1 A burndown chart tracks?
A. Work remaining across time
B. Accumulated cost on a Project.
C. Individual worker productivity.
D. Accumulated business value delivered to the customer.
A. Work remaining across time
When a Dev team determines that it has over-committed itself for a Sprint, who has to be present when reviewing and adjusting the Sprint work selected?
A. The Product Owner and Development Team.
A. The Product Owner and Development Team.
While under development the environment in which a product will be used changed. What is the effect on the product backlog?
A. It is archived and a new Product Backlog is created to take its place.
B. There is no effect, because it has to stay the same until the end of the project.
C. It evolves to reflect what the product needs to be most valuable
D. It is converted into a requirements specification to ensure stability
D. It is converted into a requirements specification to ensure stability