IRM ERM M1U3.4 Risk analysis Flashcards

1
Q

ISO 31000 (2018) The purpose of risk analysis

A

ISO 31000 (2018) states:

‘The purpose of risk analysis is to comprehend the nature of risk and its characteristics, including, where appropriate, the level of risk.’

risk analysis provides an input into risk evaluation, to decisions on whether risk needs to be treated and how.’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Chartered Institute of Internal Auditors (CIIA, 2005) - Risk analysis

A

‘The systematic use of available information to determine the likelihood of specified events occurring and the magnitude of their consequences, i.e. their impact.’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Orange Book:2020 and COSO:2017 - Risk analysis

A

Meanwhile the Orange Book:2020 and COSO:2017 place risk analysis within the broader subject of risk assessment. Risks are analysed to:

prioritise risks for treatment in terms of their significance.
achieve consistent perceptions of significance across the organisation.
inform decisions on how scarce resources are allocated.
inform decisions about whether to proceed with a new strategy, project, or investment, and so on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

To determine the importance of your risks, you could:

A

To determine the importance of your risks, you could:

look at past records.
look at personal relevant experience (and intuition).
look at industry-relevant experience of the risk.
look at published literature on the risk.
do some testing or experiments (for example, market research).
use economic or statistical models to make forecasts.
use experts in the area of that risk to make judgements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

To rate the importance of risks you could compare the risk’s:

A

To rate the importance of risks you could compare the risk’s:

Potential impact to your objectives
Potential likelihood of happening
Relative velocity
Relative vulnerability of different parts of the organisation the risks are linked to
Relative exposure of different parts of the organisation the risks are linked to
Proximity
The level of action or control needed to manage the risks to a desired (target) state
Relative difficulty of managing those risks
Relative influence of a single risk on other risks (dependency / cascade factor).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Risk prioritising techniques – impact. Qualitative, quantitative, scale

A

Impact can be measured using simple to complex approaches - from purely qualitative, descriptive levels of impact (low to high) to quantitative analytical data collection and analysis techniques, such as Value at Risk or Monte Carlo simulation.

However, most organisations take a composite approach, using the risk criteria, and measuring impacts against objective in qualitative scales from low to high, with some quantitative measures to provide consistency in the approach, so for example, the high financial impact might be greater than $1m while a low financial impact might be less than $1,000.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Risk prioritising techniques – opportunity Ex Reputation, Retention

A

When rating opportunities, the majority of the scales here can be considered from a positive perspective. For example, for reputation, instead of complaints the scale could be measured in compliments, for finance, it could be gain instead of loss, for staff it could improving retention and recruitment.

The point is, when opportunities have been identified, you can measure these in the same ways as threats, which embeds the identification, analysis and management of both the upside and downside risks with the same approach, rather than trying to introduce two different approaches.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Risk prioritising techniques – likelihood. Probably & Frequency

A

Likelihood is a term which tries to measure the chances of a specific event occurring. It captures the expected probability and frequency of an event:

Probability – Likelihood can be expressed numerically as value between 0 and 1 (or 0% and 100%) used as a probability measurement, such as: ‘There is a 2% chance of rain in the city of Jeddah on any one day during the next month.’ Probability is commonly used for risks that might only occur once in the timescale considered.

Frequency – Likelihood can also be expressed numerically as a frequency measurement, such as: ‘In just one day in 2005 Hurricane Katrina resulted in a one-in-a-hundred-year flood to New Orleans.’ This frequency measure could be converted to a probability measure as follows: the chances tomorrow of another Hurricane Katrina severity flood hitting New Orleans is 1 day × 365 days in a year × 100 years, or a 0.003% chance. Frequency is commonly used for risks that might occur more than once in the timescale considered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Prioritising techniques – impact and likelihood. X&Y Placement . Simple vs Complex

A

It does not matter which axis impact or likelihood is placed; you will find that approximately 50% of organisations who use this prioritisation method have impact you the x-axis whereas the other 50% have it on the y-axis of the matrix,

Some organisations have separate matrices for opportunities opposed to threats, whereas others roll both together through ensuring the descriptions regarding the potential impacts of the risks can be both positive and negative.

Some organisations keep their risk matrices very simple with no gridlines and few metrics, whereas others make them more complicated, numbering all positionings on the grid and colouring in different cells different colours, aimed to induce a certain reaction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Impact and action

A

One way to deal with the problem of analysing likelihood is to stop using it, or only use it as and when it is truly applicable and useful (for example, engineering risks). Instead, alternative scales can be used against impact, such as the amount of action needed to bring the risk to an ‘acceptable’ level.

This method is usually termed the ‘Impact versus action’ and is used because it:

avoids unnecessary debate on likelihood.
prioritises attention on the risks that require immediate focus.
prompts robust discussion and action regarding the extent to which risks truly need to be managed.

The use of the impact versus action map allows for risks that would traditionally be considered in the red zone, and therefore ‘unacceptable’ to be given the correct focus, whereas other risks that have a high impact on the business and need lots of action, can be highlighted. In this scenario, risks such as Covid 19 would be given greater attention, because they would be highlighted as ones which would have a significant impact on an organisation, but in most cases would need a lot of action to manage the risk to an acceptable level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Risk Proximity - Covid vs Nuclear Project Example

A

The general definition of risk proximity is how close we are to a risk occurring, or how soon can a risk happen.

For example, if we are considering the ill health of a key member of staff, especially during the Covid pandemic, this could mean a close proximity,

whereas if you are considering certain project risks on the decommissioning of a nuclear power station, these might have a distant proximity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Risk velocity

A

Another ‘timing’ term for risk is risk velocity. Risk velocity measures how fast a risk can impact an organisation once it occurs. Hopkin and Thompson also refer to risk velocity as the ‘timescale of risk impact.’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Risk clockspeed

A

Risk clockspeed
A further ‘timing’ term is the risk clockspeed. Risk clockspeed refers to the rate at which the information necessary to understand and manage a risk becomes available. There are two main classes of clockspeed:

Slow Clockspeed Risks are those where enough thinking time is available (‘Sufficient‟ is context related)
Fast Clockspeed Risks are at or close too real time
The Risk Clockspeed Window is the range between how well organisations can deal with Fast Clockspeed Risks and Slow Clockspeed Risks and still function effectively

A final note is that some organisations use the above terms interchangeably.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Levels of risk

A

Hopkin and Thompson note the levels of risk rating in chapter 1. The three main terms used by Hopkin and Thompson are:

Inherent – this is the level of risk before any controls have been put in place or actions taken to manage the risk and change the likelihood or impact. This is useful to understand the real exposure an organisation has to a risk should the controls fail. It also helps to identify when risks might be over or under controlled. This rating level is sometimes also called ‘raw,’ ‘gross’ or ‘total.’
Current – this is the level of risk, taking account of the current controls in place to manage it, working at their current effectiveness. This rating level is sometimes called ‘net’ or ‘residual.’
Target – this is the level of risk that is desired to bring the risk to an acceptable level. This rating level is often missed by organisations, but it is an important consideration in how much effort is needed to manage risks to an acceptable level.
Inherent rating is helpful when considering key or principal risks within an organisation. It is less useful when considering risks further within the organisation.

In summary the risk rating terminology comparisons are:

Inherent is usually the same as total, gross, raw, initial
Current is usually the same as net, some versions of residual
Target is closely linked to risk appetite.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

More than one risk impact

A

Note that a risk can have more than one impact. Using the example above, consider the vehicle crashing into the works and damaging assets and personnel risk that the organisation maintaining the road network faces – remember that this is despite all the measures already in place to manage the risk. Looking at the impact should the risk occur, a reasonable rating could be:

Safety – High (one fatality)
Financial – Moderate ($100k to $1m)
Production – Minor (3hrs – 1-week lost time)
Reputation – Insignificant – (<50 negative comments in social media)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Double-sided matrix.

A

When evaluating risks, the use of the heat map or RAG chart usually relates to threats only. To capture opportunities, some organisations use a double-sided matrix.

This type of matrix can be presented in a variety of ways. In some cases, upside risk is presented on the right of the matrix with downside risk on the left. With upside risks, the aim is to move the risk to the top left hand-corner of the above upside risk matrix, by increasing the likelihood and/or desirable consequence.

17
Q

Risk evaluation

A

The central idea behind risk evaluation is that after analysing a risk to estimate its effect on our objectives, we then must decide whether to:

respond to the risk in some form to reduce our exposure (hazard risk), to reduce the level uncertainty (control risk), or modify the investment (opportunity risk); or
simply tolerate the level of risk that we have estimated without any further action.
So, risk evaluation is, in effect, a decision point in which we decide whether to respond or not to respond to the risk.

18
Q

Risk Appetite Variations Across Organisations & Functions

A

Risk appetite varies from organisation to organisation – some are more risk taking (or risk aggressive) and others are more risk averse. Even within the same organisation, the appetite for risk taking will vary between different functions.

An ERM approach requires organisations to understand their overall appetite for risk and then apply a consistent approach across the organisation. The organisation can then make consistent decisions about how to respond to a particular risk. We will discuss risk responses in unit 6.

Risk appetite must be identified within the context of the organisation’s overall business strategy, tactics, operations, and its need to comply with relevant legislation and regulation. However, boards are primarily concerned with business drivers and strategic imperatives, leading to the possibility of decisions being taken that do not fully consider the actual levels of risk exposure, or the organisation’s willingness to tolerate such levels of risk

19
Q

HILP risks

A

Conversely, risks that have a very low likelihood, but very high impact, are often not given the attention they deserve. These risks are often called High Impact Low Probability or HILP risks, which, because of their very low likelihood, have been perceived as risks that do not need much attention. An example of a HILP risk would be Covid 19. We can see that a very low likelihood does not mean a risk will not occur.

20
Q

Decision making challenges with coloured zones on a matrix Ex road maintenance works

A

However, using likelihood in the scoring and coloured zones on a matrix can cause problems when making decision on how much attention should be given to risks. This can be seen in cases where you might have some risks that have a high likelihood and a high impact, which are within your risk appetite.

For example, an organisation that undertakes maintenance works on major road networks that are in use by the public, might have a risk relating to the impact of vehicles on their works, which would damage assets and injure members of the workforce. The organisation will have countless controls in place to protect their assets and workforce, from barriers, signs, and speed limits, to training, guidance, and equipment. However, there is still quite a high likelihood that a member of the public has an accident in the road works, which would affect the assets and workforce.

21
Q

Levels of risk with Auditors, HS and Risk functions

A

Different professions view these aspects of risk at different levels. For example, internal auditors will start with the gross or inherent risk and audit the controls in place. Risk managers prefer to start with the current level of risk and review what can change this level. Health and safety practitioners prefer to undertake risk assessment with the current controls in place, ie at the current level.

22
Q

ALARP

A

When seeking to establish the target level of risk, a concept that is often used by health and safety practitioners is to reduce the risk to a level that is ‘as low as reasonably practicable’ (ALARP). ALARP is one of the fundamental principles of risk management for health and safety risks. It refers to managing risk to the point where the cost of additional controls would exceed the benefits

23
Q

Risk attitude vs risk appetite

A

The difference between risk attitude and risk appetite can be described as follows: risk attitude is concerned with the criteria surrounding risk, and risk appetite is concerned with the amount of risk required to achieve objectives.

24
Q

4Cs of Risk Matrix

A

It is becoming more common for a risk attitude matrix to contain four sections.

These sections can be represented by the 4Cs of comfort, cautious, concerned and critical.

25
Q

Universe of Risk - Audit & Risk Perspective

A

The ‘universe of risk’, or those risks of real significance to the board, will be very restricted for such a risk-aggressive organization.

The phrase ‘universe of risk’ is often used by internal auditors to identify audit priorities. Working with such a closed or restricted ‘universe of risk’ will increase the chances of an unidentified significant risk impacting the organization. Each different stakeholder will have a different ‘universe of risk’ and the risk manager is likely to have a ‘universe of risk’ that includes all of the risks that have already been identified, plus any emerging risks that are starting to appear.

26
Q

Risk Perception

A

When undertaking risk assessment exercises, it is often the case that different attendees at the workshop will have different views of the risk.

The perception of risk by individuals will be affected by a number of factors

Different views on the importance of a risk can be present at different levels of seniority within the organization. It is useful for the risk assessment process to draw opinions from all levels of management, so that different perspectives of a risk can be identified.

Again, the benefits of this approach are better risk communication, fuller risk understanding and the identification of appropriate and practical control measures.

27
Q

Risk Attitude ISO

A

However, risk attitude is the organization’s approach to assess, pursue, retain or avoid risks.

Some organizations may be considered to be risk averse, whilst others will be risk aggressive.

The attitude of the organization to risk will depend on the attitude of the board, the nature of the sector and the marketplace within which it operates.