Interpretation and Definition Flashcards

1
Q

1.1 Government Law

A
  • Hong Kong law
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

1.2 Singular, plural, masculine and feminine

A
  • Singular includes plural
  • Masculine includes feminine and neuter
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

1.3 Method of reference to clauses and articles

A

Unless stated otherwise a reference in the Articles, the Conditions or the Appendix to any clause means that clause of the Conditions and a reference to an Article means that Article of the Articles of Agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

1.4 Articles of Agreement, the Conditions and the Appendix are to be read as a whole

A
  • Reading as a Whole: All three sections (Articles, Conditions, and Appendix)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

1.5 Clauses divided into sub-clauses to be read as a whole

A
  • Reading as a Whole: The sub-clauses should be read as if there were no division between them, meaning their meaning is interconnected and dependent on each other.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

1.6 Definitions

A
  • Scope of Definitions: These definitions apply to Articles of Agreement, the Conditions and the Appendix
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Appendix

A

the Appendix to the Conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Architect

A

The person named as the Architect in Article 3, or any successor appointed under Article 5.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Articles or Articles of Agreement

A

The Article of Agreement to which the Conditions are annexed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Commencement Date

A

the date stated in the Appendix for the commencement of the Works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Communication

A

The giving, submitting or issuing of, without limitation, any agreement,approval, authorisation, certificate, confirmation, consent, decision, delegation,direction, dissent, determination, endorsement, instruction, notice, notification, opinion,request,requirement or statement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Completion Date

A

the date stated in the Appendix by which the Works or a Section are to be completed or such later date to be fixed by the Architect under clause 25.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Conditions

A

the Conditions of Agreement and Schedule of Conditions of Building Contract for use in the Hong Kong Special Administrative Region, Private Edition Without Quantities and any special Conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Contract

A

the Articles of Agreement, the Appendix, the Form of tender submitted by the Contractor, the Employer’s letter of acceptance of the Contractor’s tender and Special Conditions, if any, the Conditions, the Contract Drawings, the Specification and the Schedule of Quantities and Rates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Contract Drawings

A

The drawings referred to in the first and fourth recitals of the Articles and enumerated as such in the Specification.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Contract Sum

A

The sum stated in Article 2, or such other sum that becomes payable in accordance with the Contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Contractor

A

The person named as the Contractor in the Articles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Contractors’ All Risks Insurance of the Works

A
  • Scope of Coverage: The Works, Temporary Works, Materials and Goods
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Date for Possession of the Site

A

The date or dates for the possession of the whole or parts of the Site stated in the Appendix under the reference to clause 23.1.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Date of Substantial Completion

A

The date stated in the Substantial Completion Certificate for the Works or a Section, issued by the Architect under the reference to clause 23.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Day

A

A calendar day and includes Sundays and other days which are general holidays by virtue of the General Holidays Ordinance (Chapter 149, Laws of Hong Kong)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Defects Liability Period

A

the period stated in the Appendix under the reference to clause 17.3, commencing on the day after the Date of Substantial Completion of the Works or a Section or the day after the Relevant Date of Substantial Completion of a Relevant Part.

23
Q

Defects Rectification Certificate

A

A certificate issued by the Architect to the effect that all defects, shrinkages and other faults have been rectified in accordance with the Contract, as described in clauses 17.4 and 17.5

24
Q

Direct loss and/or expense:

A

the monetary consequences that flow naturally without other intervening cause and independently of special circumstances because of the direct consequences of a qualifying event and which are not otherwise reimbursed to the Contractor.

25
Q

Domestic Sub-Contractor

A

a person, other than a Nominated Sub-Contractor, to whom the Contractor sub-lets any part of the Works and includes a labour only sub-contractor.

26
Q

Employer

A

the person named as the Employer in the Articles.

27
Q

Engineer

A

a person engaged as a member of the Employer’s design team for the design and supervision of one or more of the geotechnical, civil, structural or building services elements of the Works, as referred to in clause 1.7

28
Q

Excepted Risks

A

(a) War and Civil Unrest
(b) Architect’s Design
(c) Architect’s or Employer’s Negligence
(d) Nuclear Events
(e) Sonic Booms

29
Q

Final Contract Sum

A

the sum resulting from the adjustment of the Contract Sum in accordance with the Contract.

29
Q

Final Certificate

A

A document issued by the Architect that states two key figures:
- Final Contract Sum: total amount of money due to the Contractor for completing the project
- Total of Interim Certificates: the sum of all the interim payments that the Contractor has already received for completed work

30
Q

Form of Tender

A

the form of tender referred to in the first recital of the Articles as being part of the Tender Documents

31
Q

Hong Kong

A

the Hong Kong Special Administrative Region

32
Q

Interim Certificate

A

a certificate issued by the Architect stating the amount of an interim payment due to the Contractor, as described in clause 32.1.

33
Q

Limit of Retention

A

the amount stated in the Appendix under the reference to clause 32.4 as the limit to the amount of Retention to be held by the Employer on the payment for the Contractor’s work in progress.

34
Q

Nominated Sub-Contract

A

the sub-contract between the Contractor and a Nominated Sub-Contractor.

35
Q

Nominated Sub-Contractor

A

a sub-contractor nominated by the Architect under clause 29 to carry out work forming part of the Works.

36
Q

Nominated Supplier

A

a supplier nominated by the Architect under clause 29 to supply materials or goods for incorporation into the Works

37
Q

Nominated Supply Contract

A

the supply contract between the Contractor and a Nominated Supplier.

38
Q

parties

A

the Employer and the Contractor.

39
Q

Period of Interim Certificates

A

the period stated in the Appendix under the reference to clause 32.1 as the interval between the issuing of Interim Certificates

40
Q

person

A

an individual, firm, partnership, or body corporate.

41
Q

person for whom the Contractor is responsible

A

Persons on the Site:
- Contractor’s servants or agents,
- Sub-contractors
- Suppliers
- Persons Employed or Engaged
- Persons Properly on Site: inspectors, surveyors, or engineers
- Connection with the Works

42
Q

person for whom the Employer is responsible

A

the Employer’s servants or agents and the persons listed in clause 30.1.

43
Q

postpone

A

to defer the commencement of operations on an activity.

44
Q

Prime Cost Sum

A
  • Clause 29.1
  • work or materials that are procured through Nominated Sub-Contractor or Nominated Supplier
45
Q

Provisional Item

A
  • clause 13.2.
  • the Contractor is obligated to carry out only if instructed to do so by the Architect
  • is not made at the time of contract signing but is contingent on future circumstances or decisions

Example: additional landscaping work. Specific details of the landscaping (type of plants, layout, etc.) might not be finalized until later in the project.

46
Q

Provisional Quantities

A
  • work that the Contractor is obligated to carry out only if instructed to do so by the Architect
  • the decision to include these items in the project and the final quantity of work are not determined at the time of contract signing but are contingent on future circumstances or decisions

Example: excavation work. The exact amount of earth to be excavated might not be known until after the site investigation or during the construction process.

47
Q

Provisional Sum

A
  • clause 13.2.
  • a sum provided in the Contract Bills for work or for costs, which could not be entirely foreseen, defined or detailed when the bills of quantities were prepared.
48
Q

Key Differences

A
  • Prime Cost Sum vs. Provisional Sum:
    Both are sums allocated in the contract. The Prime Cost Sum is for specific items procured through nominated subcontractors/suppliers, while the Provisional Sum is for unforeseen work or costs.

-Provisional Item vs. Provisional Quantities:
Both are conditional work items. The Provisional Item refers to the entire work item, while Provisional Quantities refer to the estimated quantity of that work item

49
Q

Quantity Surveyor

A

the person named as the Quantity Surveyor in Article 4, or any successor appointed under Article 5.

50
Q

Relevant Date

A

the date upon which the Employer took possession of a Relevant Part under clause 18.

51
Q

Relevant Part

A

the part of the Works or part of a Section taken possession of by the Employer under clause 18 before Substantial Completion of the Works or that Section.

52
Q

Retention

A

the sum calculated in accordance with clause 32.4 and retained by the Employer from the gross valuation of the Contractor’s work in progress included in an Interim Certificate.