Integrated Project Management Flashcards
You are a project manager for your organization. Management has asked you to help determine which projects should be selected for implementation. In a project selection model, which of the following is the most important factor?
a) Business needs b) The type of constraints c) The budget d) The schedule
a) Business Needs
Projects are selected based on business needs first.
Your project is moving ahead of schedule. Management elects to incorporate additional quality testing into the project to improve the quality and acceptability of the project deliverable. This is an example of which one of the following? a) Scope creep b) Change control c) Quality assurance d) Integrated change control
d) Integrated Change Control
Additional quality testing will require additional time and resources for the project. This is an example of integrated change control.
You are the project manager of a new website design project. There are 45 stakeholders with this project and you are anticipating change requests in the project. Which of the following is not true about change requests?
a) They happen while the project work is being done.
b) They always require additional funding.
c) They must be documented
d) They can be requested by a stakeholder.
b) They always require additional funding
Change requests do not always require more money. Approved changes may require more funds, but not always. The change request may be denied, so no additional funds are needed for the project.
You are the project manager for a pharmaceutical company. You are currently working on a project for a new drug your company is creating. A recent change in a law governing drug testing will change your project scope. Since the project must be completed within two years, what’s the first thing you should do as project manager?
a) Create a documented change request.
b) Proceed as planned, since the project will be grandfathered beyond the new change in the law.
c) Consult with the project sponsor and the stakeholders.
d) Stop all project work until the issue is resolved.
a) Create a documented change request
A formal, documented change request is the best course of action for a change request stemming from a law or regulation.
Which one of the following is not beneficial to the project manager during the project plan development process?
a) Gantt charts b) PMIS c) The project management methodology d) Stakeholder knowledge
a) Gantt charts
Gantt charts are excellent tools to measure and predict the project PROGRESS, but they are not needed during the project plan development process.
Yoli is the project manager for her company and she’s reviewing the project budget with management. Management is concerned about the capital expenses in the project and they’d like more information about when Yoli will actually spend the project budget. Which one of the following represents the vast majority of a project’s budget?
a) Project planning b) Project plan execution c) Labor d) Cost of goods and services
b) Project Plan Execution
The project plan execution represents the majority of the project budget.
Natasha is the project manager for her organization. She is meeting with her project stakeholders to review the project plan and the different elements she’ll use as part of project execution. Which of the following can best help Natasha during project execution?
a) Stakeholder analysis b) Change control boards c) PMIS d) Scope verification
c) PMIS
A PMIS can assist the project manager the most during project execution. It does not replace the role of the project manager, however.
You are the project manager for your organization. When it comes to integrated change control, you must ensure that which one of the following is present?
a) Supporting detail for the change exists
b) Approval of the change from the project team
c) Approval of the change from an SME
d) Risk assessment for each proposed change
a) Supporting detail for the change exists
Integrated change control requires detail for implementing the change. Without evidence of the need for the change, there is no reason to implement it.
Jeff is the project manager of the Bridge Construction Project for his company. This project requires strict change control because of government regulations, the cost of the project deliverables, and the approved scope. The project plan provides what with regard to project changes?
a) A methodology to approve or decline CCB changes
b) A guide to all future project decisions
c) A vision of the project deliverables
d) A fluid document that may be updated as needed based on the CCB
b) A guide to all future project decisions
The project plan serves as a guide to all future project decisions.
Baseline variances, a documented plan to management variances, and a proven methodology to offer corrective actions to the project plan are all part of which process?
a) Change management b) The change control system c) The scope change control d) Integrated change control
d) Integrated change control
Integrated change control is a system to document changes, their impact, the response to those changes, and performance deficits.
You are the project manager of the GHQ Project for your company. Management has required that you utilize earned value management as part of your project and their enterprise environmental factors. EVM is used during the _______________.
a) Controlling processes b) Executing processes c) Closing processes d) Entire project
d) Entire project
EVM (earned value management) is used throughout the project processes. It is a planning and control tool used to measure performance.
You are preparing to enter into the project execution with your project team. As part of your preparation, you’ll rely on your project management plan and several tools and techniques. Which of the following contains parts of the project plan execution?
a) PMIS, WBS, and EVM
b) General management skills, status review meetings, and EVM
c) Project management methodology and the PMIS
d) General management skills, EVM, status review meetings, and interpersonal skills
c) Project management methodology and the PMIS
A project management information system is the coherent organization of the information required for an organization to execute projects successfully. A PMIS is typically one or more software applications and a methodical process for collecting and using project information
Which one of the following is a formal document to manage and control project execution? a) WBS b) The project management plan c) The organizational management plan d) The work authorization system
b) The project management plan
One of the requirements of project management in your organization is to describe your project management approach and methodology in the project plan. You can best accomplish this requirement through which one of the following actions?
a) Establishing a project office
b) Establishing a program office
c) Compiling the management plans from each of the knowledge areas
d) Creating a PMIS and documenting its inputs, tools and techniques, and outputs
c) Compiling the management plans from each fo the knowledge areas
The management approach is best described as a compilation of the individual plans in the project plan.
You are the project manager for the DGF Project. This project is to design and implement a new application that will connect to a database server. Management of your company has requested that you create a method to document technical direction on the project and to document any changes or enhancements to the technical attributes of the project deliverable. Which one of the following would satisfy management’s request?
a) Configuration management b) Integrated change control c) Scope control d) The change management plan
a) Configuration management
Configuration management is the documentation of the project product, its attributes, and its changes to the product.
You are examining the project management plan and its components with the project team. The team doesn’t understand why so much information is needed for the project. What is the difference between a project baseline and a project plan?
a) Project plans change as needed, while baselines change only at milestones.
b) Project plans and baselines do not change—they are amended.
c) Project plans change as needed, while baselines are snapshots of the project plan.
d) Baselines are control tools, while project plans are execution tools.
d) Baselines are control tools, while project plans are execution tools.
A project baseline serves as a control tool. Project plan execution and work results are measured against the project baselines.
You are the project manager for the HALO Project. You and your project team are preparing the project plan. Of the following, which one is a project plan development constraint you and your team must consider?
a) The budget as assigned by management
b) Project plans from similar projects
c) Project plans from similar projects that have failed
d) Interviews with subject matter experts (SMEs) who have experience with the project work in your project plan
a) The budget as assigned by management
If management has assigned the project a fixed budget, the project manager and the project team must determine how the project can operate within that constraint.
During project execution activities, a project sponsor’s role in a functional organization can best be described as doing which one of the following?
a) Acting as a sounding board for the project stakeholders
b) Helping the project manager and stakeholders resolve any issues ASAP
c) Deflecting change requests for the project manager
d) Showing management the project progress and status reports
b) Helping the project manager and stakeholders resolve any issues ASAP
The project sponsor can help the project manager and the stakeholders resolve issues during project execution.
Beth is the project manager of a software development project. She and her project team are done with a phase and Beth needs to make certain the lessons-learned register is complete before moving the project onto the next phase. On any project, the lessons-learned document is created by which of the following?
a) The customers b) The project sponsor c) The project team d) The stakeholders
c) The project team
The project team contributes to the lessons-learned document. The project manager also contributes, or leads, the creation, but this is not a choice in the question.
______ is a tool that can be used to enter the coherent organization of the information required for an organization to execute projects successfully. It is typically one or more software applications and a methodical process for collecting and using project information
Project management information system (PMIS)
A project team member has asked you what project scope management is. Which of the following is a characteristic of project scope management?
a) It defines the baseline for project acceptance.
b) It defines the requirements for each project within the organization.
c) It defines the processes to ensure that the project includes all the work required—and only the work required—to complete the project successfully.
d) It defines the functional managers assigned to the project.
c) It defines the processes to ensure that the project includes all the work required—and only the work required—to complete the project successfully.
You are the project manager for a pharmaceutical company. A new government regulation will change your project scope. For the project to move forward and be in accordance with the new regulation, what should be your next action?
a) Prepare a new baseline to reflect the government changes. b) Notify management. c) Present the change to the CCB. d) Create a feasibility study.
c) Present the change to the CCB.
Recommended corrective actions, which are change requests, are outputs of change control. Poor performance leads to corrective actions to bring the project back in alignment with the project plan. Recall that a corrective action is a change request.
Question 16:
Which of the following is an output of scope control?
a) Workarounds b) Recommended corrective action c) Transference d) Risk assessment
b) Recommended corrective action
A project team member has, on his own initiative, added extra vents to an attic to increase air circulation. The project plan did not call for these extra vents, but the team member decided they were needed based on the geographic location of the house. The project team’s experts concur with this decision. This is an example of which of the following?
a) Cost control b) Ineffective change control c) Self-led teams d) Value-added change
b) Ineffective change control
The project team member did not follow the change management plan’s method of incorporating changes into the scope.