Inputs and Outputs Flashcards
What is the cost baseline?
An approved version of the project budget, which is the cost estimate + contingency reserves and excluding management reserves
What is the statement of work?
SOW is developed from the scope baseline and defines the scope that is to be included within a related procurement contract.
What does the scope statement include?
- The scope description
- Deliverables
- Acceptance criteria
- Project exclusions (out-of-scope stuff)
What is the schedule baseline?
An approved version of the schedule model.
What does the scope baseline include?
An approved version of the scope statement, WBS, WBS disctionary.
What is a WBS dictionary?
A document that provides detailed information about each component in the WBS.
What is a resource breakdown structure?
A resource breakdown structure how you categorize resources (e.g., personel vs material vs equipment)
Differentiate between cost baseline and project budget.
- Cost baseline is the aggregate of cost estimate and contingency reserve.
- The project budget includes the cost baseline and the management reserve.