Glossary terms Flashcards
Accept
A response to a threat where no course of action is taken
Acceptance
The formal process of accepting delivery of a deliverable or a product
Acceptance criteria
The requirements and essential conditions that have to be achieved before a deliverable is accepted
Accrual Work done
For which payment is due but has not been made
Acquisitional strategy
The establishment of the most appropriate means of procuring the component parts or services of a project
Activity
1 - A task, job, operation or process consuming time and possibly other resources.
2 - The smallest self-contained unit of work in a project
Activity duration
The length of time that it takes to complete an activity
Activity ID
A unique code identifying each activity in a project
Activity network
Similar to network diagram - a model of activities and their dependencies used in scheduling. Also known as a Precedence network
Activity status
The state of completion of an activity
Actual cost
The incurred costs that are charged to the project budget and for which payment has been made, or accrued
Actual cost of work performed (ACWP)
The total costs actually incurred (paid or accrued) and recorded in accomplishing work performed during a given time period
Actual dates
The dates on which activities started and finished as opposed to planned or forecast dates
Actual expenditure
The costs that have been charged to the budget and for which payment has been made or accrued
Actual finish
The date on which an activity was compeleted
Actual progress
A measure of the work that has been completed in comparison with the baseline
Actual start
The date on which an activity was started
Actual time expected
The elapsed time from the beginning of an activity to date
Adoption
The optional additional phase in a linear life cycle that facilitates the use of project outputs to enable the acceptance and use of benefits
Agile
A family of development methodologies where requirements and solutions are developed iteratively and incrementally throughout the life cycle
Alliancing
An arrangement whereby two or more organisations agree to manage a contract or range of contracts between them jointly.
Similar to partnering - An arrangement between two or more organisations to manage a contract between them cooperatively, as distinct from a legally established partnership
Alternative dispute resolution (ADR)
The collective term for settling disputes with the help of an independent third party without a court hearing, for example, arbitration, adjudication and mediation
Analogous estimating
An estimating technique based on the comparison with, and factoring from, the cost of similar, previous work. Also known as comparative estimating
Analytical estimating
An estimating technique that uses detailed specifications to estimate time and cost for each product or activity. Also known as bottom-up estimating
As late as possible (ALAP)
An activity for which the early start date is set as late as possible without delaying the early dates of any successor
As soon as possible (ASAP)
An activity for which the early start date is set to be as soon as possible. This is the default activity type in most project scheduling systems