1
Q

4.1 Develop Project Charter

Inputs
Tools & Techniques
Outputs

A

Business Case, Benefits Mgmt Plan, Agreements

Assumption Log, Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

4.2 Develop Project Management Plan

Inputs
Tools & Techniques
Outputs

A

Project Charter

Data Gathering (Brainstorming, Focus Groups, Interviews, Checklists)

Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

4.3 Direct & Manage Work

Inputs
Tools & Techniques
Outputs

A

Approved Change Requests

PMIS

Deliverables, Work Performance Data (Raw Data), Change Requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

4.4 Manage Project Knowledge

Inputs
Tools & Techniques
Outputs

A

Deliverables

Knowledge Mgmt (Sharing Knowledge), Info Mgmt (Connect people to info)

Lessons Learned Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

4.5 Monitor & Control Project Work

Inputs
Tools & Techniques
Outputs

A

Work Performance Information, Agreements

Data Analysis (Alternative, Cost-Benefit, EV, Root Cause, Trend, Variance)

Work Performance Reports, Change Requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

4.6 Perform Integrated Change Control

Inputs
Tools & Techniques
Outputs

A

Work Performance Reports, Change Requests

Change Control Tools, Data Analysis (Alternative, Cost-Benefit), Decision Making (Voting)

Approved Change Requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

4.7 Close Project

Inputs
Tools & Techniques
Outputs

A

Accepted Deliverables, Business Documents (Business Case, Benefits Mgmt Plan), Procurement Documentation

Final Product/Service/Result, Final Report, Updated Lessons Learned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly