Hinze Flashcards
Notice to Bidders
Includes …
- nature or type of project
- location of project
- type of contract for construction
- bonding requirements
- dates in which to perform work
- terms of payment
- estimated construction cost (some specially exclude this)
- time, manner, and place to submit bids
- location to obtain bid documents
- deposit required on bid documents
- owners right to reject any and all bids
- requirements regarding wage rates
Advertisements for Bids - Public Sector
- Notice given
- Invitation for bids posted
- All bidders must be treated alike and be afforded an opportunity to bid under the same terms and conditions
- Prequalification may be required
Advertisements for Bids - Private Sector
- The owner may select a contractor by any means.
- Public advertising is frequently used to obtain the advantages of open and free competition.
- The owner may elect to negotiate a contract with a particular contractor. This is most common in residential construction and in industrial construction involving highly technical work. The contractor would be selected early in the life of the project and then work constructively with the owner, architect, and other design professionals throughout the design phase of the project.
- The most common approach is for the owner to select a few prime contractors who are reputable and capable of doing a good job. This list of contractors is called a select bidders list. These contractors are asked to bid in a process called invitational bidding. This process has the advantage of the competitive market while restricting bids to a select group of contractors.
Advantages of design-bid-build process
- Owner benefits from competitive marketplace
- Owner has appearance of being impartial
- Process fully embraces the fundamentals of the free market system
- May be only viable method available for some governmental agencies
Disadvantages of design-bid-build process
- Accurate costs cannot be known until the design is completed
- Bids that exceed the owner’s budget cannot be readily accommodated without jeopardizing the project
- The various parties tend to be adversarial under this process
- Errors or omissions in the design may lead to costly change orders and the opportunity for the contractor to bolster profits after contract award
Prequalification
- not a common practice
- employed public and private
results in a select bidders list, or short list, which identifies firms that have demonstrated to the owner that they have the necessary abilities to perform the required work
Prequalification submittals include:
- types of projects successfully completed by the firm
- current work load
- personnel employed by the firm
- experience of the personnel to be assigned to the proposed project
- financial stability of the firm
- other information that the owner may deem germane to the successful completion of the project
Plan service centers
Source of bidding information that publishes and distributes bulletins on regular basis that describe all projects to be bid on in near future in locality
Provides services during bidding stage - keep copies of bidding documents on file
Can answer: should general contractor bid on project? Which subcontractors and suppliers are bidding?
Value Engineering
Specific procedure carried out to critically analyze the various aspects of contract documents in relation to the owner’s objectives, to determine if alternative methods or materials might be more appropriate
reviewing the contract documents with the owner’s best interest in mind
A value engineering review on a project may result in a variety of changes in the contract documents that may:
- reduce costs
- improve or maintain project quality
- decrease duration of construction
Value includes elements of
- delivered cost of project
- costs of maintaining a completed project
- ease and duration of construction
- probability of disputes or litigation
- various other factors of interest to the owner
Value engineering review can be conducted at two phases
Design Phase - designer or third party review
Construction Phase - contractor
Constructability Review
An assessment of the contract documents, prior to the bidding phase, to identify problem areas and suggest improvements
Addenda
Formal changes or clarifications issued by the owner or owner’s representative to all identified bidders during the bidding period
Issued during the bidding or estimating period
Exculpatory provision
One party, typically the contractor, is asked to assume liability that would not otherwise be assumed
Typically provisions in which the owner contractually shifts liability or responsibility to the contractor
Valid but often under scrutiny
Courts interpret very narrowly or literally
Strict interpretation can render them ineffective
Strict interpretation
The court tries to interpret the provision, as much as it can within reason, against the party that seeks protection under the provision or against the party which drafted the provision
Torts
Disputes that relate to matters not addressed by statutory law or contract obligations
Wrongs committed against others that do not involve contracts
Common-law interpretation is often required
Wrongs of breaches of duty may stem from injuries or damages incurred by one party as a result of the action or inaction of another party who had a duty to prevent the injury or damage
A tortuous act is often one that violates the social norm
Can result from a specific action or can be caused by failure to act
For a tort to occur, the following conditions must be met:
- One party owes a duty to another party
- That party does not conform (breach in the performance of that party) to the standard.
- The second party is harmed by the act or failure to act.
- There is a clear casual relationship between the act and the harm that results.
Breach of duty. result from failure to act properly in the performance of a specific duty, or failure to act when there is a duty to act. The party to whom a duty is owed must be damaged. Damages may include physical injury, destruction of property, and defamation of character. It just be shown that the damage is a direct consequence of the breach of duty
Examples of torts
- defamation of character through libel or slander
- unlawful entry onto another’s premises
- unwarranted seizure, alteration, or destruction of another’s property
- unauthorized use of another’s patents, trademarks, or copyrights
- violation of another’s freedoms through nuisance and negligence
- failure to exercise care in the exercise of one’s duty to another
Torts can arise from damage or injury caused by failure to act with the proper standard of care
Standard of care
Broadly interpreted as conduct that is expected of someone acting in a given capacity
Negligence
Arises when a legally protected interest is overtly invaded or violated in some way.
The definition of tort is often applied to negligence suits.
Attractive nuisance
Generally defined as applying when
1. The party controlling a piece of property should know that children are likely to trespass
2. The party should realize that there is an unreasonable risk of death or serious injury on the site
3. The children, because of their age, will probably not recognize the risk involved
4. The party could reduce the risk with a small effort by keeping the children out or by reducing the dangerous condition
General Contract Method
Design-Bid-Build
Contract drawn up between the owner and a general contractor.
- Owner represented by firm that was responsible for drawing up the contract documents.
- Architectural design firm/engineering firm
- Owner will enter into two separate contracts, one with designer and one with constructor
- Only method that gives the owner a firm idea of the final cost of the total project prior to the construction phase
- Clearly defined roles for each of the contracting parties.
- Owner minimizes the contractual liability for cost overruns and late project delivery.
Brokerage
When general contractor subcontracts all the work on a project.
Generally not regarded as being beneficial to the owner.
- Many owners place contractual limits on amount of work that can be subcontracted (ex.15-20% must be performed by general contractor’s own workers)