Key Definitions Flashcards

1
Q

Acceptance Criteria

A

A set of conditions that is required to be met before deliverables are accepted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Accepted Deliverables

A

Products, results, or capabilities produced by a project and validated by the project customer or sponsors as meeting their specified acceptance criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Accuracy

A

Within the quality management system, accuracy is an assessment of correctness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Acquire Resources

A

The process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Acquisition

A

Obtaining human and material resources necessary to perform project activities. Acquisition implies a cost of resources, and is not necessarily financial

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Activity

A

A distinct, scheduled portion of work performed during the course of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Activity Attributes

A

Multiple attributes associated with each schedule activity that can be included within the activity list. Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Activity Duration

A

The time in calendar units between the start and finish of a schedule activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Activity Duration Estimates

A

The quantitative assessments of the likely number of time periods that are required to complete and activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Activity List

A

A document tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Activity-on-Node (AON)

A

See: Precedence Diagramming Method (PDM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Actual Cost (AC)

A

The realized cost incurred for the work performed on an activity during a specific time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Actual Duration

A

The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule is the schedule activity is in progress or the actual finish date if the schedule activity is complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Adaptive Life Cycle

A

A project life cycle that is iterative or incremental

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Affinity Diagrams

A

A technique that allows large numbers of ideas to be classified into groups for review and analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Agreements

A

Any document or communication that defines the initial intentions of a project. This can take the form of a contract, memorandum of understanding (MOU), letters of agreement, verbal agreements, email, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Alternative Analysis

A

A technique used to evaluate identified options in order to select the options or approaches to use
to execute and perform the work of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Analogous Estimating

A

A technique for estimating the duration or cost of an activity or a project using historical data
from a similar activity or project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Analytical Techniques

A

Various techniques used to evaluate, analyze, or forecast potential outcomes based on possible
variations of project or environmental variables and their relationships with other variables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Assumption

A

A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Assumption Log

A

A project document used to record all assumptions and constraints throughout the project life cycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Attribute Spending

A

Method of measuring quality that consists of noting the presence (or absence) of some characteristic
(attribute) in each of the units under consideration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Authority

A

The right to apply project resources, expend funds, make decisions, or give approvals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Backward Pass

A

A critical path method technique for calculating the late start and late finish dates by working backward
through the schedule model from the project end date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Bar Chart

A

A graphic display of schedule-related information. In the typical bar chart, schedule activities or work
breakdown structure components are listed down the left side of the chart, dates are shown across the top, and activity
durations are shown as date-placed horizontal bars. See also Gantt chart.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Baseline

A

The approved version of a work product that can be changed only through formal change control procedures
and is used as a basis for comparison to actual results.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Basis of Estimates

A

Supporting documentation outlining the details used in establishing project estimates such as
assumptions, constraints, level of detail, ranges, and confidence levels.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Benchmarking

A

Benchmarking is the comparison of actual or planned products, processes, and practices to those
of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for
measuring performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Benefits Management Plan

A

The documented explanation defining the processes for creating, maximizing, and
sustaining the benefits provided by a project or program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Bid Documents

A

All documents used to solicit information, quotations, or proposals from prospective sellers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Bidder Conference

A

The meetings with prospective sellers prior to the preparation of a bid or proposal to ensure all
prospective vendors have a clear and common understanding of the procurement. Also known as contractor conferences,
vendor conferences, or pre-bid conferences.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Bottom-Up Estimating

A

A method of estimating project duration or cost by aggregating the estimates of the lower-level
components of the work breakdown structure (WBS).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Budget

A

The approved estimate for the project or any work breakdown structure component or any schedule activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Budget at Completion (BAC)

A

The sum of all budgets established for the work to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Buffer

A

See “Reserve” Definition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Business Case

A

A documented economic feasibility study used to establish validity of the benefits of a selected
component lacking sufficient definition and that is used as a basis for the authorization of further project
management activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Business Value

A

The net quantifiable benefit derived from a business endeavor. The benefit may be tangible,
intangible, or both.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Cause and Effect Diagram

A

A decomposition technique that helps trace an undesirable effect back to its root cause.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Change

A

A modification to any formally controlled deliverable, project management plan component, or project document

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Change Control

A

process whereby modifications to documents, deliverables, or baselines associated with the project
are identified, documented, approved, or rejected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Change Control Board (CCB)

A

A formally chartered group responsible for reviewing, evaluating, approving, delaying,
or rejecting changes to the project, and for recording and communicating such decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Change Control System

A

A set of procedures that describes how modifications to the project deliverables and
documentation are managed and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Change Control Tools

A

Manual or automated tools to assist with change and/or configuration management.
At a minimum, the tools should support the activities of the CCB

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Change Log

A

A comprehensive list of changes submitted during the project and their current status.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Change Management Plan

A

A component of the project management plan that establishes the change control board,
documents the extent of its authority, and describes how the change control system will be implemented

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Change Request

A

A formal proposal to modify a document, deliverable, or baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Checklist Analysis

A

A technique for systematically reviewing materials using a list for accuracy and completeness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Checksheets

A

A tally sheet that can be used as a checklist when gathering data.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Claim

A

A request, demand, or assertion of rights by a seller against a buyer, or vice versa, for consideration, compensation,
or payment under the terms of a legally binding contract, such as for a disputed change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Claims Administration

A

The process of processing, adjudicating, and communicating contract claims

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Close Project or Phase

A

The process of finalizing all activities for the project, phase, or contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Closing Process Group

A

The process(es) performed to formally complete or close a project, phase, or contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Code of Accounts

A

A numbering system used to uniquely identify each component of the work breakdown
structure (WBS).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Collect Requirements

A

The process of determining, documenting, and managing stakeholder needs and requirements
to meet project objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Colocation

A

An organizational placement strategy where the project team members are physically located close to one
another in order to improve communication, working relationships, and productivity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Communication Methods

A

A systematic procedure, technique, or process used to transfer information among project
stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Communication Models

A

A description, analogy, or schematic used to represent how the communication process will
be performed for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Communication Requirements Analysis

A

An analytical technique to determine the information needs of the project
stakeholders through interviews, workshops, study of lessons learned from previous projects, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Communications Management Plan

A

A component of the project, program, or portfolio management plan that
describes how, when, and by whom information about the project will be administered and disseminated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Communication Styles Assessment

A

technique to identify the preferred communication method, format, and content
for stakeholders for planned communication activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Communication Technology

A

Specific tools, systems, computer programs, etc., used to transfer information among
project stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

Conduct Procurements

A

The process of obtaining seller responses, selecting a seller, and awarding a contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

Configuration Management Plan

A

A component of the project management plan that describes how to identify and
account for project artifacts under configuration control, and how to record and report changes to them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

Configuration Management System

A

A collection of procedures used to track project artifacts and monitor and control
changes to these artifacts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Conformance

A

Within the quality management system, conformance is a general concept of delivering results that fall
within the limits that define acceptable variation for a quality requirement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Constraint

A

A limiting factor that affects the execution of a project, program, portfolio, or process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Context Diagrams

A

A visual depiction of the product scope showing a business system (process, equipment, computer
system, etc.), and how people and other systems (actors) interact with it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Contingency

A

An event or occurrence that could affect the execution of the project that may be accounted for with
a reserve.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

Contingency Reserve

A

Time or money allocated in the schedule or cost baseline for known risks with active
response strategies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Contingent Response Strategies

A

Responses provided which may be used in the event that a specific trigger occurs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

Contract

A

A contract is a mutually binding agreement that obligates the seller to provide the specified product or service
or result and obligates the buyer to pay for it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

Contract Change Control System

A

he system used to collect, track, adjudicate, and communicate changes to
a contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Control

A

Comparing actual performance with planned performance, analyzing variances, assessing trends to effect
process improvements, evaluating possible alternatives, and recommending appropriate corrective action as ne

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

Control Account

A

A management control point where scope, budget, actual cost, and schedule are integrated and
compared to earned value for performance measurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

Control Chart

A

A graphic display of process data over time and against established control limits, which has a centerline
that assists in detecting a trend of plotted values toward either control limit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

Control Costs

A

The process of monitoring the status of the project to update the project costs and manage changes to
the cost baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

Control Limits

A

The area composed of three standard deviations on either side of the centerline or mean of a
normal distribution of data plotted on a control chart, which reflects the expected variation in the data. See also
specification limits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

Control Procurements

A

The process of managing procurement relationships, monitoring contract performance, making
changes and corrections as appropriate, and closing out contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

Control Quality

A

The process of monitoring and recording results of executing the quality management activities to
assess performance and ensure the project outputs are complete, correct, and meet customer expectations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

Control Resources

A

The process of ensuring that the physical resources assigned and allocated to the project are
available as planned, as well as monitoring the planned versus actual utilization of resources and performing corrective
action as necessary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

Control Schedule

A

The process of monitoring the status of the project to update the project schedule and manage
changes to the schedule baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

Control Scope

A

The process of monitoring the status of the project and product scope and managing changes to the
scope baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

Corrective Action

A

An intentional activity that realigns the performance of the project work with the project
management plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

Cost Aggregation

A

Summing the lower-level cost estimates associated with the various work packages for a given level
within the project’s WBS or for a given cost control account.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

Cost Baseline

A

The approved version of the time-phased project budget, excluding any management reserves, which
can be changed only through formal change control procedures and is used as a basis for comparison to actual results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

Cost-Benefit Analysis

A

A financial analysis tool used to determine the benefits provided by a project against its costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

Cost Management Plan

A

A component of a project or program management plan that describes how costs will be
planned, structured, and controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

Cost of Quality (CoQ)

A

All costs incurred over the life of the product by investment in preventing nonconformance to
requirements, appraisal of the product or service for conformance to requirements, and failure to meet requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

Cost Performance Index (CPI)

A

A measure of the cost efficiency of budgeted resources expressed as the ratio of earned
value to actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

Cost Plus Award Fee Contract (CPAF)

A

A category of contract that involves payments to the seller for all legitimate
actual costs incurred for completed work, plus an award fee representing seller profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

Cost Plus Fixed Fee Contract (CPFF)

A

A type of cost-reimbursable contract where the buyer reimburses the seller for
the seller’s allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

Cost Plus Incentive Fee Contract (CPIF)

A

A type of cost-reimbursable contract where the buyer reimburses the seller
for the seller’s allowable costs (allowable costs are defined by the contract), and the seller earns its profit if it meets
defined performance criteria.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

Cost-Reimbursable Contract

A

A type of contract involving payment to the seller for the seller’s actual costs, plus a fee
typically representing the seller’s profit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

Cost Variance (CV)

A

The amount of budget deficit or surplus at a given point in time, expressed as the difference
between the earned value and the actual cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

Crashing

A

A technique used to shorten the schedule duration for the least incremental cost by adding resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

Create WBS

A

The process of subdividing project deliverables and project work into smaller, more manageable
components.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

Criteria

A

Standards, rules, or tests on which a judgment or decision can be based or by which a product, service, result,
or process can be evaluated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

Critical Path

A

The sequence of activities that represents the longest path through a project, which determines the
shortest possible duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

Critical Path Activity

A

Any activity on the critical path in a project schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

Critical Path Method (CPM)

A

A method used to estimate the minimum project duration and determine the amount
of schedule flexibility on the logical network paths within the schedule model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

Data

A

Discrete, unorganized, unprocessed measurements or raw observations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

Data Analysis Techniques

A

Techniques used to organize, assess, and evaluate data and information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

Data Date

A

A point in time when the status of the project is recorded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

Data Gathering Techniques

A

Techniques used to collect data and information from a variety of sources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

Data Representation Techniques

A

Graphic representations or other methods used to convey data and information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

Decision-Making Techniques

A

Techniques used to select a course of action from different alternatives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

Decision Tree Analysis

A

A diagramming and calculation technique for evaluating the implications of a chain of multiple
options in the presence of uncertainty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

Decomposition

A

A technique used for dividing and subdividing the project scope and project deliverables into smaller,
more manageable parts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

Defect

A

An imperfection or deficiency in a project component where that component does not meet its requirements or
specifications and needs to be either repaired or replaced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

Defect Repair

A

An intentional activity to modify a nonconforming product or product component

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

Define Activities

A

The process of identifying and documenting the specific actions to be performed to produce the
project deliverables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

Define Scope

A

The process of developing a detailed description of the project and product

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

Deliverable

A

Any unique and verifiable product, result, or capability to perform a service that is required to be produced
to complete a process, phase, or project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

Dependency

A

See definition of “Logical Relationship”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

Determine Budget

A

The process of aggregating the estimated costs of individual activities or work packages to establish
an authorized cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

Development Approach

A

The method used to create and evolve the product, service, or result during the project life
cycle, such as predictive, iterative, incremental, agile, or a hybrid method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

Develop Project Charter

A

The process of developing a document that formally authorizes the existence of a project and
provides the project manager with the authority to apply organizational resources to project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

Develop Project Management Plan

A

The process of defining, preparing, and coordinating all plan components and
consolidating them into an integrated project management plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

Develop Schedule

A

The process of analyzing activity sequences, durations, resource requirements, and schedule
constraints to create the project schedule model for project execution and monitoring and controlling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

Develop Team

A

The process of improving competences, team member interaction, and overall team environment to
enhance project performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

Diagramming Techniques

A

Approaches to presenting information with logical linkages that aid in understanding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

Direct and Manage Project Work

A

The process of leading and performing the work defined in the project management
plan and implementing approved changes to achieve the project’s objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

Discrete Effort

A

An activity that can be planned and measured and that yields a specific output. [Note: Discrete effort is
one of three earned value management (EVM) types of activities used to measure work performance.]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

Discretionary Dependency

A

relationship that is established based on knowledge of best practices within a particular
application area or an aspect of the project where a specific sequence is desired

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

Documentation Reviews

A

The process of gathering a corpus of information and reviewing it to determine accuracy
and completeness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

Duration

A

The total number of work periods required to complete an activity or work breakdown structure component,
expressed in hours, days, or weeks. Contrast with effort.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

Early Finish Date (EF)

A

the critical path method, the earliest possible point in time when the uncompleted portions of
a schedule activity can finish based on the schedule network logic, the data date, and any schedule constraints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

Early Start Date (ES)

A

In the critical path method, the earliest possible point in time when the uncompleted portions of
a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

Earned Value (EV)

A

The measure of work performed expressed in terms of the budget authorized for that work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

Earned Value Management (EVM)

A

A methodology that combines scope, schedule, and resource measurements to assess
project performance and progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

Effort

A

The number of labor units required to complete a schedule activity or work breakdown structure component,
often expressed in hours, days, or weeks. Contrast with duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
132
Q

Emotional Intelligence

A

The ability to identify, assess, and manage the personal emotions of oneself and other people,
as well as the collective emotions of groups of people

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

Enterprise Environmental Factors

A

Conditions, not under the immediate control of the team, that influence, constrain,
or direct the project, program, or portfolio.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

Estimate

A

A quantitative assessment of the likely amount or outcome of a variable, such as project costs, resources,
effort, or durations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

Estimate Activity Durations

A

The process of estimating the number of work periods needed to complete individual
activities with the estimated resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
136
Q

Estimate Activity Resources

A

The process of estimating team resources and the type and quantities of material,
equipment, and supplies necessary to perform project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
137
Q

Estimate at Completion (EAC)

A

The expected total cost of completing all work expressed as the sum of the actual cost
to date and the estimate to complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
138
Q

Estimate Costs

A

The process of developing an approximation of the monetary resources needed to complete
project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
139
Q

Estimate to Complete (ETC)

A

The expected cost to finish all the remaining project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
140
Q

Execute

A

Directing, managing, performing, and accomplishing the project work; providing the deliverables; and providing
work performance information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
141
Q

Executing Process Group

A

Those processes performed to complete the work defined in the project management plan
to satisfy the project requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
142
Q

Expert Judgment

A

Judgment provided based upon expertise in an application area, knowledge area, discipline, industry,
etc., as appropriate for the activity being performed. Such expertise may be provided by any group or person with
specialized education, knowledge, skill, experience, or training

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
143
Q

Explicit Knowledge

A

Knowledge that can be codified using symbols such as words, numbers, and pictures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
144
Q

External Dependency

A

A relationship between project activities and non-project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
145
Q

Fallback Plan

A

Fallback plans include an alternative set of actions and tasks available in the event that the primary plan
needs to be abandoned because of issues, risks, or other causes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
146
Q

Fast Tracking

A

A schedule compression technique in which activities or phases normally done in sequence are performed
in parallel for at least a portion of their duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
147
Q

Fee

A

Represents profit as a component of compensation to a seller

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
148
Q

Finish Date

A

A point in time associated with a schedule activity’s completion. Usually qualified by one of the following:
actual, planned, estimated, scheduled, early, late, baseline, target, or current.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
149
Q

Finish-to-Finish (FF)

A

A logical relationship in which a successor activity cannot finish until a predecessor activity
has finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
150
Q

Finish-to-Start (FS)

A

A logical relationship in which a successor activity cannot start until a predecessor activity
has finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
151
Q

Firm Fixed Price Contract (FFP)

A

A type of fixed price contract where the buyer pays the seller a set amount (as defined
by the contract), regardless of the seller’s costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
152
Q

Fixed Price Contract

A

An agreement that sets the fee that will be paid for a defined scope of work regardless of the
cost or effort to deliver it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
153
Q

Fixed Price Incentive Fee Contract (FPIF)

A

A type of contract where the buyer pays the seller a set amount (as defined
by the contract), and the seller can earn an additional amount if the seller meets defined performance criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
154
Q

Fixed Price with Economic Price Adjustment Contract (FPEPA)

A
A fixed-price contract, but with a special provision
allowing for predefined final adjustments to the contract price due to changed conditions, such as inflation changes, or
cost increases (or decreases) for specific commodities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
155
Q

Flowchart

A

The depiction in a diagram format of the inputs, process actions, and outputs of one or more processes
within a system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
156
Q

Focus Groups

A

An elicitation technique that brings together prequalified stakeholders and subject matter experts to
learn about their expectations and attitudes about a proposed product, service, or result.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
157
Q

Forecast

A

An estimate or prediction of conditions and events in the project’s future based on information and knowledge
available at the time of the forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
158
Q

Forward Pass

A

critical path method technique for calculating the early start and early finish dates by working forward
through the schedule model from the project start date or a given point in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
159
Q

Free Float

A

The amount of time that a schedule activity can be delayed without delaying the early start date of any
successor or violating a schedule constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
160
Q

Functional Organization

A

An organizational structure in which staff is grouped by areas of specialization and the project
manager has limited authority to assign work and apply resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
161
Q

Funding Limit Reconciliation

A

The process of comparing the planned expenditure of project funds against any
limits on the commitment of funds for the project to identify any variances between the funding limits and the
planned expenditures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
162
Q

Gantt Chart

A

A bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the
horizontal axis, and activity durations are shown as horizontal bars placed according to start and finish dates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
163
Q

Grade

A

A category or rank used to distinguish items that have the same functional use but do not share the same
requirements for quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
164
Q

Ground Rules

A

Expectations regarding acceptable behavior by project team members

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
165
Q

Histogram

A

A bar chart that shows the graphical representation of numerical data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
166
Q

Historical Information

A

Documents and data on prior projects including project files, records, correspondence, closed
contracts, and closed projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
167
Q

Identify Risks

A

The process of identifying individual risks as well as sources of overall risk and documenting their
characteristics.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
168
Q

Identify Stakeholders

A

The process of identifying project stakeholders regularly and analyzing and documenting
relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on
project success.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
169
Q

Implement Risk Responses

A

The process of implementing agreed-upon risk response plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
170
Q

Imposed Date

A

A fixed date imposed on a schedule activity or schedule milestone, usually in the form of a “start no
earlier than” and “finish no later than” date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
171
Q

Incentive Fee

A

A set of financial incentives related to cost, schedule, or technical performance of the seller

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
172
Q

Incremental Life Cycle

A

An adaptive project life cycle in which the deliverable is produced through a series of iterations
that successively add functionality within a predetermined time frame. The deliverable contains the necessary and
sufficient capability to be considered complete only after the final iteration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
173
Q

Independent Estimates

A

A process of using a third party to obtain and analyze information to support prediction of cost,
schedule, or other items.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
174
Q

Influence Diagram

A

A graphical representation of situations showing causal influences, time ordering of events, and
other relationships among variables and outcomes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
175
Q

Information

A

Organized or structured data, processed for a specific purpose to make it meaningful, valuable, and useful
in specific contexts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
176
Q

Information Management Systems

A

Facilities, processes, and procedures used to collect, store, and distribute
information between producers and consumers of information in physical or electronic format

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
177
Q

Initiating Process Group

A

Those processes performed to define a new project or a new phase of an existing project by
obtaining authorization to start the project or phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
178
Q

Input

A

Any item, whether internal or external to the project, which is required by a process before that process proceeds.
May be an output from a predecessor process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
179
Q

Inspection

A

Examination of a work product to determine whether it conforms to documented standards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
180
Q

Interpersonal and Team Skills

A

Skills used to effectively lead and interact with team members and other stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
181
Q

Interpersonal Skills

A

Skills used to establish and maintain relationships with other people

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
182
Q

Interviews

A

A formal or informal approach to elicit information from stakeholders by talking to them directly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
183
Q

Invitation for Bid (IFB)

A

Generally, this term is equivalent to request for proposal. However, in some application areas,
it may have a narrower or more specific meaning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
184
Q

Issue

A

current condition or situation that may have an impact on the project objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
185
Q

Issue Log

A

A project document where information about issues is recorded and monitored

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
186
Q

Iterative Life Cycle

A

A project life cycle where the project scope is generally determined early in the project life cycle,
but time and cost estimates are routinely modified as the project team’s understanding of the product increases.
Iterations develop the product through a series of repeated cycles, while increments successively add to the
functionality of the product.

187
Q

Knowledge

A

A mixture of experience, values and beliefs, contextual information, intuition, and insight that people use to
make sense of new experiences and information

188
Q

Lag

A

The amount of time whereby a successor activity will be delayed with respect to a predecessor activity

189
Q

Late Finish Date (LF)

A

the critical path method, the latest possible point in time when the uncompleted portions of a
schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints.

190
Q

Late Start Date (LS)

A

In the critical path method, the latest possible point in time when the uncompleted portions of a
schedule activity can start based on the schedule network logic, the project completion date, and any schedule constraints

191
Q

Lead

A

The amount of time whereby a successor activity can be advanced with respect to a predecessor activity

192
Q

Lessons Learned

A

The knowledge gained during a project which shows how project events were addressed or should
be addressed in the future for the purpose of improving future performance.

193
Q

Lessons Learned Register

A

A project document used to record knowledge gained during a project so that it can be used
in the current project and entered into the lessons learned repository

194
Q

Lessons Learned Repository

A

A store of historical information about lessons learned in projects

195
Q

Level of Effort (LOE)

A

An activity that does not produce definitive end products and is measured by the passage of time

196
Q

Log

A

A document used to record and describe or denote selected items identified during execution of a process or
activity. Usually used with a modifier, such as issue, change, issue, or assumption

197
Q

Logical Relationship

A

dependency between two activities, or between an activity and a milestone

198
Q

Make-or-Buy Analysis

A

The process of gathering and organizing data about product requirements and analyzing them
against available alternatives including the purchase or internal manufacture of the product

199
Q

Make-or-Buy Decisions

A

Decisions made regarding the external purchase or internal manufacture of a product.

200
Q

Manage Communications

A

Manage Communications is the process of ensuring timely and appropriate collection,
creation, distribution, storage, retrieval, management, monitoring, and the ultimate disposition of project information

201
Q

Management Reserve

A

An amount of the project budget or project schedule held outside of the performance
measurement baseline (PMB) for management control purposes, that is reserved for unforeseen work that is within
scope of the project.

202
Q

Management Skills

A

The ability to plan, organize, direct, and control individuals or groups of people to achieve
specific goals.

203
Q

Manage Project Knowledge

A

The process of using existing knowledge and creating new knowledge to achieve the
project’s objectives and contribute to organizational learning

204
Q

Manage Quality

A

The process of translating the quality management plan into executable quality activities that
incorporate the organization’s quality policies into the project.

205
Q

Manage Stakeholder Engagement

A

The process of communicating and working with stakeholders to meet their needs
and expectations, address issues, and foster appropriate stakeholder involvement

206
Q

Manage Team

A

The process of tracking team member performance, providing feedback, resolving issues, and managing
team changes to optimize project performance

207
Q

Mandatory Dependency

A

A relationship that is contractually required or inherent in the nature of the work.

208
Q

Master Schedule

A

A summary-level project schedule that identifies the major deliverables and work breakdown
structure components and key schedule milestones. See also milestone schedule

209
Q

Matrix Diagrams

A

A quality management and control tool used to perform data analysis within the organizational
structure created in the matrix. The matrix diagram seeks to show the strength of relationships between factors, causes,
and objectives that exist between the rows and columns that form the matrix

210
Q

Matrix Organization

A

Any organizational structure in which the project manager shares responsibility with the functional
managers for assigning priorities and for directing the work of persons assigned to the project

211
Q

Methodology

A

A system of practices, techniques, procedures, and rules used by those who work in a discipline.

212
Q

Milestone

A

A significant point or event in a project, program, or portfolio.

213
Q

Milestone Schedule

A

A type of schedule that presents milestones with planned dates. See also master schedule.

214
Q

Mind-Mapping

A

A technique used to consolidate ideas created through individual brainstorming sessions into a single
map to reflect commonality and differences in understanding and to generate new ideas.

215
Q

Monitor

A

Collect project performance data, produce performance measures, and report and disseminate
performance information

216
Q

Monitor and Control Project Work

A

The process of tracking, reviewing, and reporting overall progress to meet the
performance objectives defined in the project management plan.

217
Q

Monitor Communications

A

The process of ensuring that the information needs of the project and its stakeholders
are met.

218
Q

Monitoring and Controlling Process Group

A

Those processes required to track, review, and regulate the progress
and performance of the project; identify any areas in which changes to the plan are required; and initiate the
corresponding changes

219
Q

Monitor Risks

A

The process of monitoring the implementation of agreed-upon risk response plans, tracking identified
risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project

220
Q

Monitor Stakeholder Engagement

A

The process of monitoring project stakeholder relationships, and tailoring strategies
for engaging stakeholders through the modification of engagement strategies and plans.

221
Q

Monte Carlo Simulation

A

An analysis technique where a computer model is iterated many times, with the input
values chosen at random for each iteration driven by the input data, including probability distributions and probabilistic
branches. Outputs are generated to represent the range of possible outcomes for the project.

222
Q

Multicriteria Decision Analysis

A

This technique utilizes a decision matrix to provide a systematic analytical approach
for establishing criteria, such as risk levels, uncertainty, and valuation, to evaluate and rank many ideas

223
Q

Network Logic

A

All activity dependencies in a project schedule network diagram.

224
Q

Network Path

A

A sequence of activities connected by logical relationships in a project schedule network diagram

225
Q

Networking

A

Establishing connections and relationships with other people from the same or other organizations

226
Q

Node

A

A point at which dependency lines connect on a schedule network diagram.

227
Q

Nominal Group Technique

A

A technique that enhances brainstorming with a voting process used to rank the most
useful ideas for further brainstorming or for prioritization

228
Q

Objective

A

Something toward which work is to be directed, a strategic position to be attained, a purpose to be achieved,
a result to be obtained, a product to be produced, or a service to be performed

229
Q

Opportunity

A

A risk that would have a positive effect on one or more project objectives

230
Q

Organizational Breakdown Structure (OBS)

A

A hierarchical representation of the project organization, which illustrates
the relationship between project activities and the organizational units that will perform those activities

231
Q

Organizational Learning

A

A discipline concerned with the way individuals, groups, and organizations develop knowledge

232
Q

Organizational Process Assets

A

Plans, processes, policies, procedures, and knowledge bases that are specific to and
used by the performing organization.

233
Q

Output

A

A product, result, or service generated by a process. May be an input to a successor process

234
Q

Overall Project Risk

A

The effect of uncertainty on the project as a whole, arising from all sources of uncertainty
including individual risks, representing the exposure of stakeholders to the implications of variations in project
outcome, both positive and negative

235
Q

Parametric Estimating

A

An estimating technique in which an algorithm is used to calculate cost or duration based on
historical data and project parameters.

236
Q

Path Convergence

A

A relationship in which a schedule activity has more than one predecessor

237
Q

Path Divergence

A

A relationship in which a schedule activity has more than one successor

238
Q

Percent Complete

A

An estimate expressed as a percent of the amount of work that has been completed on an activity
or a work breakdown structure component.

239
Q

Performance Measurement Baseline (PMB)

A

Integrated scope, schedule, and cost baselines used for comparison to
manage, measure, and control project execution.

240
Q

Performance Reviews

A

A technique that is used to measure, compare, and analyze actual performance of work in
progress on the project against the baseline

241
Q

Perform Integrated Change Control

A

The process of reviewing all change requests; approving changes and managing
changes to deliverables, organizational process assets, project documents, and the project management plan; and
communicating the decisions.

242
Q

Perform Qualitative Risk Analysis

A

The process of prioritizing individual project risks for further analysis or action by
assessing their probability of occurrence and impact as well as other characteristics

243
Q

Perform Quantitative Risk Analysis

A

The process of numerically analyzing the combined effect of identified individual
project risks and other sources of uncertainty on overall project objectives.

244
Q

Phase Gate

A

A review at the end of a phase in which a decision is made to continue to the next phase, to continue with
modification, or to end a project or program

245
Q

Plan Communications Management

A

The process of developing an appropriate approach and plan for project
communication activities based on the information needs of each stakeholder or group, available organizational assets,
and the needs of the project.

246
Q

Plan Cost Management

A

The process of defining how the project costs will be estimated, budgeted, managed,
monitored, and controlled

247
Q

Planned Value (PV)

A

The authorized budget assigned to scheduled work.

248
Q

Planning Package

A

A work breakdown structure component below the control account with known work content but
without detailed schedule activities. See also control account

249
Q

Planning Process Group

A

Those processes required to establish the scope of the project, refine the objectives, and
define the course of action required to attain the objectives that the project was undertaken to achieve

250
Q

Plan Procurement Management

A

The process of documenting project procurement decisions, specifying the approach,
and identifying potential sellers.

251
Q

Plan Quality Management

A

The process of identifying quality requirements and/or standards for the project and its
deliverables, and documenting how the project will demonstrate compliance with quality requirements and/or standards

252
Q

Plan Resource Management

A

The process of defining how to estimate, acquire, manage, and utilize physical and
team resources.

253
Q

Plan Risk Management

A

The process of defining how to conduct risk management activities for a project.

254
Q

Plan Risk Responses

A

The process of developing options, selecting strategies, and agreeing on actions to address
overall project risk exposure, as well as to treat individual project risks.

255
Q

Plan Schedule Management

A

The process of establishing the policies, procedures, and documentation for planning,
developing, managing, executing, and controlling the project schedule

256
Q

Plan Scope Management

A

The process of creating a scope management plan that documents how the project and
product scope will be defined, validated, and controlled

257
Q

Plan Stakeholder Engagement

A

The process of developing approaches to involve project stakeholders, based on their
needs, expectations, interests, and potential impact on the project

258
Q

Plurality

A

Decisions made by the largest block in a group, even if a majority is not achieved.

259
Q

Policy

A

A structured pattern of actions adopted by an organization such that the organization’s policy can be explained
as a set of basic principles that govern the organization’s conduct

260
Q

Portfolio

A

Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives

261
Q

Portfolio Management

A

The centralized management of one or more portfolios to achieve strategic objectives

262
Q

Practice

A

A specific type of professional or management activity that contributes to the execution of a process and that
may employ one or more techniques and tools

263
Q

Precedence Diagramming Method (PDM)

A

A technique used for constructing a schedule model in which activities are
represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the
activities are to be performed.

264
Q

Precedence Relationship

A

A logical dependency used in the precedence diagramming method

265
Q

Predecessor Activity

A

An activity that logically comes before a dependent activity in a schedule

266
Q

Predictive Life Cycle

A

A form of project life cycle in which the project scope, time, and cost are determined in the early
phases of the life cycle.

267
Q

Preventive Action

A

An intentional activity that ensures the future performance of the project work is aligned with the
project management plan.

268
Q

Probability and Impact Matrix

A

A grid for mapping the probability of occurrence of each risk and its impact on project
objectives if that risk occurs.

269
Q

Procedure

A

An established method of accomplishing a consistent performance or result, a procedure typically can be
described as the sequence of steps that will be used to execute a process.

270
Q

Process

A

A systematic series of activities directed towards causing an end result such that one or more inputs will be
acted upon to create one or more outputs.

271
Q

Procurement Audits

A

The review of contracts and contracting processes for completeness, accuracy, and effectiveness

272
Q

Procurement Documents

A

The documents utilized in bid and proposal activities, which include the buyer’s
Invitation for bid, invitation for negotiations, request for information, request for quotation, request for proposal,
and seller’s responses.

273
Q

Procurement Documentation

A

All documents used in signing, executing, and closing an agreement. Procurement
documentation may include documents predating the project.

274
Q

Procurement Management Plan

A

A component of the project or program management plan that describes how
a project team will acquire goods and services from outside of the performing organization

275
Q

Procurement Statement of Work

A

Describes the procurement item in sufficient detail to allow prospective sellers to
determine if they are capable of providing the products, services, or results.

276
Q

Procurement Strategy

A
The approach by the buyer to determine the project delivery method and the type of legally
binding agreement(s) that should be used to deliver the desired results
277
Q

Product

A

An artifact that is produced, is quantifiable, and can be either an end item in itself or a component item.
Additional words for products are material and goods. See also deliverable.

278
Q

Product Analysis

A

For projects that have a product as a deliverable, it is a tool to define scope that generally means
asking questions about a product and forming answers to describe the use, characteristics, and other relevant aspects
of what is going to be manufactured.

279
Q

Product Life Cycle

A

The series of phases that represent the evolution of a product, from concept through delivery,
growth, maturity, and to retirement

280
Q

Product Scope

A

The features and functions that characterize a product, service, or result

281
Q

Product Scope Description

A

The documented narrative description of the product scope.

282
Q

Program

A

Related projects, subsidiary programs, and program activities that are managed in a coordinated manner to
obtain benefits not available from managing them individually

283
Q

Program Management

A

The application of knowledge, skills, and principles to a program to achieve the program
objectives and obtain benefits and control not available by managing program components individually

284
Q

Progressive Elaboration

A

The iterative process of increasing the level of detail in a project management plan as greater
amounts of information and more accurate estimates become available.

285
Q

Project

A

A temporary endeavor undertaken to create a unique product, service, or result

286
Q

Project Calendar

A

A calendar that identifies working days and shifts that are available for scheduled activities

287
Q

Project Charter

A

A document issued by the project initiator or sponsor that formally authorizes the existence of a project
and provides the project manager with the authority to apply organizational resources to project activities

288
Q

Project Communications Management

A

Project Communications Management includes the processes required
to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control,
monitoring, and ultimate disposition of project information

289
Q

Project Cost Management

A

Project Cost Management includes the processes involved in planning, estimating,
budgeting, financing, funding, managing, and controlling costs so the project can be completed within the
approved budget.

290
Q

Project Funding Requirements

A

Forecast project costs to be paid that are derived from the cost baseline for total or
periodic requirements, including projected expenditures plus anticipated liabilities

291
Q

Project Governance

A

The framework, functions, and processes that guide project management activities in order to
create a unique product, service, or result to meet organizational, strategic, and operational goals

292
Q

Project Initiation

A

Launching a process that can result in the authorization of a new project

293
Q

Project Integration Management

A

Project Integration Management includes the processes and activities to identify,
define, combine, unify, and coordinate the various processes and project management activities within the Project
Management Process Groups.

294
Q

Project Life Cycle

A

The series of phases that a project passes through from its start to its completion

295
Q

Project Management

A

The application of knowledge, skills, tools, and techniques to project activities to meet the
project requirements.

296
Q

Project Management Body of Knowledge

A

A term that describes the knowledge within the profession of project
management. The project management body of knowledge includes proven traditional practices that are widely applied
as well as innovative practices that are emerging in the profession

297
Q

Project Management Information System

A

An information system consisting of the tools and techniques used to
gather, integrate, and disseminate the outputs of project management processes.

298
Q

Project Management Knowledge Area

A

An identified area of project management defined by its knowledge
requirements and described in terms of its component processes, practices, inputs, outputs, tools, and techniques

299
Q

Project Management Office (PMO)

A

A management structure that standardizes the project-related governance
processes and facilitates the sharing of resources, methodologies, tools, and techniques.

300
Q

Project Management Plan

A

The document that describes how the project will be executed, monitored and controlled,
and closed.

301
Q

Project Management Process Group

A

A logical grouping of project management inputs, tools and techniques,
and outputs. The Project Management Process Groups include initiating processes, planning processes, executing
processes, monitoring and controlling processes, and closing processes. Project Management Process Groups are
not project phases.

302
Q

Project Management System

A

The aggregation of the processes, tools, techniques, methodologies, resources, and
procedures to manage a project.

303
Q

Project Management Team

A

The members of the project team who are directly involved in project management
activities. See also Project Team.

304
Q

Project Manager (PM)

A

The person assigned by the performing organization to lead the team that is responsible for
achieving the project objectives

305
Q

Project Organization Chart

A

A document that graphically depicts the project team members and their interrelationships
for a specific project

306
Q

Project Phase

A

A collection of logically related project activities that culminates in the completion of one or
more deliverables.

307
Q

Project Procurement Management

A

Project Procurement Management includes the processes necessary to purchase
or acquire products, services, or results needed from outside the project team

308
Q

Project Quality Management

A

Project Quality Management includes the processes for incorporating the organization’s
quality policy regarding planning, managing, and controlling project and product quality requirements, in order to meet
stakeholders’ expectations

309
Q

Project Resource Management

A

Project Resource Management includes the processes to identify, acquire, and
manage the resources needed for the successful completion of the project

310
Q

Project Risk Management

A

Project Risk Management includes the processes of conducting risk management planning,
identification, analysis, response planning, response implementation, and monitoring risk on a project

311
Q

Project Schedule

A

An output of a schedule model that presents linked activities with planned dates, durations,
milestones, and resources

312
Q

Project Schedule Management

A

Project Schedule Management includes the processes required to manage the timely
completion of the project.

313
Q

Project Schedule Network Diagram

A

graphical representation of the logical relationships among the project
schedule activities

314
Q

Project Scope

A

The work performed to deliver a product, service, or result with the specified features and functions

315
Q

Project Scope Management

A

Project Scope Management includes the processes required to ensure that the project
includes all the work required, and only the work required, to complete the project successfully

316
Q

Project Scope Statement

A

The description of the project scope, major deliverables, assumptions, and constraints

317
Q

Project Stakeholder Management

A

Project Stakeholder Management includes the processes required to identify the
people, groups, or organizations that could impact or be impacted by the project, to analyze stakeholder expectations
and their impact on the project, and to develop appropriate management strategies for effectively engaging stakeholders
in project decisions and execution

318
Q

Project Team

A

A set of individuals who support the project manager in performing the work of the project to achieve its
objectives. See also Project Management Team

319
Q

Project Team Directory

A

A documented list of project team members, their project roles, and communication information

320
Q

Proposal Evaluation Techniques

A

The process of reviewing proposals provided by suppliers to support contract
award decisions.

321
Q

Prototypes

A

A method of obtaining early feedback on requirements by providing a working model of the expected
product before actually building it.

322
Q

Quality

A

The degree to which a set of inherent characteristics fulfills requirements

323
Q

Quality Audits

A

A quality audit is a structured, independent process to determine if project activities comply with
organizational and project policies, processes, and procedures

324
Q

Quality Checklists

A

A structured tool used to verify that a set of required steps has been performed

325
Q

Quality Control Measurements

A

The documented results of control quality activities.

326
Q

Quality Management Plan

A

A component of the project or program management plan that describes how applicable
policies, procedures, and guidelines will be implemented to achieve the quality objectives

327
Q

Quality Management System

A

The organizational framework whose structure provides the policies, processes,
procedures, and resources required to implement the quality management plan. The typical project quality management
plan should be compatible to the organization’s quality management system

328
Q

Quality Metrics

A

A description of a project or product attribute and how to measure it.

329
Q

Quality Policy

A

A policy specific to the Project Quality Management Knowledge Area, it establishes the basic principles
that should govern the organization’s actions as it implements its system for quality management

330
Q

Quality Report

A

A project document that includes quality management issues, recommendations for corrective actions,
and a summary of findings from quality control activities and may include recommendations for process, project, and
product improvements

331
Q

Quality Requirement

A

A condition or capability that will be used to assess conformance by validating the acceptability
of an attribute for the quality of a result.

332
Q

Questionnaires

A

Written sets of questions designed to quickly accumulate information from a large number
of respondents.

333
Q

RACI Chart

A

A common type of responsibility assignment matrix that uses responsible, accountable, consult, and inform
statuses to define the involvement of stakeholders in project activities

334
Q

Regression Analysis

A

An analytical technique where a series of input variables are examined in relation to their
corresponding output results in order to develop a mathematical or statistical relationship

335
Q

Regulations

A

Requirements imposed by a governmental body. These requirements can establish product, process,
or service characteristics, including applicable administrative provisions that have government-mandated compliance

336
Q

Request for Information (RFI)

A

A type of procurement document whereby the buyer requests a potential seller
to provide various pieces of information related to a product or service or seller capability

337
Q

Request for Proposal (RFP)

A

A type of procurement document used to request proposals from prospective sellers
of products or services. In some application areas, it may have a narrower or more specific meaning

338
Q

Request for Quotation (RFQ)

A

A type of procurement document used to request price quotations from prospective
sellers of common or standard products or services. Sometimes used in place of request for proposal and, in some
application areas, it may have a narrower or more specific meaning

339
Q

Requirement

A

A condition or capability that is necessary to be present in a product, service, or result to satisfy a
business need.

340
Q

Requirements Documentation

A

A description of how individual requirements meet the business need for the project

341
Q

Requirements Management Plan

A

A component of the project or program management plan that describes how
requirements will be analyzed, documented, and managed

342
Q

Requirements Traceability Matrix

A

A grid that links product requirements from their origin to the deliverables that
satisfy them.

343
Q

Reserve

A

A provision in the project management plan to mitigate cost and/or schedule risk. Often used with a modifier
(e.g., management reserve, contingency reserve) to provide further detail on what types of risk are meant to be mitigated.

344
Q

Reserve Analysis

A

An analytical technique to determine the essential features and relationships of components in the
project management plan to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project

345
Q

Residual Risk

A

The risk that remains after risk responses have been implemented.

346
Q

Resource

A

A team member or any physical item needed to complete the project.

347
Q

Resource Breakdown Structure

A

A hierarchical representation of resources by category and type.

348
Q

Resource Calendar

A

A calendar that identifies the working days and shifts upon which each specific resource is
available.

349
Q

Resource Histogram

A

A bar chart showing the amount of time that a resource is scheduled to work over a series of
time periods.

350
Q

Resource Leveling

A

A resource optimization technique in which adjustments are made to the project schedule to
optimize the allocation of resources and which may affect critical path. See also resource optimization technique and
resource smoothing.

351
Q

Resource Management Plan

A

A component of the project management plan that describes how project resources are
acquired, allocated, monitored, and controlled.

352
Q

Resource Manager

A

An individual with management authority over one or more resources.

353
Q

Resource Optimization Technique

A

A technique in which activity start and finish dates are adjusted to balance demand
for resources with the available supply. See also resource leveling and resource smoothing.

354
Q

Resource Requirements

A

The types and quantities of resources required for each activity in a work package

355
Q

Resource Smoothing

A

A resource optimization technique in which free and total float are used without affecting the
critical path. See also resource leveling and resource optimization technique

356
Q

Responsibility

A

An assignment that can be delegated within a project management plan such that the assigned resource
incurs a duty to perform the requirements of the assignment

357
Q

Responsibility Assignment Matrix (RAM)

A

A grid that shows the project resources assigned to each work package.

358
Q

Result

A

An output from performing project management processes and activities. Results include outcomes (e.g.,
integrated systems, revised process, restructured organization, tests, trained personnel, etc.) and documents
(e.g., policies, plans, studies, procedures, specifications, reports, etc.). See also deliverable.

359
Q

Rework

A

Action taken to bring a defective or nonconforming component into compliance with requirements
or specifications.

360
Q

Risk

A

An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.

361
Q

Risk Acceptance

A

A risk response strategy whereby the project team decides to acknowledge the risk and not take any
action unless the risk occurs.

362
Q

Risk Appetite

A

The degree of uncertainty an organization or individual is willing to accept in anticipation of a reward.

363
Q

Risk Audit

A

A type of audit used to consider the effectiveness of the risk management process.

364
Q

Risk Avoidance

A

A risk response strategy whereby the project team acts to eliminate the threat or protect the project
from its impact.

365
Q

Risk Breakdown Structure (RBS)

A

A hierarchical representation of potential sources of risks.

366
Q

Risk Categorization

A

Organization by sources of risk (e.g., using the RBS), the area of the project affected (e.g., using
the WBS), or other useful category (e.g., project phase) to determine the areas of the project most exposed to the effects
of uncertainty.

367
Q

Risk Category

A

A group of potential causes of risk.

368
Q

Risk Data Quality Assessment

A

Technique to evaluate the degree to which the data about risks is useful for
risk management

369
Q

Risk Enhancement

A

A risk response strategy whereby the project team acts to increase the probability of occurrence
or impact of an opportunity

370
Q

Risk Escalation

A

risk response strategy whereby the team acknowledges that a risk is outside of its sphere of
influence and shifts the ownership of the risk to a higher level of the organization where it is more effectively managed

371
Q

Risk Exploiting

A

A risk response strategy whereby the project team acts to ensure that an opportunity occurs

372
Q

Risk Exposure

A

An aggregate measure of the potential impact of all risks at any given point in time in a project,
program, or portfolio.

373
Q

Risk Management Plan

A

A component of the project, program, or portfolio management plan that describes how risk
management activities will be structured and performed

374
Q

Risk Mitigation

A

A risk response strategy whereby the project team acts to decrease the probability of occurrence or
impact of a threat.

375
Q

Risk Owner

A

The person responsible for monitoring the risks and for selecting and implementing an appropriate risk
response strategy

376
Q

Risk Register

A

A repository in which outputs of risk management processes are recorded

377
Q

Risk Report

A

A project document developed progressively throughout the Project Risk Management processes, which
summarizes information on individual project risks and the level of overall project risk

378
Q

Risk Review

A

A meeting to examine and document the effectiveness of risk responses in dealing with overall project
risk and with identified individual project risks

379
Q

Risk Sharing

A

A risk response strategy whereby the project team allocates ownership of an opportunity to a third party
who is best able to capture the benefit of that opportunity.

380
Q

Risk Threshold

A

The level of risk exposure above which risks are addressed and below which risks may be accepted

381
Q

Risk Transference

A

risk response strategy whereby the project team shifts the impact of a threat to a third party,
together with ownership of the response

382
Q

Role

A

A defined function to be performed by a project team member, such as testing, filing, inspecting, or coding

383
Q

Rolling Wave Planning

A

An iterative planning technique in which the work to be accomplished in the near term is
planned in detail, while the work in the future is planned at a higher level.

384
Q

Root Cause Analysis

A

An analytical technique used to determine the basic underlying reason that causes a variance or
a defect or a risk. A root cause may underlie more than one variance or defect or risk.

385
Q

Schedule Baseline

A

The approved version of a schedule model that can be changed using formal change control
procedures and is used as the basis for comparison to actual results

386
Q

Schedule Compression

A

A technique used to shorten the schedule duration without reducing the project scope

387
Q

Schedule Data

A

The collection of information for describing and controlling the schedule.

388
Q

Schedule Forecasts

A

Estimates or predictions of conditions and events in the project’s future based on information and
knowledge available at the time the schedule is calculated

389
Q

Schedule Management Plan

A

A component of the project or program management plan that establishes the criteria
and the activities for developing, monitoring, and controlling the schedule.

390
Q

Schedule Model

A

A representation of the plan for executing the project’s activities including durations, dependencies,
and other planning information, used to produce a project schedule along with other scheduling artifacts

391
Q

Schedule Network Analysis

A

A technique to identify early and late start dates, as well as early and late finish dates, for
the uncompleted portions of project activities

392
Q

Schedule Performance Index (SPI)

A

A measure of schedule efficiency expressed as the ratio of earned value to
planned value.

393
Q

Schedule Variance (SV)

A

A measure of schedule performance expressed as the difference between the earned value
and the planned value.

394
Q

Scheduling Tool

A

A tool that provides schedule component names, definitions, structural relationships, and formats that
support the application of a scheduling method.

395
Q

Scope

A

The sum of the products, services, and results to be provided as a project. See also project scope and
product scope.

396
Q

Scope Baseline

A

The approved version of a scope statement, work breakdown structure (WBS), and its associated
WBS dictionary, that can be changed using formal change control procedures and is used as a basis for comparison
to actual results

397
Q

Scope Creep

A

The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources

398
Q

Scope Management Plan

A

A component of the project or program management plan that describes how the scope will
be defined, developed, monitored, controlled, and validated.

399
Q

Secondary Risk

A

A risk that arises as a direct result of implementing a risk response.

400
Q

Self-Organizing Teams

A

A team formation where the team functions with an absence of centralized control

401
Q

Seller

A

A provider or supplier of products, services, or results to an organization.

402
Q

Seller Proposals

A

Formal responses from sellers to a request for proposal or other procurement document specifying
the price, commercial terms of sale, and technical specifications or capabilities the seller will do for the requesting
organization that, if accepted, would bind the seller to perform the resulting agreement.

403
Q

Sensitivity Analysis

A

An analysis technique to determine which individual project risks or other sources of uncertainty
have the most potential impact on project outcomes, by correlating variations in project outcomes with variations in
elements of a quantitative risk analysis model

404
Q

Sequence Activities

A

The process of identifying and documenting relationships among the project activities.

405
Q

Service Level Agreement (SLA)

A

A contract between a service provider (either internal or external) and the end user
that defines the level of service expected from the service provider

406
Q

Simulation

A

An analytical technique that models the combined effect of uncertainties to evaluate their potential impact
on objectives.

407
Q

Source Selection Criteria

A

set of attributes desired by the buyer which a seller is required to meet or exceed to be
selected for a contract.

408
Q

Specification

A

A precise statement of the needs to be satisfied and the essential characteristics that are required

409
Q

Specification Limits

A

The area, on either side of the centerline, or mean, of data plotted on a control chart that meets
the customer’s requirements for a product or service. This area may be greater than or less than the area defined by the
control limits. See also control limits.

410
Q

Sponsor

A

A person or group who provides resources and support for the project, program, or portfolio and is accountable
for enabling success.

411
Q

Sponsoring Organization

A

The entity responsible for providing the project’s sponsor and a conduit for project funding
or other project resources

412
Q

Stakeholder

A

An individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a
decision, activity, or outcome of a project, program, or portfolio

413
Q

Stakeholder Analysis

A

A technique of systematically gathering and analyzing quantitative and qualitative information
to determine whose interests should be taken into account throughout the project.

414
Q

Stakeholder Engagement Assessment Matrix

A

A matrix that compares current and desired stakeholder

engagement levels.

415
Q

Stakeholder Engagement Plan

A

A component of the project management plan that identifies the strategies and actions
required to promote productive involvement of stakeholders in project or program decision making and execution

416
Q

Stakeholder Register

A

A project document including the identification, assessment, and classification of project
stakeholders.

417
Q

Standard

A

A document established by an authority, custom, or general consent as a model or example

418
Q

Start Date

A

A point in time associated with a schedule activity’s start, usually qualified by one of the following: actual,
planned, estimated, scheduled, early, late, target, baseline, or current.

419
Q

Start-to-Finish (SF)

A

A logical relationship in which a successor activity cannot finish until a predecessor activity
has started.

420
Q

Start-to-Start (SS)

A

A logical relationship in which a successor activity cannot start until a predecessor activity
has started.

421
Q

Statement of Work (SOW)

A

A narrative description of products, services, or results to be delivered by the project.

422
Q

Statistical Sampling

A

Choosing part of a population of interest for inspection

423
Q

Successor Activity

A

dependent activity that logically comes after another activity in a schedule.

424
Q

Summary Activity

A

A group of related schedule activities aggregated and displayed as a single activity

425
Q

SWOT Analysis

A

Analysis of strengths, weaknesses, opportunities, and threats of an organization, project, or option.

426
Q

Tacit Knowledge

A

knowledge that can be difficult to articulate and share such as beliefs, experience,
and insights.

427
Q

Tailoring

A

Determining the appropriate combination of processes, inputs, tools, techniques, outputs, and life cycle
phases to manage a project

428
Q

Team Charter

A

A document that records the team values, agreements, and operating guidelines, as well as establishing
clear expectations regarding acceptable behavior by project team members

429
Q

Team Management Plan

A

A component of the resource management plan that describes when and how team members
will be acquired and how long they will be needed

430
Q

Technique

A

A defined systematic procedure employed by a human resource to perform an activity to produce a product
or result or deliver a service, and that may employ one or more tools

431
Q

Templates

A

A partially complete document in a predefined format that provides a defined structure for collecting,
organizing, and presenting information and data

432
Q

Test and Evaluation Documents

A

Project documents that describe the activities used to determine if the product meets
the quality objectives stated in the quality management plan

433
Q

Threat

A

A risk that would have a negative effect on one or more project objectives.

434
Q

Three-Point Estimating

A

A technique used to estimate cost or duration by applying an average or weighted average of
optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates

435
Q

Threshold

A

A predetermined value of a measurable project variable that represents a limit that requires action to be
taken if it is reached

436
Q

Time and Material Contract (T&M)

A

A type of contract that is a hybrid contractual arrangement containing aspects of
both cost-reimbursable and fixed-price contracts.

437
Q

To-Complete Performance Index (TCPI)

A

A measure of the cost performance that is required to be achieved with the
remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the
outstanding work to the remaining budget

438
Q

Tolerance

A

The quantified description of acceptable variation for a quality requirement

439
Q

Tool

A

Something tangible, such as a template or software program, used in performing an activity to produce a product
or result.

440
Q

Tornado Diagram

A

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables.

441
Q

Total Float

A

The amount of time that a schedule activity can be delayed or extended from its early start date without
delaying the project finish date or violating a schedule constraint

442
Q

Trend Analysis

A

An analytical technique that uses mathematical models to forecast future outcomes based on
historical results

443
Q

Trigger Condition

A

An event or situation that indicates that a risk is about to occur

444
Q

Unanimity

A

Agreement by everyone in the group on a single course of action.

445
Q

Update

A

A modification to any deliverable, project management plan component, or project document that is not under
formal change control

446
Q

Validate Scope

A

The process of formalizing acceptance of the completed project deliverables.

447
Q

Validation

A

The assurance that a product, service, or result meets the needs of the customer and other identified
stakeholders. Contrast with verification

448
Q

Variance

A

A quantifiable deviation, departure, or divergence away from a known baseline or expected value.

449
Q

Variance Analysis

A

A technique for determining the cause and degree of difference between the baseline and actual
performance.

450
Q

Variance at Completion (VAC)

A

A projection of the amount of budget deficit or surplus, expressed as the difference
between the budget at completion and the estimate at completion.

451
Q

Variation

A

An actual condition that is different from the expected condition that is contained in the baseline plan.

452
Q

Verification

A

The evaluation of whether or not a product, service, or result complies with a regulation, requirement,
specification, or imposed condition. Contrast with validation

453
Q

Verified Deliverables

A

Completed project deliverables that have been checked and confirmed for correctness through
the Control Quality process.

454
Q

Virtual Teams

A

Groups of people with a shared goal who fulfill their roles with little or no time spent meeting face to face

455
Q

Voice of the Customer

A

A planning technique used to provide products, services, and results that truly reflect customer
requirements by translating those customer requirements into the appropriate technical requirements for each phase
of project product development

456
Q

WBS Dictionary

A

A document that provides detailed deliverable, activity, and scheduling information about each
component in the work breakdown structure

457
Q

What-If Scenario

A

The process of evaluating scenarios in order to predict their effect on project objectives

458
Q

Work Breakdown Structure (WBS)

A

A hierarchical decomposition of the total scope of work to be carried out by the
project team to accomplish the project objectives and create the required deliverables

459
Q

Work Breakdown Structure Component

A

An entry in the work breakdown structure that can be at any level.

460
Q

Work Package

A

The work defined at the lowest level of the work breakdown structure for which cost and duration are
estimated and managed.

461
Q

Work Performance Data

A

The raw observations and measurements identified during activities being performed to carry
out the project work

462
Q

Work Performance Information

A

The performance data collected from controlling processes, analyzed in comparison
with project management plan components, project documents, and other work performance information

463
Q

Work Performance Reports

A

The physical or electronic representation of work performance information compiled
in project documents, intended to generate decisions, actions, or awareness