GPDS Flashcards

1
Q

GPDS

A

Global Product Development System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Key Ford Process

A

Failure Mode Avoidance
Prototype Builds
P- Authority

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

3 Core Corporate Process

A

GPDS
FPS
OTD

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

GPDS 3 Distinct phases

A

phase 1: Powertrain units
Phase 2: Platform systems
Phase 3 : Tophat systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

GPDS 3 sets of Milestone within each developmental phase

A
  1. Powertrain unit milestones.
  2. Platform development milestones
  3. Tophat development milestones
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Engineering Gateways -definition

A

Engineering Gateways are Technical Maturity events guiding

the major development phases in support of the Milestones

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Engineering Gateway - Platform

A

Underbody development gateways - Platform compatibility process for
Underbody (UN) and Powertrain systems during Platform
development.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Engineering Gateway - Tophat (no of gateways)

A
  1. Design Feasibility checkpoint

2. Upperbody virtual development Gateways

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Each

Milestone and Gateway has a defined set of ______________

A

deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

deliverables are tracked and managed in

our GPDS management tool called

A

Global Integrator ( GI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

______contain the definition of the deliverables as well as the logical
connections (i.e. dependencies).

A

Process sheet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Deliverables are

captured in ———————–

A

Process Sheet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Each

process sheet includes:

A
• Deliverables to judge the Quality of
Event
• Steps required to execute the process
•
Inputs (Predecessors) and Outputs (
• Reference
Information
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Each

deliverable in the process sheet includes

A
  • Executor
  • Start and Finish Timing
  • Description
  • Quality of Event Criteria
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

_________ affects the time between Milestone and Gateway events, so vehicle programs won’t

A

scaling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Bundled Platform Plan (or BPP) covers—

A
covers the timing of 
conceptualization, 
design, 
sourcing,
engineering, 
tooling, 
testing 
of underbodies with a common Platform architecture and shared technologies.
17
Q

Vehicle Program Plan (or VPP)

A
covers the timing of 
conceptualization, 
design, 
sourcing,
engineering, 
tooling, 
testing 
pre production builds of the vehicle programs’ saleable products.
18
Q

Key Dates List

A

a table derived from the Vehicle Program Plan with timing of all
Milestones,
Gateways,
prototype and production build material required dates,
and other Key Events of the
program.