High Rise Water Systems Flashcards

1
Q

Pre-60 inlets

A

(2) 2 1/2 inlets if 4-5 stories. (4) 2 1/2 inlets if 6 stories or more

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Pre-60 riser

A

4-6 inch riser rated at 500 GPM per riser

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Pre-60 Classes

A

Class 1 Dry, Class 2 Wet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

60-74 less than 150 feet?

A

Same as Pre-60

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

60-74 above 150 feet?

A

Class III Combination Standpipe

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

60-74 inlets

A

(4) 2 1/2 inlets. (6) 2 1/2 inlets if 3 or more risers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

60-74 risers

A

6 inch riser rated at 1000 GPM per riser

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

orifice plates

A

metal like washer device designed to lower pressure rated at 200 gpm at 45 psi.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

orifice plates found at pressures above ___

A

135 psi

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

60-74 water supply

A

primary - domestic / secondary - LAFD

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

74 to Present 75-150’

A

Damp system, On site water calculated sprinkler flow of most demanding area for 30 minutes + 100 GPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

74 to Present 75-150’ (Pressure Restricting Valve)

A

found when pressure is between 135 to 150 PSI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

74 to Present 150-275’ onsite water

A

Calculated for standpipe demand + 500 GPM for 1st riser and 250 GPM for each additional riser.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

74 to Present over 275’ onsite water

A

45K - 105K gallon water tank

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

74 to Present over 150 (Pressure Regulating Device)

A

Found when pressure exceeds 150 psi, provides 80-125 psi at 300 GPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Mercoid pressure switch

A

the policy in LA for the Stop pressure is set 10 psi below system pressure and START pressure is set 50 psi below the system pressure

17
Q

Dry standpipe outlets are located based on requirement

A

That every point within the structure must be reachable by a 30’ stream of water from a nozzle attached to 100’ of hose

18
Q

Jockey pumps

A

installed to make up minor leakages rates in system pressure.

19
Q

Jockey pumps prevent

A

the fire pump from continually starting and stopping due to the minor fluctuation in the system pressure

20
Q

Looped system (except 1983 - 1988 )

A

water for a given sprinkle head is delivered from two or more risers

21
Q

Exception to the looping between 1938-1988 was due to the

A

Uniform building code in 1983

22
Q

Uniform building code in 1983

A

did not require two separate points of connections for sprinklers

23
Q

Buildings under construction…. every building ____ stories or more shall be provided with not less than ___ standpipe for use during construction

A

6 stories or more, Not less than 1 standpipe

24
Q

The standpipe shall be installed when the progress of construction is not more than ____ in height

A

50’

25
Q

Such standpipe shall be provided with a ____ on each floor adjacent to useable stairs

A

2 1/2” outlet

26
Q

Such standpipe shall be extended as construction progresses to within ___ floor of the highest point of construction having _____

A

One / having secure decking or flooring

27
Q

Where construction heights requires installation of combination standpipe…

A

fire pumps and water main connections shall be provided to serve standpipe

28
Q

Once the standpipe exceeds ____

A

150’ a temporary manually started fire pump shall be installed.

29
Q

Jockey pumps should be set to operate

A

at a pressure of 5 to 10 psi higher than the main pumps starting pressure

30
Q

Fuel supply: there must be a separate ____ for each engine

A

fuel line and fuel supply tank

31
Q

On new high rise post 74 : minimum fuel supply

A

8 hours

32
Q

On existing high rise 60-74: minimum fuel supply

A

4 hours