Inputs To Risk Management Flashcards
Important inputs to risk management?(8)
Project background information Project charter Stakeholder register Scope statements Constraints Assumptions Work breakdown structure (wbs) Network diagram
Project background information
Risk articles and publications Project management article Copies of contracts/standards and regulations related to the project Technical drawings and spec Project organization charts
What in the project charter?(7) f
Deliverables Estimated cost Estimated duration Project assumptions High level risks Project approach Scope
Who can be in a stakeholder register
Individual, group, or organization who may be affected by the project
What are the 4 part of the stakeholder register
High power /low interest
High power/high interest
Low power/low interest
Low power /high interest
What are 4 constraints for a project?
Time
Cost
Scope
Quality
What a critical path?
A critical path is the longest duration path in a network diagram and determines the shortest time it could take to complete the project
What at two schedule compression
Fast tracking
Crashing
What fast tracking
Taking the critical path activities that were originally planned in a series and doing them instead in parallel
What is crashing schedule?
Crashing -adding or adjusting resources in order to compress the schedule while maintaining the project scope
What should the project team do at the beginning of the project
Lesson learned. Look at Similar projects and find out what went wrong during those projects. finding the risk of the old project so you can help the new project