Case - restructuring plan that has been announced but does not commence until 2 years.

A

Should not recognize a provision as external parties are unlikely to have a valid expectation that management is committed to the reorganization as the time frame allows significant opportunity for management to change the details of the plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Provision for warranty

A

Should be recognised because past event has created legal obligation to spend money on repair.
Company cannot avoid the cost of repair or replacement of goods for which warranty was given before year end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Do we need a provision

A

1, is there a present obligation as a result of a past event ?
2, is an outflow of economic benefits probable as a result?
3. Is it reliably measurable? Assumed yes in case of no info to the contrary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Law is virtually certain with retrospective effect

A

Recognize

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Provision for environmental damage

A

Asset dr

Provision cr

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

27 a iii Kaplan

Date of provision

A

Provision should be made on the date of the obligating event ie date on which the event takes place that results in an entity having no realistic alternative to settling the legal or constructive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Entry for provision for damage in court case

A

P/l dr

Provision cr

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Reimbursement from insurance to cover some expenditure required to settle the obligation

A

Recognized only if receipt is virtually certain

Reimbursement should be treated as a separate asset

Receivables dr
P/l cr