ICC/UST Flashcards

1
Q

Corrosion Specialist

A

Designs and certifies Cathodic Protection System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Secondary Containment shall be constructed to contain at least the following volumes:

A

A. 100% of usable capacity of primary where there is only one primary is within the secondary

B. 150% of the largest container if there are multiple primary containers in a single secondary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cathodic Protection tester will test cathodic protection system within ___ months of installation and every ___ years thereafter

A

6 months

3 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Spill container shall meet the following requirements:

A

A. If made of metal, exterior shall be protected from galvanic corrosion

B. Shall have minimum capacity of 5 gallons (19L)

C. Shall have been drain valve which allows drainage of the collected spill into the primary container or provide means to keep spill container empty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

OVerfill prevention shall alert transfer operator when tank is __% full

A

90%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Flapper Valves shall provide positive shut off when tank is filled to no more than __% capacity

A

95%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Primary pressurized piping shall be tested for tightness hydrostatically at __% of design operating pressure

A

150%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Date that all UST systems must have Line Leak Detector (LLD) installed

A

November 9, 2004

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Secondary containment testing shall be done upon __, __ months, and every __ months or __ years thereafter

A

Installation

6 months

36 months or 3 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Owner/Ops shall submit SCT results to local agency within __ days of completion

A

30 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

All monitoring equipment shall be tested, calibrated, operated, maintained, and certified every __ months

A

12 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A person conducting UST monitoring equipment certification shall affix tag/sticker on each component and shall include __ and __.

A

Date certified, replaced or repaired

Contractor/Tank Tester’s License Number

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

LLD shall direct Release of __ GPH and __ PSI within __ hour(s)

A

3 GPH

10 PSI

1 Hour

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Suction piping shall be tested every __ years

A

3 years (36 months)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Owners/Operators of UST shall submit copy of Enhanced Leak Detection (ELD) results to Local Agency within __ days of completion of test

A

60 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Within __ hours of unauthorized release, owner/operator should notify __.

A

24 hours

Local agency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Date that all UDC upgrades shall be completed

A

December 31, 2003

18
Q

Tanks and piping which have been repaired shall be tested for tightness within __ days of completion of repair

A

30 days

19
Q

UST shall be inspected every __ months to verify that temporary closure measures are still in place

A

3 months

20
Q

If UST is removed, soil samples shall be taken

A

beneath removed portions at a minimum of 2 feet at each end of the tank

21
Q

Within ___ of affixing red tag, local agency shall notify owner of significant violation

A

24 hours

22
Q

Location of the Red Tag

A

Fill Pipe

23
Q

Any person who intentionally tampers with LLD shall be punished with fines no less than $___.

A

$5000

24
Q

CA law requires USTs be inspected every ____

A

1 year

25
Q

Monitoring records must be kept on file for ___

A

3 years

26
Q

Cathodic protection maintenance records must be kept on file for ___

A

6.5 years

27
Q

Written performance claims on release detection systems must be kept on file for ___

A

5 years

28
Q

Underground storage tank system includes:

A

UST, piping, storage of hazardous substance

29
Q

For existing UST with ATG as sole means of quantitative release detection, the ATG must be capable of ___ gallons per hour

A

0.2 GPH

30
Q

Designated operator must provide training to employees ___ how often?

A

Annually

31
Q

Interior lining must be inspected by a coating expert within __ years of installation

A

10 years

32
Q

Designated operator must conduct inspections of UST every ___

A

month

33
Q

Enhanced leak detection must be capable of detecting leak at least __ GPH

A

0.005 GPH

34
Q

When ATG is utilized for SW detection, it shall test tank monthly after product delivery or when tank is filled to within ___% of highest operating level during the previous month

A

10%

35
Q

Date that overfill alarms were required on all UST systems

A

December 22, 1998

36
Q

Spill buckets shall be tested…

A

Annually

37
Q

Unauthorized release must be notified to local agency within ___ followed by written notification within ___.

A

24 hours

5 days

38
Q

By December 22, 1998, all automatic line leak detectors installed on SW pressurized piping must be capable of:

A

Shutting down the piping system

39
Q

During the temporary closure, the following openings must be sealed:

A

Fill and access

40
Q

Pressurized product piping with secondary containment subject to annual pressure test must be tested with method capable of detecting:

A

0.1 GPH