Q

Which of the below purposes of electric heat tracing “do not” apply?

A

a. provide freeze protection
b. eliminate the use of thermal insulation✅
c. maintain the temperature of process fluids
d. Prevent condensation in piping systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which type of temperature control that would most likely be used for process lines that carry syrup is?

A

Narrow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In a typical power distribution scheme Branch circuit, _______
breakers are used to apply
operating voltages to the power connection boxes of heat tracing circuits.

A

Ground Fault Interrupting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which cable Is used for applications that require a heat output that varie With changes in the temperature of the air or other medium surrounding the cable?

A

Self-regulating heat tracing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which control method is used for heat tracing systems uses a programmable controller connected to remote temperature input modules and contactor control modules to regulate one or more heat tracing cables?

A

Proportional ambient-sensing control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

In dead-leg control, what type of flow condition exists in the dead leg?

A

No flow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The main function of special ground-fault circuit breakers in a heat tracing system is to protect the____

A

Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What type of temperature-sensing device is generally used to monitor the temperature of the pipe for heat-tracing control purposes?

A

RTD

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Powerline carrier technology?

A

uses frequency-Shift keying to decode digital data on the Powerline network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When installing heat-tracing cables, their cold leads must be positioned so that they penetrate the piping thermal insulation in?

A

the lower 180-degree segment of the pipe

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The most cost-efficient type of steam heat-tracing system likely to be installed in a new facility is a channel/tube______
system

A

Channel/tube Conduction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Does propylene glyco have
better heat transfer efficiency than ethylene glycol?

A

No- Ethylene glycol does

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The concentration of chemical additives added to a system to provide for burst protection is

A

less than is needed to provide for freeze protection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The general term used to describe the covering placed directly over the insulation materials Is?

A

Lagging

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

In some heat tracing installations covered with insulation, aluminum foil is wrapped over the heat tracing line before insulating the piping to _______

A

Increase the radiation heat transfer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A protective device that can be installed at the inlet of a pressure element to prevent rapid pressure changes in the input to the instrument is called a

A

Snubber

17
Q

The main reason to blow down instrument air lines is to remove_______from the lines

A

Moisture/Debris

18
Q

Why does water vapor begin to condense inside the receiver of a compressed air system?

A

Because the air in the receiver may cool down to the dew point

19
Q

Blowdown valves should never be opened too wide because______

A

the extreme pressure drop could cause water to freeze in the line

20
Q

The first consideration in preparing to blow-down signal lines is to consider the?

A

purpose of the instrument in the process