Inputs and Outputs Flashcards

1
Q

What is the cost baseline?

A

An approved version of the project budget, which is the cost estimate + contingency reserves and excluding management reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the statement of work?

A

SOW is developed from the scope baseline and defines the scope that is to be included within a related procurement contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does the scope statement include?

A
  1. The scope description
  2. Deliverables
  3. Acceptance criteria
  4. Project exclusions (out-of-scope stuff)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the schedule baseline?

A

An approved version of the schedule model.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does the scope baseline include?

A

An approved version of the scope statement, WBS, WBS disctionary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a WBS dictionary?

A

A document that provides detailed information about each component in the WBS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a resource breakdown structure?

A

A resource breakdown structure how you categorize resources (e.g., personel vs material vs equipment)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Differentiate between cost baseline and project budget.

A
  • Cost baseline is the aggregate of cost estimate and contingency reserve.
  • The project budget includes the cost baseline and the management reserve.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly