Government Procurement Flashcards
The following is not a scope and application of RA No. 9184 (Government Procurement Reform Act)
a. Procurement of Infrastructure Projects
b. Goods
c. Consulting Services
d. All of the choices are scopes and applications
d
Which of the following statement/s are incorrect?
a. Specifications for procurement of goods shall be based on brand names
b. The procuring entity shall ensure equal access to information in all stages of preparation of bidding documents
c. Prior to official release, no aspect of Bidding Documents shall be released to any prospective bidder
d. Reference to brand names shall not be allowed
a.
When shall the Bids and Awards Committee be mandated to hold a pre-procurement conference (prior to issuance of invitation to bid)?
a. 3 months prior to issuance of invitation to bid
b. 3 months after the issuance of invitation to bid
c. On each and every procurement
d. None, this is only optional.
c
If, however, the contracts have below a certain level or amount specified in the IRR, the pre-procurement conference will just be optional.
This assesses the readiness of the procurement in terms of confirming the certification and availability of funds, as well as reviewing all relevant documents and the draft invitation to Bid, as well as consultants hired by the agency.
a. Invitation to bid
b. Pre-procurement conference
c. Bid evaluation
d. Pre-bid conference
b.
All invitations to bid contracts under competitive bidding shall be advertised by the Procuring Entity for how long?
a. As may be necessary under the circumstances
b. 30 working days
c. 3 months
d. 60 working days
a
How many pre-procurement conferences shall be conducted for each procurement?
a. At least twice
b. At least thrice
c. At least one, unless provided by the IRR
d. None of the choices
d
Pre-bid conference, not PRE-PROCUREMENT CONFERENCE
After invitation to bid, what is the next step?
a. Preparation of bidding documents
b. Submission & Receipt of Bids
c. Receipt & Opening of Bids
d. None of the choices
c
What eligibility requirement for consulting services is not present in eligibility requirement for infrastructure projects and procurement of goods?
a. Submission of documents in satisfaction of requirements shall be made under oath
b. Submission of bids may be done electronically
c. Presence of evaluation using numerical ratings
d. There is no difference between the two.
c
Which of the following is a component of a bid?
a. Technical component
b. Technological component
c. Written component
d. Documented component
a
Which of the following rule/s does not pertain to the components of a bid?
a. The bids’ components should be in a separate sealed envelope, which shall be submitted separately
b.The bids shall be received by the BAC on such date, time and place specified in the invitation to bid
c. Deadline for the receipt of bids shall be fixed by the bidders
d. Options a and c
d
Option a - “… which shall be submitted SIMULTANEOUSLY”
Option d - “… shall be fixed by the BAC”
Identify the true statements.
Statement I - A bidder may modify his bid, provided it is done before the deadline for the receipt of bids
Statement II - A bidder may, through oral communication, withdraw his bid or express his intention not to participate in the bidding before the deadline for the receipt of bids.
a. Statement II
b. Statement I
c. Both I and II
d. Neither I nor II
b
Statement II - “… through a LETTER, withdraw his bid or express…”
Which of the following statements is false?
a. When a bidder intends to modify his bid after the deadline, he shall submit the same in a sealed envelope duly identified as a modification of the original bid and stamped received by the BAC
b. When a bidder intends to modify his bid before the deadline, he shall submit the same in a sealed envelope duly identified as a modification of the original bid and stamped received by the BAC
c. When a bidder withdraws his bid, he shall no longer be allowed to submit another Bid for the same contract
d. Bids and bid securities shall be valid for such reasonable period of time indicated in the Bidding Documents
a
How is the technical component of a bid examined?
a. Numerical rating
b. Pass/fail criteria
c. Checking the financial component of the bids
d. Any combination of the 3 options
b
How is the financial component of a bid for procurement of goods and infrastructure examined?
a. Numerical rating
b. Pass/fail criteria
c. Evaluating the financial component of the bids
d. Any combination of the 3 options
c
How is the ranking for bids to procure goods be evaluated after they have passed the preliminary examinations?
a. Highest to lowest
b. Lowest to highest
c. Either option a or b
d. Whichever the BAC feels they want
b