When construction of the structure is started, what must be posted at the building site.?
A Permit
Card is signed by the building inspector and is sent out with the permit
What are zoning regulations?
Bylaws that define and control what individual properties are used for and what type of physical development they may have.
How are zones specified?
Recreational
Residential
Commercial
Industrial
Each zone has specific requirements
What is a Building code?
legal document that sets out construction, demolition and occupancy requirements for building in order to protect the health, safety and welfare of the public
What do building codes not touch on?
Planning or zoning requirements
What are building codes intended for?
to compliment and not conflict with the regulations in other trades concerning the installation of, plumbing, gas, mechanical and electrical equipment.
Only professional that can design an, electrical, mechanical and building structure that is not covered in the building code
Engineer
What does a building permit display and confirm?
Has been applied for and is issued and that the permit is current.
Who signs a building permit?
By the building inspector and is sent out with the permit
Work not covered by building codes must be approved by who?
Engineer
What confirms that a building is safe and that there are no potential health or fire dangers?
Occupancy Pemit
Role of building inspector
Ensure work is done in compliance with building code and approved plans
Responsible to local municipality and, although not directly related to the project, act as an advisory and regulatory role with the superintendent and/or general contractor.
What kind of (mark) Ensures a design will perform safely.
engineers stamp
Subcontractor responsibilities?
Supplying materials as well as labour and they report to the general contractor’s superintendent.