High - Low methods is used to

A

estimate Fixed and Variable costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Computation of Variable Costs Per Unit

A

(Highest costs - lowest costs)/(highest activities - lowest activities)

Changes in costs/changes in activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Computation of total fixed costs

A

Total Costs - (Variable cost per unit x activity)