Introduction Flashcards
What does Prince2 stand for?
Projects In Controlled Environments
What have the 3 main revisions of Prince2 been?
1975 - Promtpt
1989 - Prince (focus on IT projects)
1996 - Prince2 (suitable for all projects regardless of size and environment)
What are the 4 integrated elements of Prince2?
7 Themes - Ingredients
7 Processes - Instructions
7 Principles - Good practises/Why
Project Environment - Tailoring
What are the 3 core management products within Prince2?
Baseline products - e.g business case, PMP
Records - logs, register, configuration records
Reports - Prince2 recommended reports
What’s the difference between projects and BAU?
Projects: Bring change Higher risk Project life cycle Six major variables Deliver products
BAU: Repetitive Easy to f/c Easy to improve efficiences Low risk
What is Prince2 definition of a project?
A temporary organisation that is created for the purpose of delivering one or more business products according to an agreed business case
What are the 7 themes?
Business case:
Justifies project, documents project f/c benefits.
Organisation:
Roles & responsibilities, accountability
Plans:
Project, stage and team plans.
Risk:
How to manage risks
Quality:
Quality approach
Meet requirements, standards
Change:
How to manage change
Progress:
Monitor & controlling the project successfully
List the 7 themes of Prince2
Business case Organisation Plans Risk Quality Change Progress
What are the 7 processes?
Starting up a project (SU) Directing a Project (DP) Initiating a Project (IP) Controlling a Stage (CS) Managing Product Delivery (MPD) Managing a Stage Boundary (SB) Closing Project (CP)
What is SU?
Starting up a project (SU):
Should the project go ahead? Viable?
Triggered by project mandate.
Project brief is outputted
What is DP?
Directing a Project (DP): Analysis of project brief undertaken Used to make decisions about the projects future Used throughout lifecycle Project Board has exclusive access
What is IP?
Initiating Project (IP):
Detailed analyis of whole project undertaken to answer:
Who, what, when, where, why, how much etc.
Project Initiation Document is outputted from this process.
What is the PID?
Project Initiation Document:
Prince2 version of the PMP
Collection of all key documents required to manage the project
Reviewed by project board in DP (directing project) to ensure viability
Requires approval before project can progress
What is CS?
Controlling a stage (CS):
PM uses this stage to allocate work
Work allocated in work packages
Corrective action taken where required
Progress reported on
PM provides highlight reports to the project board via the DP theme
Captures and deals with risks/issues/changes
What is MPD?
Managing Product Delivery (MP)
Accept work from the PM
Complete work
Handback to PM once completed
What is SB?
Managing a Stage Boundary:
When the end of a stage is nearing
Requires planning of the next stage
Progress of the current stage should be reported to the project board
Project board need to approve plan for next stage and the end of stage report.
What are the two reports used to report progress between the PM/Project Board?
Highlight Report
End of Stage Report
What 3 processes are repeated until project closure?
CS (Controlling Stage)
MPD (Managing Product Delivery)
Managing a Stage Boundary (SB)
What is CP?
Closing Project (CP)
Formally handover the products
Review the project and how it was managed
Review performance
Project Board have to authorise project closure
What are the 7 principles?
Continued Business Justification Learn From Experience Defined Roles & Responsibilities Manage By Stages Manage By Exception Focus on Products Tailoring
What does the continued business justification principle refer to?
Must be a valid business case to justify project
Must remain valid throughout the project
Should be reviewed regularly
What does LFE mean?
Learn From Experience Emphasise good practise Avoid bad practises Continually improve Become more mature
What is the roles and repsonsibilities principle?
Who’s doing what
Accountability
What is the principle of managing by stages?
Doing work to progress the project then reviewing the work/progress May be at predetermined stages May follow the project life cycle Undertaken by project board Go / No go decision made
What is managing by exception (principle?
Project board only meeting at the end of each stage to give authority to proceed
Set tolerance for next stage which the project can act within
Only meeting at predetermined stages unless there is an emergency etc.
What are tolerances?
Permissable deviation from the plan that is allowed before it needs to be escalated
What is the focus on products principle?
Discuss what products to build
Standard at which they’re to be built
Embodied in product based planning technique, plans and quality themes
What is the tailoring principle and what does it ensure?
Being aware of the project context, environment and size
Tailoring Prince2 to meet the project needs
Ensures the right level of governance, planning and control IAW prince2 is implemented on the project given its nature.
What can tailoring be applied to?
Processes - combined or adapted
Themes - Applied using appropriate techniques
Roles - Combined or split in a way to ensure accountability and prevent conflicts of interest
Management Products - Combined or split into any number of elements
Terminology - Changed to suit other standards or policies
What is the PM responsible for in relation to tailoring?
Responsible for idenitfying the level of tailoring required and how it will be implemented on the project.
PM should then document this in the PID (Project Initiation Document), control section.
This then requires approval from the project board.
Who may support/advise the tailoring of the project?
PM/Project Board may take advice from:
Project assurance
Project support
Team managers
Centre of excellence
What are the 6 variables of a project that require management?
Timescales Costs Quality Scope Benefits Risks
In relation to the theme, organisation, what does prince2 assume is the structure / who are the mains stakeholder representatives?
Customer supplier environment
Customer & supplier
What is the method and what viewpoint is it written from?
Outlines how the project will be delivered.
Written from customer view point.
What is the customer and what is their view on the project?
Persons/Organisation who fund the projcet.
Business and user perspective
Focuses on value for money and the realisation of benefits
What is the user and what are their priorities?
User is:
Concerned with quality and functionality of the products
Will be using the project outputs or maintaining products
What is the supplier & what view do they provide on a project?
An internal or external person or group that supplies skills or products.
Focus on supplier aspect.
What are the four levels of management?
Corporate / programme management or customer
Project Board (Directing) Project Manager (Managing) Team Manager (Delivering)
What are the corporate / programme mgt or customer responsible for?
Provide the project mandate
Appoint the project executives
Set project tolerances
What is the project board & their responsibilities?
Make decisions r.e the project Provide strategic direction Report to the customer/organisation 3 key roles within the project board: Executive (sponsor) Senior user (represents users) Senior Supplier (represents supplier/s)
What is the project manager & their responsibilities?
Managing the project on day-to-day basis
Ensure the project produces the required products
What is the team manager & their responsibilities?
Executes assigned work packages
Builds and delivers required products
With reference to the project board, what is the executive?
AKA the sponsor
Accountable for the project being a success
Represents the business
Owns the business case
Responsible for funding
Focus on business strategy and benefits realisation
With reference to the project board, what is senior user?
Represents those who use the products
Ensure user needs are specified and met
Ensure the user can realise the benefits
Concerned with quality and functionality
With reference to the project board, what is senior supplier?
Represents the internal/external suppliers providing skills or products required for the project.
What are the project board collectively responsible for / expected to do?
Monitor risks
Authority to commit and manage resources
Make decisions using the DP (directing project) process to guide the team.
When do the board meet?
At the end of each project stages to make decisions r.e progress and viability.
Apart from this, they meet by exception.
Rely on highlight reports from the PM
The project board need to be confident that?
The project manager is in control
Project is progressing as expected/reported
With relation to project assurance, what are the project boards responsibilities?
Executive:
Focus on risk and finance assurance
Senior User:
Ensures products meet user requirements.
Senior Supplier:
Ensures suppliers are following quality standards
Ensures product descriptions are correct
Can the project boards assurance responsibilities be delegated? If so, who can this role be delegated to?
Yes:
It can be delegated however, it cant be delegated to the PM, project team or team managers.
If delegated, highlight reports should be used to provide confidence to the project board.
What are the PMs main responsibilities?
Plan the project and the stages within it
Allocate work packages
Monitor progress using checkpoint reports
Take corrective action where required
Report progress using highlight reports
Prepare benefits management approach
What are the team managers main responsibilities?
Takes direction from PM
Agrees work packages with the PM
Reports progress via checkpoint reports
What are the project teams main responsibilities?
Managing registers and logs
Collating and analysing data
Updating the schedule and plans
May also include procurement, finance and configuration support.
Role may not be required and may be undertaken by PM
What is the change authority and what is their main responsibilities?
Decide whether change requests are implemented or not
Accept / Reject / Defer changes
Assess changes
Usually the project board is responsible however this may be delegated or there is a separate group of people responsible for change.
How may the project board roles be merged?
Executive:
Executive
Senior user
Assurance
Project Manager:
PM
Project Team
Team managers
Senior Supplier:
Project Assurance
Suppliers
What are the three primary stakeholder interests?
User
Business
Supplier
What is a stakeholder?
individual, group or organisaiton that can be effected by or effect or perceive to be effected by a project and its activities.
When are stakeholders identified and analysed?
Start Up (SU) and Intiation of the project (IP)
Whena are stakeholders engaged?
Throughout the project life cycle.
What does the communication management strategy define?
Defines means and frequency of communications.
What 3 things must the project do to be a Prince2 project relating to organisations & structures.
Define organisation structure and roles
Document rules for delegates and change authority
Define approach to engaging and communicating with stakeholders.
What are the two organisational products/documents required?
PID - project initiation document
Communications management approach
Which role makes sure the right people are involved?
Project assurance
How does Prince2 define the business case?
The BC establishes mechanism to judge whether the project is (and remains) viable, achieveable and desireable to support decision making in its investment.
When referring to the business case, what does desirable mean?
Examing cost beenfit balance
Benefits should outweigh costs and risks
Taking account of risks
When referring to the business case, what does viable mean?
Satisfied and confident that the products/scope required can actually be produced.
When referring to the business case, what does achieveable mean?
Satisfied that the products produced will achieve the expected benefits.
When is the business case produced / developed?
During the pre project / intiation stages of the project life cycle Done during the following processes: SU = Starting Up the project DP = Directing the Project IP = Initiating the Project
Is the business case included in the project brief?
If so, what does this allow?
Yes
This allows the project board to have a clear understanding on the reasoning and business option to progress the project.
When is the business case refined after it has initially been accepted?
Initiation Stage / IP (Initiating Project)
Business case is refined using the information from the Proejct Plan which is then formed apart of the PID (project intiaition document)
At what other points in the project life cycle is the business case reviewed and updated? What is updated?
End stage assessments are done by the project board to ensure the Business Case remains viable
At the end of each project stage the business case is also updated to reflect the most accurate information r.e costs, schedule, risks etc.
What if the business case is invalid or becomes invalid during the project?
The project should be stopped
When are the business case f/c benefits reviewed?
These are reviewed apart of the benefits management approach where a comparison of actual benefits realised are made in comparison to what was outlined in the business case.
What are outputs?
Outputs are the product/deliverables of the project
What are outcomes?
The result of the change that the project outputs bring.
What are benefits?
The tangible or intangible measurement at which the project brings to the business.
When referring to the business case, what does desirable mean?
At an end stage assessments
List and explain the 9 contents within the business case?
Executive Summary - Provides a summary to senior management on the project
Reasons - Describes problem trying to solve or the new opportunity. Describes the current situation.
Options - Do nothing, Minimum, Maximum. Analysis and recommendation provided.
Benefits - Expected benefits to result from executing the project.
Disbenefits - Bad things that might happen as a result of the project
Timescales - Duration of project, how long it will take to realise benefits.
Cost - Total costs of running project, operational and maintenance costs. Funding arrangements
Investment Apprailsal - How VFM is achieved, financial appraisals of each option
Major Risks - Major risks impacting business case. High probability and impact, red risks.
What is the benefits management approach and when is it produced?
Produced in the IP process
Decribes how benefits will be benchmarked and measure benefits, analyse progress, document and f/c benefits.
What are the 4 aspects a projcet must follow to be a Prince2 project?
Create and maintain a business justification for the project, usually a business case
Review and update the business justification throughout the project
Define the management actions necessary to create the outcomes and realize the benefits and
Define and document the roles and responsibilities for the business case and benefits management approach.
In a customer/supplier environment, who has a busienss case?
Both the supplier and the customer.
Supplier - Justifies their involvement in the project
Customer - Justifies the reasoning and need for the project
Who owns the business case and which is most important?
Project Executive owns the customers business case which is the basis of the project and drives decision making.
What is the Prince2 definition of plans?
A document describing how, when and by who a specific or set of targets will be achieved.
Targets refer to the projects products, baselines, timescales, costs, quality and benefits.
What is the Prince2 purpose of plans?
The facilitation of communications and control by defining means of delivering products (who, what, when, where, why, how, how much).
What are the 4 levels of the project organisation/
Customer/Organisation
Project Board
Project Manager
Team Manager
What is the first plan to be produced on a project?
Initiation plan
Developed in the SU (starting up) process
Brief and high level
Shows key dates and brief activities
What plans do the project board require?
Project Plan and/or Programme plan if applicable.
This will outline key activities, critical path and milestones on the project.
What plans do the PM require?
Stage Plans (Delivery)
Provide more detail to allow the PM to manage the project day to day.
Timescales, resource requirements, costs, critical path etc.
What plans do the team managers require?
Team Plan
Provide further detail than the stage plans. Provide more detail r.e work packages etc.
What is the exception plan?
Something managed and requested by exception and requested by the project board if the project is exceeding initial plans and tolerances.
Project board requests, PM produces.
What is the Project Plan, when is it created and updated?
How does the project plan relate to schedules?
Provides an overview of the entire project
Produced in the initiation of the project (IP) process.
Part of the Project Plan is schedules and key decision points are identified in the plan. This is then used to define stage boundaries.
Updated at the end of stages