JCT Section 4 Payment Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

When is the first Interim Valuation Date?

A

The first Interim Valuation Date is one month from the Date of Possession.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Where can you find the first Interim Valuation Date and intervals between the Interim Valuation Dates?

A

The first Interim Valuation Date and the intervals between Interim Valuation Dates may be stated in the Contract Particulars or agreed at the Pre-Contact Site Meeting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the Interim Valuation Date?

A

The date by which the Contractor should submit a Payment Application.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a Payment Application?

A

An application for payment submitted to the Employer’s CA/QS by the Contractor; stating the sum the Contractor considers to be due on the relevant due date and the basis on which that sum has been calculated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How long between the Interim Valuation Date and the Due Date and what is this time for?

A

7 days. In this time the Employer’s CA/QS may ask for more information and do a walk around site with the Contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When is the Interim/Payment Certificate due?

A

The Interim/Payment Certificate is due no later than 5 days after each due date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an Interim/Payment Certificate?

A

The Interim/Payment Certificate is issued by the Employer’s CA/QS to the Contractor stating the amount due to the Contractor and the basis on which that sum is calculated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What happens if an Interim/Payment Certificate is not issued by 5 days after the due date, where the Contractor has made a Payment Application?

A

The Contractor’s Payment Application becomes a Payment Notice and is treated in the same way as a Certificate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What happens if an Interim/Payment Certificate is not issued by 5 days after the due date, where the Contractor has not made a Payment Application?

A

The Contractor may at any time after the last date for the issue of the Interim/Payment Certificate give a Payment Notice to the Employer’s CA/QS stating the sum the Contractor considers to be due at the relevant due date and the basis on which that sum has been calculated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When is the final date for interim and final payment?

A

The final date for interim and final payment is 14 days from its due date except where the Contractor has issued a Payment Notice later than the last date for the issue of the Payment Certificate. In this case the final payment date is postponed by the number of days the Payment Notice was issued past the last date of the issue of the Payment Certificate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Pay Less Notice and when is it used?

A

A Pay Less Notice is a notice of intention to Pay Less than the sum stated in the Interim/Payment Certificate or the Payment Notice. It is given to the Contractor by the Employer’s CA/QS no less than 5 days before the final date for payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the 4 consequences of Employer’s failure to pay a sum or any part of it?

A

1) Simple interest.
2) Recoverable as a debt.
3) Right of suspension.
4) Loss and expense.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When is simple interest paid?

A

If an interim or final payment is not paid by its final date for payment, simple interest on that sum shall be added from the final date for payment until the payment is made.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does ‘recoverable as a debt’ mean and when does it occur?

A

If a payment is not made by its final date for payment, it becomes recoverable as a debt which means the Contractor may institute proceedings to recover the amount.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is right of suspension and when does it occur?

A

If the Employer fails to pay a sum to the Contractor by its final date for payment, the Contractor may suspend performance of any or all of those obligations until payment is made in full.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What loss and expense is the Contractor entitled to in relation to a sum not paid by the final date for payment?

A

The Contractor is entitled to claim a reasonable amount in respect of costs and expenses incurred by him as a result of exercising his right of suspension.

17
Q

When should adjustments to the Contract Sum be taken into account?

A

Additions or deductions shall be taken into account in the next Interim Certificate.

18
Q

Does the Contract Sum include VAT?

A

The Contract Sum is exclusive of VAT.

19
Q

Which act governs payment in construction?

A

The Housing Grant, Construction and Regeneration Act 1996 Part II, Section 109 - 112.

20
Q

What are the time restrictions for the final Contract Sum adjustment?

A

The Contractor must provide the Employer’s CA/QS with all documents necessary for the adjustment of the Contract Sum no later than 6 months after the issue of the Practical Completion Certificate.

The Employer’s CA/QS must prepare a statement showing all adjustments to the Contract Sum no later than 3 months from receipt of these documents.

21
Q

What is retention?

A

A percentage of the Contract Sum that is held back by the Employer to ensure themselves against Contractor failure. Usually set between 3-5%.

22
Q

When is retention released?

A

Full retention is held back until the Certificate of Practical Completion is issued.

After the Practical Completion Certificate is issued but before the Certificate of Making Good, half retention is released.

Full retention is released after the Certificate of Making Good is issued.

23
Q

What happens if the Contractor doesn’t supply information relating to the final account after 6 months from the issue of the Practical Completion Certificate?

A

The Employer’s CA/QS can give the Contractor one months notice requiring their supply after which time the Employer’s CA/QS can complete the statement of adjustment on the basis of the information in their possession.

24
Q

Which NEC4 option relates to payments under the Housing Grants, Construction and Regeneration Act 1996?

A

Option Y(UK)2.