.
L&E claim items? (heads of claim)
Checking costs?
Heads of Claim:
P - expense
T - expense
U - loss
I - expense
O - expense
P - loss
F - expense
A - expense
C - expense
Checking Costs [OH STAFF]:
Timesheets
Staff grades and rates
Project codes? [correct project?]
Payroll burden
—Hudson formula—
Site Works:
Invoices
Subcontract accounts
Applications and payments
Materials invoices
Dates
Rates [???]
Quants
Delivery tickets
etc
L&E claim items? (Heads of Claim)
Prolongation.
* Thickening of preliminaries for example extra supervision required due to variations.
* Disruption causing plant or labour to be underemployed.
* Increases in labour or material costs during the period of delay.
* Head office overheads.
* Loss of profit.
* Finance charges.
* Acceleration costs.
* Claim preparation costs.
Variations submission items?
Breakdown: alterations or modifications to:
-design
-quality
-quantity
-access/working conditions
Additions/omissions (of works)
Additions/omissions (of costs)
[Additions (L&E and EoT) - this will be separate!]
Basis of costs (contract rates, adjustment to rates, quotations, dayworks)
OHP
Risk Register format?
A risk register format will typically include:-
o 1) A description of the risk.
o 2) The risk owner.
o 3) A probability of occurrence.
o 4) The impact of its occurrence (£/wks).
o 5) Risk factors (probability x impact). [EMV? expected monetary value?]
o 6) Actions required.[eg accept, reduce, etc]
o 7) Review date.
o 8) Status (open or closed).
Pricing Document sections? (Before work starts, so does not contain variations, claims, materials on or off site, etc)
Basis and Conditions of Pricing Doc
Preliminary costs
Provisional Sums, Prime Costs, and Contingencies (also including Dayworks sections)
Measured Works
Summary of Costs
Preliminaries (contract document) sections?
Condensed:
DESCRIPTION OF THE WORKS, CONTRACT, AND TENDERING PROCESS:
Project particulars (high level-name, works required, team members, etc)
The site
The works
[workmanship?]
Tender procedure
Contract details
Supply chain
CARRYING OUT THE WORKS:
Management of works
Quality of works
Security
Limitations on carrying out works
Facilitation requirements eg utilities
PREPARATION FOR HANDOVER:
Requirements to enable operation and future maintenance.
A10 Project particulars
A11 Tender and contract documents
A12 The site/ existing buildings
A13 Description of the work
A20 JCT minor works building contract with contractor’s design (MWD)
A30 Tendering/ subletting/ supply
A31 Provision, content and use of documents
A32 Management of the works
A33 Quality standards/ control
A34 Security/ safety/ protection
A35 Specific limitations on method/ sequence/ timing
A36 Facilities/ temporary work/ services
A37 Operation/ maintenance of the finished works
Preliminaries items? (pricing doc)
list of items: staff; welfare provisions; site offices; plant; site waste clearance; water; electricity; furniture; ICT; consumables; rates; protection fo work; clothing; site transport; setting out; building control fees; …insurances, bonds, …
What information is required to measure preliminaries? FOR ESTIMATING!! [site, management, contract, costs] [information that would identified directly from the contract document when filled out ie RACacs?]
Contract duration.
* Location.
* Type of project (New Build vs. Refurb).
* The size of the project.
* Temporary works.
* Employers accommodation.
- Security.
- Methodology.
- Programme.
- Services.
- Contractor designed work.
- Sectional completion.
- Insurances / Bonds.
ITT contents?
Condensed (OVERVIEW OF):
PROJECT, TENDER DOCUMENTATION, CONTRACT:
Project title and where
Statement of ‘invited..’
List docs to be based on
Proposed contract
TENDERING PROCESS AND CONDITIONS:
Submit by: date, FOT, docs requested
Price/Quality scoring
Queries addressed to.
Confidentiality/Collusion
Processes accordance JCT Practice
RESERVATION OF RIGHTS
After award
Reserve right: postpone/accept any or no tender
No tender expenses to claim
Signature
To; Project Title; Works Location
Invited to tender on the basis of…(list of documents/drawings/etc)
Accordance with contract
Submit using the FoT and by closing date
Submit documents requested
Queries addressed to….
Basis of assessment (price/quality)
Confidentiality
After award - will list tenderers
Procedure conducted in accordance with JCT Tendering Practice Note 2017
Reserve right to postpone closing date and accept ANY TENDER or NO TENDER AT ALL.
No tendering expenses will be payable.
SIGNATURE
FoT contents?
Condensed
Formal statement, confirming project and documentation, will carry out works as stated in the tender docs for sum and programme period, when start, how long offer open for.
Project Title
Tender from and to
Documents identified in ITT have been examined
Offer (tender sum; within…; programme duration)
Adjustment rule
Parent company guarantee statement
Will execute contract within…days
Signature, position, date
JCT Contract Sections?
What are the main parts of the JCT contracts?
* Recitals.
* Articles.
* Contract Particulars.
* Attestation.
* Conditions divided into 9 sections (7 for minor works - no Variations; Assigment…)
* Schedules.
Name the 9 sections
* Definition and interpretation.
* Carrying out the works.
* Control of the works.
* Payment.
* Variations.
- Injury, damage and insurance.
- Assignment, Third Party Rights and collateral Warranties.
- Termination.
- Settlement of disputes.
CDP ER contents?
Function, quality, size, location
Design reqs; spec requirements; performance requirements
Prime Cost item allowances?
Supplier quote figure (supply only or install as well?)
Attendances (or installation if supply only)
OHP
Examples of Defined PSUMs?
Below seems to be good definitions all round:
Defined Provisional Sums in a JCT contract typically cover ANTICIPATED COSTS for items with uncertain quantities or specifications at the contract stage.
Examples include
- allowances for client-selected items yet to be finalized, or
- provisional quantities for variations expected during construction.
Examples of Undefined PSUMs?
- groundworks for unforeseen conditions,
…..
Examples of CDP items?
SPECIALISED DESIGN elements not fully specified in the employer’s requirements, such as
- bespoke finishes,
- structural modifications,
- mechanical and electrical systems design, and
- temporary works.
NRM1 contents? (for work breakdowns - OoCE and cost plans are same, but cost plans have greater breakdown levels)
The key sections of NRM1 are:
o Part 1: General introduction explaining the purpose of the document and how it should be
used.
o Part 2: Measurement rules for the production of order of cost estimates.
o Part 3: Measurement rules for the production of elemental cost plans.
o Part 4: Tabulated rules of measurement for elemental cost planning.
o Appendices: With references to the definitions for GIA, functional units, NIA, elemental
breakdowns, templates and general information required for cost plan production.