Jeopardy Flashcards
The ___________ is developed by the PM at Milestone __________, and updated prior to each Milestone. It reflects the approved program being executed.
Acquisition Program Baseline; Milestone B
PAUC
Program Acquisition Unit Cost
A critical breach to the APB is ________% of the Current Baseline Estimate and _________% of the Original Baseline Estimate.
25%; 50%
When a program deviation occurs, the PM must notify the MDA _________ and follow up within _________ days to explain the reason for deviation and to provide a get well plan.
immediately; 30 days
The PM has the flexibility to work within the _________ between threshold and objective parameters.
Trade space
The Responsibility Assignment Matrix (RAM) shows the intersection of __________.
the Work Breakdown Structure (WBS) (what work needs to be done) and the Organizational Breakdown Structure (OBS) (who does the work)
The three step process to develop a Performance Measurement Baseline (PMB).
- Defining the work (WBS)
- Scheduling the work
- Allocating the budgets
__________ is: a formal review conducted jointly between the Government and the contractor, mandatory for all EVMS contracts, assesses validity of control account budgets, resources and time phasing
Integrated Baseline Review (IBR); must be done within 180 days of contract award
Two major types of EVMS surveillance performed by DCMA
- System surveillance
2. Contract surveillance
The _____ EVMS guidelines in ANSI/EIA-748 provide a framework to evaluate the adequacy of a contractor’s EVM system.
32
Your IT program requires stable software requirements and will be developed in one long release cycle. Which software development paradigm would you choose?
Waterfall
An open system facilitates operations on different hardware platforms, can save time and cost (when used properly), and ________.
promotes interoperability
The ________ is the current act covering the acquisition of information technology.
Clinger-Cohen Act (CCA)
Nunn-McCurdy Act
Congressional unit cost reporting requirements for Major Defense Acquisition Programs (MDAPs), i.e., ACATs ID/IC
You are the APM for a new C4I system, and must identify software critical requirements. What is generally the predominant critical requirement for your type of system?
Security
The four necessary software measurement activities that have been found to be universally employed by successful projects are _________, perform measurement, evaluate measurement, and establish and sustain commitment.
Plan measurement