IT 221 Entire Course New Flashcards

1
Q

IT 221 Entire Course New

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-entire-course-new
For more classes visit
https://www.assignmentcloud.com/

IT 221 Entire Course New

IT 221 Week 1 DQS part 1 of 2

IT 221 Week 1 DQS part 2 of 2

IT 221 Week 1 CheckPoint: The Phases of the System Development Process

IT 221 Week 2 CheckPoint: Project Management in Everyday Life (GROUP ASSIGNMENT)

IT 221 Week 2 Assignment: Final Project—Project Overview- Appendix B

IT 221 Week 2 CheckPoint: Project Management in Everyday Life

IT 221 Week 2 CheckPoint: Final Project—Proposal

IT 221 Week 3 DQS part 1 of 2

IT 221 Week 3 DQS part 2 of 2

IT 221 Week 3 CheckPoint: Final Project—WBS

IT 221 Week 4 CheckPoint: Estimating Resources

IT 221 Week 4 Exercise: Toolwire Lab: Planning and Maintaining a Network

IT 221 Week 5 DQS part 1 of 2

IT 221 Week 5 DQS part 2 of 2

IT 221 Week 6 CheckPoint: Assessing Project Performance

IT 221 Week 6 Assignment: Final Project—Conditions, Structure, and Team Organization- Appendix B

IT 221 Week 7 CheckPoint: Creating a Change Control Document - Appendix D

IT 221 Week 7 DQS part 2 of 2

IT 221 Week 7 DQS part 1 of 2

IT 221 Week 8 CheckPoint: Managing Project Team Issues

IT 221 Week 8 Exercise Toolwire Lab: Mapping System Maintenance to Information System Building Blocks

IT 221 Week 8 Assignment: Final Project—Communication Plan

IT 221 Week 9 Capstone Discussion Question

IT 221 Final Project: Final Project

A

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-entire-course-new
For more classes visit
https://www.assignmentcloud.com/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

IT 221 Final Project: Final Project New

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-final-project-final-project-new
For more classes visit
https://www.assignmentcloud.com/

IT 221 Final Project: Final Project New

Measurement, Project Termination, and Final Draft Compilation

Resources: Appendixes A and B

Complete sections 9 and 10 of the IT/221N Final Project Template in Appendix B by summarizing the Implementation Phase and detailing a maintenance and project termination plan.

Compile each of the sections created in Weeks Two through Nine into one comprehensive document to submit as your final project. Be sure to make revisions to individual sections based on feedback that you have received from your instructor instead of just resubmitting the original documents.

Include all supplemental Gantt charts and diagrams related to your final project. Renumber the table of contents as needed.

Post your Final Project as an attachment

A

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-final-project-final-project-new
For more classes visit
https://www.assignmentcloud.com/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

IT 221 Week 1 CheckPoint: The Phases of the System Development Process New

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-1-checkpoint-the-phases-of-the-system-development-process-new
For more classes visit
https://www.assignmentcloud.com/

IT 221 Week 1 CheckPoint: The Phases of the System Development Process New

Use the information from the reading to complete this activity.

Identify the phases of the System Development Process (also referred to as the Systems Development Life Cycle (SDLC).

Specify the activities of each phase

A

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-1-checkpoint-the-phases-of-the-system-development-process-new
For more classes visit
https://www.assignmentcloud.com/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

IT 221 Week 2 Assignment: Final Project—Project Overview- Appendix B New

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-2-assignment-final-project-project-overview-appendix-b-new
For more classes visit
https://www.assignmentcloud.com/

IT 221 Week 2 Assignment: Final Project—Project Overview- Appendix B New

Resources: Appendixes A and B

Complete the following sections of the IT/221N Final Project Template in Appendix B:

Project Definition

Project Executive Summary, including the impact of the triple constraints

Project Overview

Course Syllabus

IT/221N Version 3

12

Post only the identified sections as an attachment.

A

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-2-assignment-final-project-project-overview-appendix-b-new
For more classes visit
https://www.assignmentcloud.com/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

IT 221 Week 3 CheckPoint: Final Project—WBS New

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-3-checkpoint-final-project-wbs-new
For more classes visit
https://www.assignmentcloud.com/

IT 221 Week 3 CheckPoint: Final Project—WBS New

Use Microsoft® Project to develop a Work Breakdown Structure (WBS) for your project defined in Week Two.

Include a 100- to 150-word description of how and why you would use a WBS in a project.

A

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-3-checkpoint-final-project-wbs-new
For more classes visit
https://www.assignmentcloud.com/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

IT 221 Week 4 CheckPoint: Estimating Resources New

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-4-checkpoint-estimating-resources-new
For more classes visit
https://www.assignmentcloud.com/

IT 221 Week 4 CheckPoint: Estimating Resources New

You are managing a project and you have an $850,000 budget. For the project, your resources include four developers and one project manager. You can assume that the average workweek per person is 40 hours and that the developers earn $30 per hour while the project manager will receive $50 per hour. Without knowing the deliverables, estimate how long you can keep these resources with the budget you have.
HOW LONG CAN THIS PROJECT RUN???
Compose your response to the scenario.

A

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-4-checkpoint-estimating-resources-new
For more classes visit
https://www.assignmentcloud.com/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

IT 221 Week 5 DQS part 1 of 2 New

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-5-dqs-part-1-of-2-new
For more classes visit
https://www.assignmentcloud.com/

IT 221 Week 5 DQS part 1 of 2 New

  1. Discussion Questions

Is a project that is on time and on budget a successful project? Why or why not? How do we determine that a project is successful?

Log in to your student Web site.

Click on Week Five, then click on the link to the Toolwire lab. A new window will open containing a

Course Syllabus

IT/221N Version 3

17

description of the lab. Scroll to the bottom of the page and click the Lab Access link to begin the lab.

Complete the lab assignment as indicated.

Answer the following: Based on your experience in the Toolwire Lab, what could the impact be on the quality of the project (the delivery date, the budget, and overall quality of work produced) if you do not select the best possible project team members? If you did not analyze risks and requirements thoroughly enough? Finally, what would the impact on quality be if you did not have an accurate design plan?

A

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-5-dqs-part-1-of-2-new
For more classes visit
https://www.assignmentcloud.com/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

IT 221 Week 6 Assignment: Final Project—Conditions, Structure, and Team Organization- Appendix B New
Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-6-assignment-final-project-conditions-structure-and-team-organization-appendix-b-new
For more classes visit
https://www.assignmentcloud.com/

IT 221 Week 6 Assignment: Final Project—Conditions, Structure, and Team Organization- Appendix B New

Resources: Appendixes A and B

Determine the necessary quality assurance details related to your approved project. These details will define the project conditions, structure, and organization.

Use this information to complete sections 5, 6, and 7 of the IT/221N Final Project Template in Appendix B.

Post only the identified sections as an attachment

A

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-6-assignment-final-project-conditions-structure-and-team-organization-appendix-b-new
For more classes visit
https://www.assignmentcloud.com/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

IT 221 Week 7 CheckPoint: Creating a Change Control Document - Appendix D New

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-7-checkpoint-creating-a-change-control-document-appendix-d-new
For more classes visit
https://www.assignmentcloud.com/

IT 221 Week 7 CheckPoint: Creating a Change Control Document - Appendix D New

Using the Change Control Template Document in Appendix D, create a Change Control Document to address the possible problems defined in your current project, and propose a logical change that will fit with your approved project

A

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-7-checkpoint-creating-a-change-control-document-appendix-d-new
For more classes visit
https://www.assignmentcloud.com/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

IT 221 Week 8 Assignment: Final Project—Communication Plan New

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-8-assignment-final-project-communication-plan-new
For more classes visit
https://www.assignmentcloud.com/

IT 221 Week 8 Assignment: Final Project—Communication Plan New

Resources: Appendixes A and B

Determine the necessary details related to scope changes and communication for your approved project.

Complete section 8 of the IT/221N Final Project Template in Appendix B.

Post only the identified sections as an attachment.

A

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-8-assignment-final-project-communication-plan-new
For more classes visit
https://www.assignmentcloud.com/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

IT 221 Week 9 Capstone Discussion Question New

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-9-capstone-discussion-question-new
For more classes visit
https://www.assignmentcloud.com/

IT 221 Week 9 Capstone Discussion Question New

As a project manager, you are asked to facilitate a lessons learned session as part of the project termination process. How would you facilitate this session and what are some guidelines you would use? How would you incorporate and document the information gleaned from this session into future project plans and tools?

A

Check this A+ tutorial guideline at
https://www.assignmentcloud.com/it-221/it-221-week-9-capstone-discussion-question-new
For more classes visit
https://www.assignmentcloud.com/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly