Glossary Flashcards

1
Q

A set of conditions that is required to be met before deliverables are accepted.

A

Acceptance Criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Product, results, or capabilities produced by a project and validated by the project or customer or sponsor as meeting their specified acceptance criteria.

A

Accepted Deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Within the quality management system, this is an assessment of correctness.

A

Accuracy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The process of confirming human resources availability and obtaining the team necessary to complete project activities.

A

Acquire Project Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Obtaining human an material resources necessary to perform project activities. Acquisition implies a cost of resources, and is not necessarily financial.

A

Acquisition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A distinct, scheduled portion of work performed during the course of a project.

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Multiple attributes associated with each schedule activity that can be included within the activity list. Include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.

A

Activity Attributes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

One or more numerical or text values that identify characteristics of the work or in some way categorize the schedule activity that allows filtering and ordering of activities within reports.

A

Activity Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The projected cost of the schedule activity that includes the cost for all resources required to perform and complete the activity, including all cost types and cost components.

A

Activity Cost Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The time in calendar units between the start and finish of a schedule activity. Also known as duration.

A

Activity Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A quantitative assessment of the likely amount or outcome for the duration of an activity.

A

Activity Duration Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A short, unique numeric or text identification assigned to each schedule activity to differentiate that project activity from other activities. Typically unique within any one project schedule network diagram.

A

Activity Identifier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed.

A

Activity List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

See project schedule network diagram.

A

Activity Network Diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

See precedence diagramming method (PDM)

A

Activity-on-Node (AON)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The types and quantities of resources required for each activity in a work package.

A

Activity Resource Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The realized cost incurred for the work performed on an activity during a specific time period.

A

Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is completed.

A

Actual Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A project life cycle, also known as change-driveen or agile method, that is intended to facilitate change and require a high degrees of ongoing stakeholder involvement. Adaptive life cycles are also iterative and incremental, but differ in that iterations are very rapid (usually 2-4 weeks in length) and are fixed in time and resources.

A

Adaptive Life Cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A set of tools used to define the quality requirements and to plan effective quality management activities. They include, but are not limited to: brainstorming, force field analysis, nominal group techniques and quality management and control tools.

A

Additional Quality Planning Tools

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A technique used to find ways to bring project activities that are behind into alignment with plan during project execution.

A

Adjusting Leads and Lags

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The process of calling public attention to a project or effort.

A

Advertising

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

A group creativity technique that allows large number of ideas to be classified into groups for review and analysis.

A

Affinity Diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Any document or communication that defines the initial intentions of the project. This can take the form of a contract, memorandum of understanding (MOM), letters of agreement, verbal agreements, email, etc.

A

Agreements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

A technique use to evaluate identified options in order to select which options or approaches to use to execute and perform the work of the project.

A

Alternative Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

A technique used to develop as many potential options as possible in order to identify different approaches to execute and perform the work of the project.

A

Alternatives Generation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

A technique for estimating the duration of cost of an activity or a project using historical data from a similar activity or project.

A

Analogous Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Various techniques used to evaluate, analyze, or forecast potential outcomes based on possible variations of project or environmental variables and their relationships with other variables

A

Analytical Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

A category of projects that have common components significant in such projects, but are not needed or present in all projects. Are usually defined in terms of either the product (i.e., by similar technologies or production methods) or the type of customer (i.e., interval vs. external, government vs. commercial) or industry sector (i.e., utilities, automotive, aerospace, information technologies, etc.) Area can overlap.

A

Application Area

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

A technique that is used to adjust the amount of time between predecessor and successor activities.

A

Applying Leads and Lags

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts [Note: Apportioned effort is one of three earned value management (EVM) types of activities used to measure work performance]

A

Apportioned Effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

A change request that has been processed through the integrated change control process and approved.

A

Approved Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

A review of the change request to verify that these are implemented as approved.

A

Approved Change Request Review

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration.

A

Assumption

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

A technique that explores the accuracy of assumptions and identifies risks to the project from inaccuracy, inconsistency, or incompleteness of assumptions.

A

Assumption Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Method of measuring quality that consists of noting the presence (or absence) of some characteristic (attribute) in each of the units under consideration. After each unit is inspected, the decision is made to accept a lot, reject it or inspect another unit.

A

Attribute Sampling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

The right to apply project resources, expend funds, make decisions, or give approvals.

A

Authority

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

A listing of product requirements and deliverables to be completed, written as stories, and prioritized by the business to manage and organize the project’s work.

A

Backlog

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date

A

Backward Pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

A graphic display of schedule-related information. In the typical bar chart, schedule activities or work breakdown structure components are listed down the left side of the chart, dates are show across the top, and activity durations are show as date-placed horizontal bars. See also Gantt Chart.

A

Bar Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison

A

Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Supporting documentation outlining the details used in establishing project estimates such as assumptions, constraints, level of detail, ranges, and confidence levels.

A

Basis of Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

The comparison of actual or planned practices, such as processes and operations, to those of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.

A

Benchmarking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

The meeting with prospective sellers prior to the preparation of a bid or proposal to ensure all prospective vendors have a clear and common understanding of the procurement. Also known as contractor conferences, vendor conferences, or pre-bid conferences.

A

Bidder Conference

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

A method of estimating project duration or cost by aggregating the estimates of the lower level components of the work breakdown structure (WBS)

A

Bottom-Up Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

A general data gathering and creativity technique that can be used to identify risks, ideas, or solutions to issues by using a group of team members or subject matter experts.

A

Brainstorming

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

The approved estimate for the project or any work breakdown structure component or any schedule activity.

A

Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

The sum of all budgets established for the work to be performed

A

Budget at Completion (BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

See Reserve

A

Buffer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

A documented economic feasibility study used to establish validity of the benefits of a elected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities

A

Business Case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

A concept that is unique to each organization and includes tangible and intangible elements. Through the effective use of project, program and portfolio management disciplines, organizations will possess the ability to employ reliable, established processes to meet enterprise objectives and obtain greater business value from their investments.

A

Business Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

The acquirer of products, services, or results for an organization.

A

Buyer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

A decomposition technique that helps trace an undesirable effect back to its root cause. Also known as a FishBone Diagram.

A

Cause and Effect Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

A property whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected.

A

Central Tendency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

A process whereby modifications to documents, deliverables, or baselines associated with the projects are identified, documented, approved or rejected.

A

Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

A formally charted group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.

A

Change Control Board (CCB)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

A set of procedures that describe how modifications to the project deliverables and documentation are managed and controlled. Under Configuration Management System

A

Change Control System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Manual or automated tools to assist with change and/or configuration management. At a minimum, the tools should support the activities of the CCB.

A

Change Control Tools

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

A comprehensive list of changes made during the project. This typically includes dates of the change and impacts in terms of time, cost and risk.

A

Change Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

A formal proposal to modify any document, deliverable, or baseline.

A

Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

See Project Charter

A

Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

A technique for systematically reviewing materials using a list for accuracy and completeness.

A

Checklist Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

A tally sheet that can be used as a checklist when gathering data.

A

Checksheets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

A request, demand, or assertion of rights by a seller against a buyer, or vice vera, for consideration, compensation, or payment under the terms of a legally biding contract, such as for a disputed change.

A

Claim

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

The process of processing, adjudicating, and communicating contract claims

A

Claims Administration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

The process of completing each project procurement

A

Close Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

The process of finalizing the all activities across all of the Project Management Process Groups to formally complete a project or phase.

A

Close Project or Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Project contracts or other procurement agreements that have been formally acknowledged by the proper authorizing agent as being finalized and signed off.

A

Closing Process Group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

A numbering system used to uniquely identify each component of the WBS

A

Code of Accounts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.

A

Collect Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

An organizational placement strategy where the project team members are physically located close to one another in order to improve communication, working relationships, and productivity.

A

Colocation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

Restrictions on the content, timing, audience, or individual who will deliver a communication usually stemming from specific legislation or regulation, technology, or organizational policies.

A

Communication Constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

A systematic procedure, technique, or process used to transfer information amount project stakeholders.

A

Communication Methods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

A description, analogy or schematic used to represent how the communication process will be performed for the project.

A

Communication Models

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

An analytical technique to determine the information needs of the project stakeholders through interviews, workshops, study of lessons learned from previous projects, etc.

A

Communication Requirements Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

Specific tools, systems, computer programs, etc., used to transfer information among project stakeholders.

A

Communication Technology

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

A component of the project, program or portfolio management plan that describes how, when and by who information about the project will be administered and disseminated.

A

Communication Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

A general concept of conforming to a rule, standard, law or requirement such that the assessment of compliance results in a binomial result stated as “complaint” or “noncompliant”

A

Compliance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

The process of obtaining seller responses, selecting a seller, and awarding a contract.

A

Conduct Procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

A subsystem of the overall project management system. It is a collection of formal documented procedures used to apply technical and administrative direction and surveillance to: identify and document the functional and physical characteristics of a product, result, services, or component; control any changes to such characteristics; record and report each change and its implementation status; and support the audit of the products, results, or components to verify conformance to requirements. It includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes. An umbrella - all changes are captured, analyzed and reported.

A

Configuration Management System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

Handling, controlling, and guiding a conflictual situation to achieve a resolution.

A

Conflict Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

Within the quality management system, conformance is a general concept of delivering results that fall within the limits that define acceptable variations for a quality requirement.

A

Conformance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

In the cost of quality framework, conformance work is done to compensate for imperfections that prevent organizations from completing planned activities correctly as essential first-time work. Conformance works consists of course of actions that are related to prevention and inspection.

A

Conformance Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

A limiting factor that affects the execution of a project, program, portfolio, or process.

A

Constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

A visual depiction of the product scope showing a business system (process, equipment, computer system, etc.) and how people and other systems (actors) interact with it.

A

Context Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

An event or occurrence that could affect the execution of the project that may be accounted for with a reserve.

A

Contingency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

See reserve

A

Contingency Allowance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

Budget within the cost baseline or performance measurement baseline that is allocated for identified risks that are accepted and for which contingent or mitigating responses are developed.

A

Contingency Reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

Responses provided which may be used in the event that a specify trigger occurs

A

Contingent Response Strategies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

A mutually binding agreement that obligates the seller to provide the specified product or service or result and obligates the buyer to pay for it.

A

Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

The system used to collect, track, adjudicate, and communicate changes to a contract.

A

Contract Change Control System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

Comparing actual performance with planned performance, analyzing variances, assessing trends to effect process improvements, evaluating possible alternatives, and recommending appropriate corrective action as needed.

A

Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

A management control point where scope, budget, actual cost and schedule are integrated and compared to earned value for performance measurement.

A

Control Account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

A graphic display of process data over time and against established control limits, which has a centerline that assists in detecting a trend of plotted value toward either control limit.

A

Control Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

The process of monitoring and controlling communications throughout the entire project life cycle to ensure the information needs of the project stakeholders are met.

A

Control Communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

The process of monitoring the status of the project to update the project costs and managing changes to the cost baseline.

A

Control Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

The area composed of three standard deviations on either side of the centerline or mean of a normal distribution of data plotted on a control chart, which reflects the expected variation in the data. See also specification limits.

A

Control Limits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

The process of managing procurement relationships, monitoring contract performance, and making changes and corrections as appropriate.

A

Control Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

The process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes.

A

Control Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

The process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks and evaluating risk process effectiveness throughout the project.

A

Control Risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

The process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.

A

Control Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

The process of monitoring the status of the project and product scope and managing changes to the scope baseline.

A

Control Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

The process of monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders.

A

Control Stakeholder Engagement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

An intentional activity that realigns the performance of the project work with the project management plan.

A

Corrective Action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

Summing the lower-level cost estimates associated with the various work packages for a given level within the project’s WBS or of a given cost control account.

A

Cost Aggregation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

The approved versions of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as a basis for comparison to actual results.

A

Cost Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

A component of a project or program management plan that describes how cost will be planned, structured, and controlled.

A

Cost Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

A method of determining the costs incurred to ensure quality. Prevention and appraisal costs (cost of conformance) include costs for quality planning, quality control, and quality assurance to ensure compliance to requirements (i.e., training, quality control systems, etc.) Failure costs (cost of nonconformance) include costs to rework product, components, or processes that are non-compliant, costs of warranty work and waste, and lost of reputation.

A

Cost of Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.

A

Cost Performance Index (CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

A category of contract that involves payments to the seller for all legitimate actual costs incurred for completed work, plus an award fee representing seller profile.

A

Cost Plus Award Fee Contracts (CPAF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

A type of cost reimbursable contract where the buyer reimburse the seller for the seller’s allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee)

A

Cost Plus Fixed Fee Contract (CPFF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

A type of cost-reimbursable contract where the buyer reimburse the seller for the seller’s allowable costs (allowable costs are defined by the contract) and the seller earns its profit if it meets defined performance criteria.

A

Cost Plus Incentive Fee Contract (CPIF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.

A

Cost Variance (CV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

A financial analysis tool used to determine the benefits provided by a project against its costs.

A

Cost-Benefit Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

A type of contract involving payment to the seller for the seller’s actual costs, plus a fee typically representing seller’s profit. Cost-reimbursable contracts often include incentive clause where, if the seller meets or exceeds selected project objectives, such as schedule targets or total cost, then the seller receives from the buyer an incentive or bonus payment.

A

Cost-Reimbursable Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

A technique used to shorten the schedule duration for the least incremental cost by adding resources.

A

Crashing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

The process of subdividing project deliverables and project work into smaller, more manageable components.

A

Create WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

Standards, rules, or tests on which a judgement or decision can be baed or by which a product, service, result or process can be evaluated.

A

Criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.

A

Critical Chain Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

The sequence of activities that represent the longest path through a project, which determines the shortest possible durations.

A

Critical Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

Any activity on the critical path in a project schedule.

A

Critical Path Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.

A

Critical Path Method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

The person(s) or organization(s) that will pay for the project’s product, service, or result. Can be internal or external to the performing organization

A

Customers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

Within the quality management system, a state of fulfillment in which the needs of a customer are met or exceeded for the customer’s expected experiences as assessed by the customer at the moment of evaluation.

A

Customer Satisfaction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

A point in time when the status of the project is recorded.

A

Data Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

A diagramming and calculation technique for evaluating the implication of a change of multiple options in the presence of uncertainty.

A

Decision Tree Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.

A

Decomposition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

An imperfection or deficiency in a project component where that component does not meet its requirements or specifications and needs to be either repaired or replaced.

A

Defect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

An intentional activity to modify a nonconforming product or product component.

A

Defect Repair

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

The process of identifying and documenting the specific actions to be performed to produce the project deliverables.

A

Define Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

The process of developing a detailed description of the project and product.

A

Define Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
132
Q

Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project.

A

Deliverable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

An information gathering technique used as a way to reach consensus of experts on a subject. Experts on the subject participate in this technique anonymously. A facilitator uses a questionnaire to solicit ideas about the important project points related to the subject. The responses are summarized and are then recirculated to the experts for further comment. Consensus may be reached in a few rounds of this process. Helps reduce bias in data and keeps any one person from having undue influence on the outcome.

A

Delphi Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

A logical relationship between two activities, or between an activity and a milestone.

A

Dependency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

A technique used to identify the type of dependency that is used to create the logical relationship between predecessor and successor activities.

A

Dependency Determination

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
136
Q

A statistical method fo identifying which factor may influence specific variables of a product or process under development or in production.

A

Design of Experiments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
137
Q

The process of aggregating the estimated cost of individual activities or work packages to establish an authorized cost baseline

A

Determine Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
138
Q

The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

A

Develop Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
139
Q

The process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan.

A

Develop Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
140
Q

The process of improving competencies, team member interaction, and overall team environment to create the project schedule model.

A

Develop Project Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
141
Q

The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model

A

Develop Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
142
Q

Approaches to presenting information with logical linkages that aid in understanding.

A

Diagramming Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
143
Q

A group decision making technique in which one individual makes the decision for the group.

A

Dictatorship

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
144
Q

The process of learning and performing the work defined in the project management plan and implementing approved changes to achieve the project’s objectives.

A

Develop and Manage Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
145
Q

An activity that can be planned and measured and that yields a specific output. Is one of the three earned value management (EVM) types of activities used to measure work performance.

A

Discrete Effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
146
Q

A relationship that is established based on knowledge of best practice within a particular application area or an aspect of the project where a specified sequence is desired.

A

Discretionary Dependency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
147
Q

An elicitation technique that analyzes existing documentation and identifies information relevant to the requirements.

A

Document Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
148
Q

The process of gathering a corpus of information and reviewing it to determine accuracy and completeness.

A

Documentation Reviews

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
149
Q

The total number of work periods (not including holidays or other nonworking periods) required to complete a schedule activity or work breakdown structure component. Usually expressed as workdays or work weeks. Sometimes incorrectly equated with elapsed time. Contrast with effort.

A

Duration (DU or DUR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
150
Q

In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the data date, and nay schedule constraints.

A

Early Finish Date (EF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
151
Q

In the critical path method, the earliest possible point in time when the uncompleted portion of a schedule activity can start based on the schedule network logic, the data date and any schedule constraints.

A

Early Start Date (ES)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
152
Q

The measure of work performed expressed in terms of the budget authorized for that work.

A

Earned Value (EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
153
Q

A methodology that combines scope, schedule and resource measurements to assess project performance and process.

A

Earned Value Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
154
Q

The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks.

A

Effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
155
Q

The capability to identify, assess, an manage the personal emotions of oneself and other people, as well as the collective emotions of groups of people.

A

Emotional Intelligence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
156
Q

Conditions, not under the immediate control of the team, that influence, constrain, or direct the project, program or portfolio

A

Enterprise Environmental Factors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
157
Q

A quantitative assessment of the likely amount or outcome. Usually applied to project costs, resources, effort and durations and is usually preceded by a modifier (i.e., preliminary, conceptual, feasibility, order-of-magnitude, definitive) It should always include some indication of accuracy (e.g., + or - percent. See also budget and cost.

A

Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
158
Q

The process of estimating the number of work periods needed to complete individual activities with estimated resources.

A

Estimate Activity Durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
159
Q

The process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity.

A

Estimate Activity Resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
160
Q

The expected total cost of completing all work expressed as the sums of the actual cost to date and the estimate to complete.

A

Estimate at Completion (EAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
161
Q

The process of developing an approximation of the monetary resources needed to complete project activities.

A

Estimate Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
162
Q

The expected cost to finish all the remaining project work.

A

Estimate to Complete (ETC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
163
Q

Directing, managing, performing, and accomplishing the project work; providing the deliverables; and providing work performance information.

A

Execute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
164
Q

Those processes performed to complete the work defined in the project management plan to satisfy the project specifications.

A

Executing Process Group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
165
Q

A statistical technique that calculates the average outcome when the future includes scenarios that may or may not happen. A common use of this technique is within decision tree analysis.

A

Expected Monetary Value (EMV) Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
166
Q

Judgment provided based upon expertise in an application area, knowledge area, discipline, industry, etc., as appropriate for the activity being performed. Such expertise may be provided by any group or person with specialized education, knowledge, skill, experience or training.

A

Expert Judgement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
167
Q

A relationship between project activities and non-project activities.

A

External Dependency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
168
Q

An elicitation technique using focused sessions that bring key cross-functinoal stakeholders together to define product requirements.

A

Facilitated Workshops

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
169
Q

An analytical procedure in which each potential failure mode in every component of a product is analyzed to determine its effect on the reliability of that component and, by itself or in combination with other possible failure modes, on the reliability of the product or system and on the required function of the component; or the examination of a product (at the system and/or lower levels) for all ways that a failure may occur. For each potential failure, an estimate is made of its effect on the total system and of its impact. In addition, a review is undertaken of the action planned to minimize the probability of failure and to minimize its effects.

A

Failure Mode and Effect Analysis (FMEA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
170
Q

Include an alternative set of actions and tasks available in the event that the primary plan needs to be abandoned because issues, risks, or other causes.

A

Fallback Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
171
Q

A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.

A

Fast Tracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
172
Q

Represents profit as a component of compensation to a seller

A

Fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
173
Q

A point in time associated with a schedule activity’s completion. Usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, baseline, target, or current

A

Finish Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
174
Q

A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.

A

Finish-to-Finish (FF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
175
Q

A logical relationship in which a successor activity cannot start until a predecessor activity has finished.

A

Finish-to-Start (FS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
176
Q

A type of fixed price contract where the buyer pays the seller a set amount as defined by the contract, regardless of the seller’s cost.

A

Firm-Fixed-Price Contract (FFP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
177
Q

A decomposition technique that helps trace an undesirable effect back to its root cause. Also known as Cause and Effect Diagram

A

Fishbone Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
178
Q

An earned value method for assigning a specified percentage of budget value for a work package to the start milestone of the work package with the remaining budget value percentage assigned when the work package is complete.

A

Fixed Formula Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
179
Q

A type of contract where the buyer pays the seller a set amount (as defined by the contract) and the seller can each an additional amount if the seller meets defined performance criteria.

A

Fixed Price Incentive Fee Contract (FPIF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
180
Q

A fixed price contract, but with a special provision allowing for predefined final adjustments to the contract price due to change conditions, such as inflation changes or increases or decreases for specific commodities.

A

Fixed Price with Economic Price Adjustment Contracts (FP-EPA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
181
Q

An agreement that sets the fee that will be paid for a defined scope of work regardless of the cost or effort to deliver it.

A

Fixed-Price Contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
182
Q

The amount of time that a scheduled activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.

A

Free Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
183
Q

The depiction in a diagram format of the input, process actions, and outputs of one or more processes within a system.

A

Flowchart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
184
Q

An elicitation technique that brings together pre qualified stakeholders and subject matter experts to learn about their expectations and attitudes about a proposed project, service, or result.

A

Focus Group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
185
Q

An estimate or prediction of conditions and events in the project’s future based on information and knowledge available at the time of the forecast. The information is baed on the project’s past performance and expected future performances, and includes information that could impact the project in the future, such as estimate at completion and estimate to complete.

A

Forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
186
Q

A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.

A

Forward Pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
187
Q

Someone with management authority over an organizational unit within a functional organization. The manager of any group that actually makes a product or performs a service. Sometimes called a line manager.

A

Functional Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
188
Q

A hierarchical organization where each employee has one clear superior, and staff are grouped by areas of specialization and managed by a person with expertise in that area.

A

Functional Organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
189
Q

The process of comparing the planned expenditure of project funds against any limits on the commitment of funds for the project to identify any variances between the funding limits and the planned expenditures.

A

Funding Limit Reconciliation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
190
Q

A bar chart of schedule information where activities are listed on the vertical axis, date are shown on the horizontal axis, and activity duration are show as horizontal bars placed according to start and finish dates.

A

Gantt Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
191
Q

A category or rank used to distinguish items that have the same functional use (e.g., “hammer”) but do not share the same requirements for quality (e.g., different hammers may need to withstand different amounts of force)

A

Grade

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
192
Q

Expectations regarding acceptable behavior by project team members.

A

Ground Rules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
193
Q

Techniques that are used to generate ideas within a group of stakeholders.

A

Group Creativity Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
194
Q

Techniques to assess multiple alternatives that will be used to generate, classify, and prioritize product requirements.

A

Group Decision-Making Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
195
Q

An official recommendation or advice that indicates polices, standards, or procedures for how something should be accomplished.

A

Guideline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
196
Q

A group of related schedule activities aggregated and displayed as a single activity. Also known as Summary Activity

A

Hammock Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
197
Q

A relationship that is contractually required or inherent in the nature of the work. Also known as Mandatory Dependency.

A

Hard Logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
198
Q

A special form of bar chat used to describe the central tendency, dispersion, and shape of a statistical distribution.

A

Histogram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
199
Q

Documents and data on prior projects including project files, records, correspondence, closed contracts, and closed projects.

A

Historical Information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
200
Q

A component of the project management plan that describes how the roles and responsibilities, reporting relationship and staff management will be addressed and structured.

A

Human Resource Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
201
Q

Technique used to consolidate ideas created through individual brainstorming sessions into a single map to reflect commonality and differences in understanding and to generate a new ideas.

A

Idea/Mind Mapping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
202
Q

The process of determining which risks may affect the project and documenting their characteristics.

A

Identify Risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
203
Q

The process of identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or out of the project; and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence and potential impact on project success.

A

Identify Stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
204
Q

A fixed date imposed on a schedule activity or schedule milestone, usually in the form of a “start no earlier than” and “finish no later than” date.

A

Imposed Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
205
Q

A set of financial incentives related to cost, schedule, or technical performance of the seller.

A

Incentive Fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
206
Q

A project life cycle where the project scope is generally determined early in the project life cycle, but time and cost estimates are routinely modified as the project team’s understanding of the product increases. Iterations develop the product through a series of repeated cycles, while increments successively add to the functionality of the project.

A

Incremental Life Cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
207
Q

A process of using a third party to obtain and analyze information to support prediction of cost, schedule, or other items.

A

Independent Estimates

208
Q

A graphical representation of situations showing causal influence, time ordering of events, and other relationships among variables and outcomes.

A

Influence Diagram

209
Q

Repeatable processes used to assemble and organize data across a spectrum of sources.

A

Information Gathering Techniques

210
Q

Facilities, processes, and procedures used to collect, store, and distribute information between producers and consumers of information in physical or electronic format.

A

Information Management Systems

211
Q

Those processes performed to define a new project or a new phase of an existing project by obtaining authorization to start the project or phase.

A

Initiating Process Group

212
Q

Any item, whether internal or external to the project that is required by a process before that process proceeds. May be an output from a predecessor process.

A

Input

213
Q

Examining or measuring to verify whether an activity, component, product, result, or service conforms to specified requirements.

A

Inspection

214
Q

A process to observe performance of contracted work or a promised product against agreed upon requirements.

A

Inspections and Audits

215
Q

Ability to establish and maintain relationships with other people.

A

Interpersonal Skills

216
Q

A quality management planning tool the interrelationship digraphs provide a process for creative problem solving in moderately complex scenarios that posses intertwined logical relationships.

A

Interrelationship Digraphs

217
Q

A formal or informal approach to elicit information from stakeholders by talking to them directly.

A

Interviews

218
Q

Generally, this term is equivalent to request for proposal. However, in some application areas, it may have a narrower or more specific meaning.

A

Invitation for Bid (IFB)

219
Q

A point or matter in question or in dispute, or a point or matter that is not settled and is under discussion or over which there are opposing views or disagreements.

A

Issue

220
Q

A project document used to document and monitor elements under discussion or in dispute between project stakeholders.

A

Issue Log

221
Q

A project life cycle where the project scope is generally determined early in the project life cycle, but time and cost estimates are routinely modified as the project team’s understanding of the product increases. Iterations develop the product through a series of repeated cycles, while increments successively add to the functionality of the product.

A

Iterative Life Cycle

222
Q

The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.

A

Lag

223
Q

In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints.

A

Late Finish Date (LF)

224
Q

In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can start based on schedule network logic, the project completion date, and any schedule constraints.

A

Late Start Date (LS)

225
Q

The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.

A

Lead

226
Q

The knowledge gained during a project which shows how project events were addressed or should be addressed in the future with the purpose of improving future performance.

A

Lessons Learned

227
Q

A store of historical information and lessons learned about both the outcomes of previous project selection decisions and previous project performance.

A

Lessons Learned Knowledge Base

228
Q

An activity that does not produce definitive end products and is measured by the passage of time. Is one of the 3 earned value management types of activities used to measure work performance

A

Level of Effort (LOE)

229
Q

A document used to record and describe or denote selected items identified during execution of a process or activity. Usually used with a modifier, such as issue, quality control, action or defect.

A

Log

230
Q

A dependency between two activities or between an activity and a milestone.

A

Logical Relationship

231
Q

Support from more than 50% of the members of the group.

A

Majority

232
Q

The process of gathering and organizing data about product requirements and analyzing them against available alternatives including the purchase or internal manufacture of the product.

A

Make-or-Buy Decisions

233
Q

The process of creating, collecting, distributing, storing, retrieving and the ultimate disposition of project information in accordance with the communication management plan.

A

Manage Communications

234
Q

The process of tracking team member performance, providing feedback, resolving issues and managing team changes to optimize project performance.

A

Manage Project Team

235
Q

The process of communicating and working with stakeholders to meet their needs/expectations, address issues as they occur, and foster appropriate stakeholder engagement in project activities throughout the project life cycle.

A

Manage Stakeholder Engagement

236
Q

An amount of project budget withheld for management control purposes. These are budgets reserved for unforeseen work that is within scope of the project. This is not included in the performance measurement baseline.

A

Management Reserve

237
Q

The ability to plan, organize, direct and control individuals or groups of people to achieve specific goals.

A

Management Skills

238
Q

A relationship that is contractually required or inherent in the nature of the work.

A

Mandatory Dependency

239
Q

The process of gathering information at conferences, online reviews, and a variety of sources to identify market capabilities.

A

Market Research

240
Q

A summary level project schedule that identifies the major deliverables and work breakdown structure components and key schedule milestones. Also known as milestone schedule.

A

Master Schedule

241
Q

The aggregate of things used by an organization in any undertaking, such as equipment, apparatus, tools, machinery, gear, material and supplies

A

Material

242
Q

A quality management and control tool used to perform data analysis within the organizational structure created in the matrix. The matrix diagram seeks to show the strength of relationships between factors, causes, and objectives that exist between the rows and columns that form the matrix

A

Matrix Diagram

243
Q

Any organizational structure in which the project manager shares responsibility with the functional managers for assigning priorities and for directing the work of persons assigned to the project.

A

Matrix Organization

244
Q

A system of practices, techniques, procedures and rules used by those who work in a discipline.

A

Methodology

245
Q

A significant point or event in a projet, program or portfolio.

A

Milestone

246
Q

A list identifying all project milestones and normally indicates whether the milestone is mandatory or optional.

A

Milestone List

247
Q

A summary level schedule that identifies the major schedule milestones. Also known as Master Schedule.

A

Milestone Schedule

248
Q

Collect project performance data with respect to a plan, produce performance measures, and report and disseminate performance information.

A

Monitor

249
Q

The process of tracking, reviewing, and reporting the progress to meet the performance objectives defined in the project management plan.

A

Monitor and Control Project Work

250
Q

Those processes required to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes.

A

Monitoring and Controlling Process Group

251
Q

A process which generates hundreds or thousands of probable performance outcomes baed on probability distributions for cost and schedule on individual tasks. The outcomes are then used to generate a probability distribution for the project as a whole.

A

Monte Carlo Simulation

252
Q

An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.

A

Most Likely Duration

253
Q

This technique utilizes a decision matrix to provide a systematic analytical approach for establishing criteria, such as risk levels, uncertainty, and valuation, to evaluate and rank many ideas.

A

Multi-Criteria Decision Analysis

254
Q

A schedule activity that has low total float. The concept is equally applicable to a schedule activity or schedule network path. The limit below which total float is considered near critical is subject to expert judgement and varies from project to project.

A

Near-Critical Activity

255
Q

The process of reaching final equitable settlement of all outstanding issues, claims, and disputes through negotiation.

A

Negotiated Settlements

256
Q

The process and activities to resolve disputes through consultation between involved parties.

A

Negotiation

257
Q

The collection of schedule activity dependencies that make up a project schedule network diagram.

A

Network Logic

258
Q

Any continuous series of schedule activities connected with logical relationships in a project schedule network diagram.

A

Network Path

259
Q

Establish connections and relationships with other people from the same or other organizations.

A

Networking

260
Q

One of the defining points of a schedule network; a junction point joined to some or all of the other dependency lines.

A

Node

261
Q

A technique that enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization.

A

Nominal Group Technique

262
Q

In the cost of quality framework, nonconformance work is done to deal with the consequences of errors and failures in doing activities correctly on the first attempt. In efficient quality management systems, the amount of nonconformance work will approach zero.

A

Nonconformance Work

263
Q

Something toward which work is to be directed, a strategic position to be attained, a purpose to be achieved, a result to be obtained, a product to be produced, or a service to be performed.

A

Objective

264
Q

A technique that provides a direct way of viewing individuals in their environment performing their jobs or tasks and carrying out processes.

A

Observations

265
Q

A risk that would have a positive effect on one or more project objectives

A

Opportunity

266
Q

An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.

A

Optimistic Duration

267
Q

A hierarchical representation of the project organization that illustrates the relationship between project activities and the organizational units that will perform those activities.

A

Organizational Breakdown Structure (OBS)

268
Q

Plans, processes, policies, procedures, and knowledge bases that are specific to and used by the performing organization.

A

Organizational Process Assets

269
Q

The level of an organization’s ability to deliver the desired strategic outcomes in a predictable, controllable, and reliable manner.

A

Organizational Project Management Maturity

270
Q

A product, result, or service generated by a process. May be in input to a successor process.

A

Output

271
Q

An estimating technique in which an algorithm is used to calcite cost or duration based on historical data and project parameters.

A

Parametric Estimating

272
Q

A histogram, ordered by frequency of occurrence, that shows how many results were generated by each identified cause.

A

Pareto Diagram

273
Q

A relationship in which a schedule activity has more than one predecessor.

A

Path Convergence

274
Q

A relationship in which a schedule activity has more than one successor.

A

Path Divergence

275
Q

The system used to provide and track supplier’s invoices and payments for services and products.

A

Payment Systems

276
Q

An estimate expressed as a percent of the amount of work that has been completed on an activity or work breakdown structure component.

A

Percent Complete

277
Q

The process of reviewing all change requests; approving change and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition.

A

Perform Integrated Change Control

278
Q

The process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact.

A

Perform Qualitative Risk Analysis

279
Q

The process of auditing the quality requirements and the results from quality control measurements to ensure the appropriate quality standards and operational definitions are used.

A

Perform Quality Assurance

280
Q

The process of numerically analyzing the effect of identified risks on the overall project objectives.

A

Perform Quantitative Risk Analysis

281
Q

An approved, integrated scope schedule change plan for the project work against which project execution is compared to measure and manage performance. Includes contingency reserve, but excludes management reserve.

A

Performance Measurement Baseline (PMB)

282
Q

A technique that is used to measure, compare, and analyze actual performance of work in progress on the project against the baseline.

A

Performance Reviews

283
Q

An enterprise whose personnel are most directly involved in doing the work of the project or program.

A

Performing Organization

284
Q

Estimate the longest activity duration that takes into account all of the known variables that could affect performance.

A

Pessimistic Duration

285
Q

A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a project or program.

A

Phase Gate

286
Q

The process of developing an appropriate approach and plan for project communications based on stakeholder’s information needs and requirements and available organizational assets

A

Plan Communication Management

287
Q

The process that establishes the policies and procedures and documentation for planning, managing, expending and controlling project costs.

A

Plan Cost Management

288
Q

The process of identifying and documenting project roles, responsibilities, required skills, reporting relationships and creating a staff management plan.

A

Plan Human Resource Management

289
Q

The process of documenting procurement decisions, specifying the approach, and identifying potential sellers.

A

Plan Procurement Management

290
Q

The process of identifying quality requirements and/or standards for the project and its deliverables and documenting how the project will demonstrate compliance with quality requirements

A

Plan Quality Management

291
Q

The process of defining how to conduct risk management activities for a project.

A

Plan Risk Management

292
Q

The process of developing options and actions to enhance opportunities and to reduce threats to project objectives.

A

Plan Risk Responses

293
Q

The process of establishing the policies, procedures, and documentation for planning developing managing, executing and controlling the project schedule

A

Plan Schedule Management

294
Q

The process of creating a scope management plan that documents how the project scope will be defined, validated, and controlled.

A

Plan Scope Management

295
Q

The authorized budget assigned to scheduled work.

A

Planned Value (PV)

296
Q

A work breakdown structure component below the control account with known work content but without detailed schedule activities. See also control account.

A

Planning Package

297
Q

Those processes require to establish the scope of the project, refine objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve.

A

Planning Process Group

298
Q

Decisions made by the larger block in a group, even if a majority is not achieved.

A

Plurality

299
Q

A structure pattern of actions adopted by an organization such that the organization’s policy can be explained as set of basic principles that govern the organization’s conduct.

A

Policy

300
Q

Projects, programs, and sub portfolios and operations managed as a group to achieve strategic objectives.

A

Portfolios

301
Q

The centralized management of one or more portfolios to achieve strategic objectives.

A

Portfolio Management

302
Q

A specific type of professional or management activity that contributes to the execution of a process and that may employ one or more techniques and tools.

A

Practice

303
Q

A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or ore logical relationships to show the sequence in which the activities are to be performed.

A

Precedence Diagramming Method (PDM)

304
Q

The term used in the precedence diagramming method for a logical relationship. In current usage, however, precedence relationship, logical relationship and dependency are widely used interchangeably regardless of the diagramming method used. See also logical relationship

A

Precedence Relationship

305
Q

Within the quality management system this is a measure of exactness.

A

Precision

306
Q

An activity that logically come before a dependent activity in a schedule

A

Predecessor Activity

307
Q

A form of project life cycle in which the project scope, and the time and cost required to deliver that scope, are determined as early in the life cycle as possible.

A

Predictive Life Cycle

308
Q

An intentional activity that ensures the future performance of the project work is aligned with the project management plan

A

Preventive Action

309
Q

A quality management planning tool used to identify key issues and evaluate suitable alternatives to define a set of implementation priorities.

A

Prioritization Matrices

310
Q

A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.

A

Probability and Impact Matrix

311
Q

An established method for accomplishing a consistent performance or result, a procedure typically can be described as the sequence of steps that will be sued to execute a process.

A

Procedure

312
Q

A systematic series of activities directed toward causing an end result such that one or more inputs will be acted upon to create one or more outputs.

A

Process

313
Q

Follows the steps outlined in the process improvement plan to identify needed improvements

A

Process Analysis

314
Q

Used to understand a goal in relation to the steps for getting to the goal.

A

Process Decision Program Charts

315
Q

A subsidiary plan of the project management plan. It details the steps for analyzing process to identify activities that enhance their value.

A

Process Improvement Plan

316
Q

The review of contracts and contracting processes for completeness, accuracy, and effectiveness

A

Procurement Audits

317
Q

The documents utilized in bid and proposal activities which include the buyer’s Invitation for Bid, Invitation for Negotiations, Request for Information, Request for Quotation, Request for Proposal, and seller’s responses.

A

Procurement Documents

318
Q

A component of the project or program management plan that describes how a project team will acquire goods and services from outside the performing organizations.

A

Procurement Management Plan

319
Q

A structured review of the seller’s progress to deliver project scope and quality, within cost and on schedule, as compared to the contract.

A

Procurement Performance Reviews

320
Q

Describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the product, services, or results.

A

Procurement Statement of Work

321
Q

An artifact that is produced, is quantifiable and can be either an end item in itself or a component item. Also known as material and goods. Contrast with results. See also deliverables.

A

Product

322
Q

For projects that have a product as a deliverable, it is a tool to define scope that generally means asking questions about a product and forming answers to describe the use, characteristics and other relevant aspects of what is going to be manufactured.

A

Product Analysis

323
Q

The series of phases that represent the evolution of product, from concept through delivery, growth, maturity, and to retirement.

A

Product Life Cycle

324
Q

The features and function that characterize a product, service, or result.

A

Product Scope

325
Q

The documented narrative description of the product scope.

A

Product Scope Description

326
Q

A group of related projects, subprograms, and program activities managed in a coordinated way to obtain benefits not available from managing them individually.

A

Program

327
Q

A technique for estimating that applies a weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.

A

Program Evaluation and Review Techniques (PERT)

328
Q

The application of knowledge, skills, tools, and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.

A

Program Management

329
Q

The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.

A

Progressive Elaboration

330
Q

A temporary endeavor undertaken to create a unique product, service, or result.

A

Project

331
Q

A variety of organizational forms that involve the creation of temporary systems for the performance of projects. Conduct a majority of their activities as projects and/or provide project over functional approaches

A

Project Based Organization (PBO)

332
Q

A calendar that identifies working days and shifts that are available for schedule activities.

A

Project Calendar

333
Q

A document issues by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

A

Project Charter

334
Q

Includes the processes that are required to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring, and the ultimate disposition of project information.

A

Project Communication Management

335
Q

Includes the process involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget.

A

Project Cost Management

336
Q

Forecast project costs to be paid that are derived from the cost baseline for total or periodic requirements including projected expenditures plus anticipated liabilities.

A

Project Funding Requirements

337
Q

The alignment of project objectives with the strategy of the larger organization by the project sponsor and project team. A project’s governance is defined by and is required to fit within the larger context of the program or organization sponsoring it, but is separate from organizational governance.

A

Project Governance

338
Q

Includes the process that organize, manage, and lead the project team.

A

Project Human Resource Management

339
Q

Launching a process that can result in the authorization of a new project

A

Project Initiation

340
Q

Includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Group.

A

Project Integration Management

341
Q

The series of phases that a project passes through from its initiation to its closure.

A

Project Life Cycle

342
Q

The application of knowledge, skills, tools, and techniques to project activities to mer the project requirements.

A

Project Management

343
Q

An inclusive term that describes the sum of knowledge within the profession of project management. As with other professions, such as law, medicine, and account, the body of knowledge rest with the practitioners and academics that apply and advance it. The complete project management body of knowledge includes proven traditional practice that are widely applied and innovative practices that are emerging in the profession. The body of knowledge included both published and unpublished materials. This body of knowledge is constantly evolving. PMI’s PMBOK Guide identifies a subset of the project management body of knowledge that is generally recognized as good practice.

A

Project Management Body of Knowledge

344
Q

An information system consisting of tools and techniques used to gather, integrate and disseminate the outputs of project management processes. It is used to support all aspects of the project from initiating through closing, and can include both manual and automated systems.

A

Project Management Information System

345
Q

An identified area of project management defined by its knowledge requirements and described it term of its component processes, practices, inputs, output, tools and techniques.

A

Project Management Knowledge Area

346
Q

An organizational structure that standardizes the project related governance process and facilitates the sharing of resources, methodologies, tool and techniques.

A

Project Management Office (PMO)

347
Q

The document that describes how the project will be executed monitored and controlled.

A

Project Management Plan

348
Q

A logical grouping of project management inputs, tools and techniques, and outputs. Includes initiating processes, planning processes, executing processes, monitoring and controlling processes, and closing processes. Not project phases.

A

Project Management Process Group

349
Q

The members of the project team who perform project management activities such as schedule, communication, risk management, etc.

A

Project Management Staff

350
Q

The aggregation of the processes, tools, techniques, methodologies, resources and procedures to manage a project.

A

Project Management System

351
Q

The members of the project team who are directly involved in project management activities. On some smaller projects, the project management team may include virtually all of the project team members.

A

Project Management Team

352
Q

The person assigned by the performing organization to the lead the team that is responsible for achieving the project objectives.

A

Project Manager (PM)

353
Q

A document that graphically depicts that project team members and their interrelationships for a specific project.

A

Project Organization Chart

354
Q

A collection of logically related project activities that culminates in the completion of one or more deliverables.

A

Project Phase

355
Q

Includes the processes necessary to purchase or acquire products, services, or results needed from outside the project team.

A

Project Procurement Management

356
Q

Includes the processes and activities of performing organization that determine quality polices, objectives, and responsibilities so that the project will satisfy the needs for which it was undertaken.

A

Project Quality Management

357
Q

Includes the processes of conducting risk management, planning, identification, analysis, response planning, and controlling risk on a project.

A

Project Risk Management

358
Q

An output of schedule model that present linked activities with planned dates, durations, milestone, and resources.

A

Project Schedule

359
Q

A graphical representation of the logical relationship amount the project schedule activities.

A

Project Schedule Network Diagram

360
Q

The work performed to deliver a product, service, or result with the specified features and functions.

A

Project Scope

361
Q

Includes the processes required to ensure that the project includes all the work required and only the work required to complete the project successfully

A

Project Scope Management

362
Q

The description of the project scope, major deliverables, assumptions, and constraints.

A

Project Scope Statement

363
Q

Include the processes required to identify the people, groups, or organizations that could impact or be impacted by the project, to analyze stakeholder expectations and their impact on the project, and to develop appropriate management strategies for effectively engaging stakeholders in project decision and execution.

A

Project Stakeholder Management

364
Q

A narrative description of products services, or results to be delivered by the project.

A

Statement of Work or Project Statement of Work

SOW

365
Q

A set of individuals who support the project manager in performing the work of the project to achieve the objectives.

A

Project Team

366
Q

A documented list of project team members, their project roles, and communication information.

A

Project Team Directory

367
Q

Include the process required to manage the timely completed of the project.

A

Project Time Management

368
Q

Any organization structure in which the project manager has full authority to assigned priorities, apply resources, and direct the work of persons assigned to the project.

A

Projectized Organization

369
Q

The process of reviewing proposals provided by suppliers to support contract award decisions.

A

Proposal Evaluation Techniques

370
Q

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building it.

A

Prototypes

371
Q

The degree to which a set of inherent characteristics fulfill requirements.

A

Quality

372
Q

Is a structured, independent process to determine if project activities comply with organizational and project policies, processes, and procedures.

A

Quality Audit

373
Q

A structure tool used to verify that a set of required steps have been performed

A

Quality Checklists

374
Q

The documented results of control quality activities.

A

Quality Control Measurements

375
Q

A facilitate workshop technique that helps to determine critical characteristics for new product development.

A

Quality Function Deployment (QFD)

376
Q

The are types of quality planning tools used to link and sequence the activities identified.

A

Quality Management and Control Tools

377
Q

A component of the project or program management plan that describes how an organization’s quality policies will be implemented.

A

Quality Management Plan

378
Q

The organizational framework whose structure provides the policies, processes, procedures, and resources required to implement the quality management plan. The typical project quality management plan should be compatible to the organization’s quality management system.

A

Quality Management System

379
Q

A description of a project or product attribute and how to measure it.

A

Quality Metrics

380
Q

A policy specific to the Project Quality Management Knowledge Area, it establishes the basic principles that should govern the organization’s actions as it implements its system for quality management.

A

Quality Policy

381
Q

A condition or capability that will be used to assess conformance by validating the acceptability of an attribute for the quality of a result.

A

Quality Requirement

382
Q

Commonly used technique for both event oriented and project oriented analyze approaches.

A

Quantitative Risk Analysis and Modeling Technique

383
Q

Written set of questions designed to quickly accumulate information from a larger number of respondents.

A

Questionnaires

384
Q

A common type of responsibility assignment matrix that uses responsible, accountable, consult and inform statuses to define the involvement of stakeholders in project activities.

A

RACI

385
Q

A specific set of processes, related control functions, and tools that are consolidated and combined to record and retain information about the project.

A

Records Management System

386
Q

An analytic technique where a series of input variables are examined in relation to their corresponding output results in order to develop a mathematical or statistical relationship.

A

Regression Analysis

387
Q

Requirements imposed by a governmental body, These requirements can establish product, process, or service characteristics, including applicable administrative provisions that have government mandated compliance.

A

Regulation

388
Q

Facilities, processes, and procedures used to generate or consolidate reports fro one or more information management systems and facilitate report distribution to the project stakeholders.

A

Reporting Systems

389
Q

A type of procurement document whereby the buyer requests a potential seller to provide various pieces of information related to a produce or service or seller capability.

A

Request for Information (RFI)

390
Q

A type of procurement document used to request proposals from prospective sellers of products or services. In some application areas, it may have a narrower or more specific meaning.

A

Request for Proposal (RFP)

391
Q

A type of procurement document used to request price quotations from prospective sellers of common or standard products or services. Sometimes used in place of request for propose and in some application areas, it may have a narrower or more specific meaning.

A

Request for Quotation (RFQ)

392
Q

A formally documented change request that is submitted for approval to the integrated change control process.

A

Requested Change

393
Q

A condition or capability that is required to be present in a product, service or result to satisfy a contract or other formally imposed specification.

A

Requirement

394
Q

A description of how individual requirements mer the business need for the project.

A

Requirements Documentation

395
Q

A component of the project or program management plan that describes how requirements will be analyzed, documented, and managed.

A

Requirements Management Plan

396
Q

A grid that links product requirements from their origin to the deliverables that satisfy them.

A

Requirements Traceability Matrix

397
Q

A provision in the project management plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g., management reserve, contingency reserver) to provide further detail on what types of risk are meant to be mitigated.

A

Reserver

398
Q

An analytical technique to determine the essential features and relationship of components in the project management plan to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project.

A

Reserve Analysis

399
Q

A risk that remains after risk response have been implemented.

A

Residual Risk

400
Q

Skilled human resources (specific disciplines either individually or in crews or teams), equipment, services, supplies, commodities, materials, budgets or funds.

A

Resource

401
Q

A hierarchical representation of resource by category or type.

A

Resource Breakdown Structure

402
Q

A calendar that identifies the working days and shifts on which each specific resource is available.

A

Resource Calendar

403
Q

A bar chart showing the amount of time that a resource is scheduled to work over a series of time periods. Resource availability may be depicted as a line for comparison purposes. Contrasting bars may show actual amount of resources used as the project progresses.

A

Resource Histogram

404
Q

A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supple.e

A

Resource Leveling

405
Q

A technique that is used to adjust the start and finish dates of activities that adjust planned resource used to be equal to or less than resource availability.

A

Resource Optimization Techniques

406
Q

A technique which adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits.

A

Resource Smoothing

407
Q

An assignment that can be delegated within a project management plan such that the assigned resource incurs a duty to perform the requirements of the assignment.

A

Responsibility

408
Q

A grid that shows that project resource assigned to each work package.

A

Responsibility Assignment Matrix (RAM)

409
Q

An output from performing project management processes and activities. Results include outcomes - integrated systems, revised process, restructured organizations, test, trained personnel and documents - polices, plans, studies, procedures, specifications, reports. Contrast with product. See also delivertables

A

Result

410
Q

Action taken to bring a defective or nonconforming component into compliance with requirements or specifications.

A

Rework

411
Q

An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.

A

Risk

412
Q

A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.

A

Risk Acceptance

413
Q

The degree of uncertainty an entity is will to take on, in anticipation of a reward.

A

Risk Appetite

414
Q

Examination and documentation of the effectiveness of risk responses in dealing with identified risk and their root causes, as well as the effectiveness of the risk management plan.

A

Risk Audits

415
Q

A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.

A

Risk Avoidance

416
Q

A hierarchical representation of risks according to their risk categories.

A

Risk Breakdown Structure (RBS)

417
Q

Organization by source of risk (using the RBS), the area of the project affected (using the WBS) or other useful category (project phase) to determine the areas of the project most exposed to the effects of uncertainty.

A

Risk Categorization

418
Q

A group of potential causes of risk.

A

Risk Category

419
Q

Technique to evaluate the degree to which the data about risks is useful for risk management.

A

Risk Data Quality Assessment

420
Q

A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed.

A

Risk Management Plan

421
Q

A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.

A

Risk Mitigation

422
Q

The identification of new risks, reassessment of current risks, and the closing of risks that are outdated.

A

Risk Reassessment

423
Q

A document in which the results of risk analysis and risk response planning are recorded.

A

Risk Register

424
Q

Measure the level of uncertainty or the level of impact at which a stakeholder may have a specific interest. Below that risk threshold, the organization will accept the risk. About that risk threshold, the organization will not tolerate the risk.

A

Risk Threshold

425
Q

The degree, amount, or volume of risk that an organization or individual will withstand.

A

Risk Tolerance

426
Q

A risk response strategy whereby the project team shifts the impact of a threat to a third party, together with ownership of the response.

A

Risk Transference

427
Q

Review and determination of the timing of actions that may need to occur sooner then other risk items.

A

Risk Urgency Assessment

428
Q

A define function to be performed by a project team member, such as testing, filing, inspecting or coding.

A

Role

429
Q

An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.

A

Rolling Wave Planning

430
Q

An analytical technique to determine the basic underlying reason that causes a variance or defect or risk. A root cause may under lie more than one variance or defect or risk.

A

Root Cause Analysis

431
Q

A correlation chart that uses a regression line to explain or to predict how the change in an independent variable will change a dependent variable.

A

Scatter Diagram

432
Q

The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.

A

Schedule Baseline

433
Q

Techniques used to shorten the schedule durations without reducing the project scope.

A

Schedule Compression

434
Q

The collection of information for describing and controlling the schedule.

A

Schedule Data

435
Q

Estimates or predictions of conditions and events in the project’s future based on information and knowledge available at the time the schedule is calculated.

A

Schedule Forecast

436
Q

A component of the project management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule.

A

Schedule Management Plan

437
Q

A representation of a the plan for executing the project’s activities including durations, dependencies, and other planning information, used to produce a project schedule along with other scheduling artifacts.

A

Schedule Model

438
Q

The technique of identifying early and late start dates, as well as early and late finish dates, for the uncompleted portion of the project schedule activities. See also backward pass, critical path method, critical chain method, and resource leveling.

A

Schedule Network Analysis

439
Q

A set of activities and relationships that have been established that can be used repeatedly for a particular application area or an aspect of the project where a prescribed sequence is desired.

A

Schedule Network Templates

440
Q

A measure of schedule efficiency expresses as the ratio of earned value (EV) to planned value (PV)

A

Schedule Performance Index (SPI)

441
Q

A measure of schedule performance expressed as the difference between the earned value and the planned value.

A

Schedule Variance (SV)

442
Q

A told that provides schedule component names, definitions, structural relationships, and formats that support the application of scheduling method.

A

Scheduling Tool

443
Q

The sums of products, services, and results to be provided as a project. See also project scope and product scope.

A

Scope

444
Q

The approved version of a scope statement, work breakdown structure (WBS) and its associated WBS dictionary, that can be changed only through formal change control procedures and is used as a basis for comparison.

A

Scope Baseline

445
Q

Any change to the project scope. A scope change almost always requires an adjustment to the project cost or schedule.

A

Scope Change

446
Q

The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.

A

Scope Creep

447
Q

A component of the project or program management plan that describes how scope will be defined, developed, monitored, controlled, and verified.

A

Scope Management Plan

448
Q

A risk that arises as a direct result of implementing a risk response

A

Secondary Risk

449
Q

The sellers which have been selected to provide a contracted set of services or products.

A

Selected Sellers

450
Q

A provider or supplier of products, services, or results to an organization

A

Seller

451
Q

Formal responses from seller to a request for proposal or other procurement document specifying the price, commercial terms of sale, and technical specifications or capabilities the seller will do for the requesting organization that, if accepted, would bind the seller to perform the resulting agreement.

A

Seller Proposal

452
Q

A quantitative risk analysis and modeling technique used to help determine which risks have the most potential impact on the project. It examines the extent to which the uncertainty of each project element affects the objectives being examined when all other uncertain elements are held at their baselines values. The typical display of results in in the form of a tornado diagram.

A

Sensitivity Analysis

453
Q

The process of identifying and documenting relationships among the project activities.

A

Sequence Activities

454
Q

A standard toolkit used by quality management professionals who are responsible for planning, monitoring and controlling the issues related to quality in an organization.

A

Seven Basic Quality Tools

455
Q

Uses a project model that translates the uncertainties specified at a detailed level into their potential impact on objectives that are expressed at the level of the total project. Uses computer models and estimates of risk usually expressed as a probability distribution of possible costs or durations at a detailed work level and are typically performed using Monte Carlo analysis.

A

Simulations

456
Q

A set attributes desired by the buyer which a seller is required to meet or exceed to be selected for a contract.

A

Source Selection Criteria

457
Q

A document that specifies, in a complete, precise, verifiable manner, the requirements, design, behavior or other characteristics of a system, component, product, result, or service and the procedures for determining whether these provisions have been satisfied. Examples are: requirement specification, design specification, product specification, and test specification.

A

Specification

458
Q

The area, on either side of the centerline, or mean, of data plotted on a control chart that meets the customer’s requirements for a product or service. This area may be greater than or less than the area defined by the control limits. See also control limits.

A

Specification Limits

459
Q

A person or group who provides resources and support for the project, program or portfolio and it accountable for enabling success

A

Sponsor

460
Q

The entity responsible for providing the project’s sponsor and a conduit for project funding or other project resources.

A

Sponsoring Organization

461
Q

A component of the human resource plan that describes when and how project team members will be acquired and how long they will be needed.

A

Staffing Management Plan

462
Q

An individual, group, or organization who may affect, be affected by, or perceive itself to be affected by a decision, activity or outcome of a project.

A

Stakeholder

463
Q

A technique of systematically gathering and analyzing quantitative and qualitative information to determine whose interests should be taken into account throughout the project.

A

Stakeholder Analysis

464
Q

A subsidiary plan of the project management plan that defines the processes, procedures, tools and techniques to effective engage stakeholders in project decisions and execution based on the analysis of their needs, interests and potential impacts.

A

Stakeholder Management Plan

465
Q

A project document including the identification, assessment and classification of project stakeholders.

A

Stakeholder Register

466
Q

A document that provides, for common and repeated use, rules, guidelines, or characteristics for activities for their results, aimed at the achievement of the optimum degree in a given context.

A

Standard

467
Q

A point in time associated with a schedule activity’s start, usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, target, baseline, or current

A

Start Date

468
Q

A logical relationship in which a successor activity cannot finish until a predecessor activity has started

A

Start-to-Finish

469
Q

A logical relationship in which a successor activity cannot start until a predecessor activity has started.

A

Start-to-Start

470
Q

A narrative description of products, services, or results to be delivered by the project.

A

Statement of Work (SOW)

471
Q

Choosing part of a population of interest for inspection.

A

Statistical Sampling

472
Q

A subdivision (fragment) of a project schedule network diagram, usually representation a subproject or a work package. Often used to illustrate or study some potential or proposed schedule conditions, such as changes in preferential schedule logic or project scope.

A

Subnetwork

473
Q

A smaller portion of the overall project created when a project is subdivided into more manageable components or pieces.

A

Subproject

474
Q

A dependent activity that logically comes after another activity in a schedule.

A

Successor Activity

475
Q

A group of related schedule activities aggregated and displayed as a single activity.

A

Summary Activity

476
Q

Analysis of strengths, weaknesses, opportunities, and threats of an organization, project, or option

A

SWOT Analysis

477
Q

The act of carefully selecting process and related inputs and outputs contained with the PMBOK Guide to determine a subset of specific processes that will be included within a project’s overall management approach.

A

Tailor

478
Q

A defined systematic procedure employed by a human resource to perform an activity to produce a product or result or deliver a service and that may employe one or more tools.

A

Technique

479
Q

A partially completed document in a predefined format that provides a defined structure for collecting, organizing, and presenting information and data.

A

Templates

480
Q

A risk that would have a negative effect on one or more project objectives.

A

Threat

481
Q

A technique used to estimate cost or duration by applying an average of optimistic, pessimistic and most likely estimates when there is uncertainty with the individual activity estimates.

A

Three-Point Estimates

482
Q

A cost, time, quality, technical or resource value used as a parameter and which may be included in product specifications. Crossing the threshold should trigger some actin, such as generating an exception report.

A

Threshold

483
Q

A type of contract that is a hybrid contractual arrangement containing aspects of both cost-reimbursable and fixed-price contracts. Time and material contracts. No definitive end, because the full value of the arrangement is not defined at the time of the award. Can grow in contract value.

A

Time and Materials Contract

484
Q

Any project schedule network diagram drawn in such a way that the positioning and length of the schedule activity represents its duration. Essentially, it is a bar chart that includes schedule network logic.

A

Time-Scaled Schedule Network Diagram

485
Q

A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.

A

To-Complete Performance Index (TCPI)

486
Q

The quantified description of acceptable variation for a quality requirement.

A

Tolerance

487
Q

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables.

A

Tornado Diagram

488
Q

Something tangible, such as a template or software program, used in performing an activity to produce a product or result.

A

Tool

489
Q

The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.

A

Total Float

490
Q

A systematic diagram of a decomposition hierarchy used to visualize as parent-to-child relationship a systematic set of rules.

A

Tree Diagram

491
Q

An analytical technique that uses mathematical models to forecast future outcomes baed on historical results. It is a method of determining the variance from a baseline of a budget, cost, schedule, or scope parameter by using prior progress reporting periods data and projecting how much that parameter’s variance from baseline might be at some future point in the project if no changes are made in executing the project.

A

Trend Analysis

492
Q

An event of situation that indicates that a risk is about to occur.

A

Trigger

493
Q

Agreement by everyone in the group on a single course of action.

A

Unanimity

494
Q

The process of formalizing acceptance of the completed project deliverables.

A

Validate Scope

495
Q

The assurance that a product, service, or system meets the needs of the customer and other identified stakeholders. It often involves acceptance and suitability with external customers. Contrast with verification.

A

Validation

496
Q

An approach used to optimize project life cycle costs, save time, increase profits, improve quality, expand market share, solve problems, and/or use resources more effectively.

A

Value Engineering

497
Q

A quantifiable deviation, departure, or divergence away from a known baseline or expected value.

A

Variance

498
Q

A technique for deterring the cause and degree of difference between the baseline and actual performance.

A

Variance Analysis

499
Q

A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion.

A

Variance at Completion (VAC)

500
Q

An actual condition that is different from the expected condition that is contained in the baseline plan.

A

Variation

501
Q

A measure of a team’s productivity rate at which the deliverables are produced, validated, and accepted within a predefined internal. Is a capacity planning approach frequently used to forecast future project work.

A

Velocity

502
Q

The evaluation of whether or note product, service, or system complies with a regulation, requirement, specification or imposed condition. It is often an internal process. Contracts with validation

A

Verification

503
Q

Completed project deliverables that have been checked and confirmed for correctness through the Control Quality process.

A

Verified Deliverables

504
Q

A planning technique used to provide products, services, and results that truly reflect customer requirements by translating those customer requirements into the appropriate technical requirements for each phase of project product development.

A

Voice of Customer

505
Q

A document that provides detailed deliverable, activity, and scheduling information about each component in the work breakdown structure.

A

WBS Dictionary

506
Q

An earned value method that divides a work package into measurable segments each ending with an observable milestone, and then assigns a weighted value to the achievement of each milestone.

A

Weighted Milestone Method

507
Q

The process of evaluating scenarios in order to predict their effect on project objectives.

A

What-If Scenario Analysis

508
Q

A permission and direction, typically written, to begin work on a specific schedule activity or work package or control account. It is a method for sanctioning project work to ensure that the work id one by the identified organization, at the right time and in the proper sequence.

A

Work Authorization

509
Q

A subsystem of the overall project management system. It is a collection of formal documented procedures that defines how project work will be authorized (committed) to ensure that the work is done by the identified organization, at the right time, and in the proper sequence. It includes the steps, documents, tracking system, and defined approval levels needed to issue work authorizations.

A

Work Authorization System

510
Q

A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.

A

Work Breakdown Structure (WBS)

511
Q

An entry in the work breakdown structure that can be at any level.

A

Work Breakdown Structure Component

512
Q

The work defined at the lowest level of the work breakdown structure for which cost and duration can be estimated and managed.

A

Work Package

513
Q

The raw observations and measurements identified during activities being performed to carry out the project work

A

Work Performance Data

514
Q

The performance data collected from various controlling processes, analyzed in context and integrated based on relationship across areas.

A

Work Performance Information

515
Q

The physical or electronic representation of work performance information complied in project documents, intended to generate decisions, actions, or awareness

A

Work Performance Reports

516
Q

A response to a threat that has occurred, for which a prior response had not been planned or was not effective.

A

Workaround