JCT Intermediate Flashcards
What is the main difference between the JCT Intermediate Contract (IC) and the JCT Intermediate with Contractor’s Design (ICD)?
The contractor is responsible for both the construction and the design of certain aspects of the project under ICD, while under IC, the contractor is only responsible for construction.
What is the contractor’s responsibility under the JCT ICD regarding design?
The contractor is responsible for the design of certain parts of the project, in addition to the construction work.
How does the employer provide design information to the contractor under the JCT ICD?
The employer provides the contractor with the Employer’s Requirements, which outline the design specifications and expectations.
What is the procedure if the contractor’s design does not meet the Employer’s Requirements?
The contractor must revise the design to meet the Employer’s Requirements, often at their own cost and within a specified time frame.
Who is responsible for checking the contractor’s design under the JCT ICD contract?
The employer may review and approve the contractor’s design, but the contractor remains fully responsible for it.
What must the contractor submit to the employer before starting work on the design?
The contractor must submit design documents, including drawings and calculations, for approval by the employer or their representative.
What happens if the employer fails to approve the contractor’s design on time?
Delays in approval may lead to an extension of time for the contractor to complete the project.
How are design changes handled under the JCT ICD contract?
Design changes must be formally instructed by the employer, and the contractor must adjust the project accordingly, with possible cost and time adjustments.
How does the JCT ICD contract handle delays in design approval?
The contractor may request an extension of time for completion due to delays in design approval, which could affect the project’s overall timeline.
What is the role of the project manager under the JCT ICD contract?
The project manager typically manages the process, ensures design compliance, and may review and approve certain aspects of the design, but the contractor retains the responsibility for design quality.
What is the contractor required to provide in terms of design documentation?
The contractor must provide detailed design documents, including drawings, specifications, calculations, and any other relevant material for the employer’s approval.
What happens if the contractor’s design is defective?
The contractor is responsible for correcting defective designs at their own cost, and the employer may be entitled to claim damages if defects lead to additional costs.
How is the time for completion determined under the JCT ICD contract?
The contractor must submit a construction programme showing the planned completion dates, and this is subject to any agreed extensions of time due to delays.
How are interim payments made under the JCT ICD contract?
Interim payments are made based on the value of work completed, including the design and construction phases, with payments certified by the employer or project manager.
What are the circumstances under which the contractor can request an extension of time under the JCT ICD?
The contractor can request an extension of time for delays caused by events such as variations, design changes, or delays in receiving the employer’s approval or instructions.