Glossary Flashcards
[Project Risk Management] one of the risk response strategies for threats/opportunities in which the risk is accepted as it is without any risk mitigation measures and the risk will only be dealt with either actively or passively if it occurs.
⇔ see also Avoid, Transfer, Mitigate, Exploit, Share and Enhance
Accept
[Project Quality Management] the factors the deliverables must be met before they will be formally accepted.
Acceptance Criteria
[Project Quality Management] the deliverables (e.g. products, services or capabilities) that are accepted by the client / customer to meet the acceptance criteria.
⇔ see also Verified Deliverables
Accepted Deliverables
[Project Scope Management] both sides of a conflicting situation try to identify points of agreements and play down disagreement
⇔ see also Avoidance, Compromise, Forcing, Collaboration and Confrontation
Accommodation
[Project Quality Management] a measure of correctness.
⇔ see also Precision
Accuracy
[Project Human Resource Management] one of the motivational theories proposing that individuals are motivated by either achievement, power and affiliation.
Achievement Theory
[Project Resource Management] the process to acquire team members with required competencies to complete the project successfully.
Acquire Project Team
[Project Schedule Management] the work package is decomposed into activities. Each activity must have an expected duration.
Activity
[Project Schedule Management] a document providing additional information to the activities listed in the activity list; additional info include: activity identifier, description, constraints, assumptions, predecessor and successor activities, resources and responsible persons.
Activity Attributes
[Project Schedule Management] one of the activity attributes used to uniquely identify an activity for sequencing and tracking activities.
Activity Identifier
[Project Schedule Management] the time required for the schedule activity between the start and finish dates.
Activity Duration
[Project Schedule Management] a document listing all the activities of the project with identifiers and brief descriptions.
Activity List
[Project Schedule Management] a diagramming technique used for sequencing activities by placing the activities on arrows and dependencies are indicated by connecting the arrows with nodes.
Activity-on-Arrow (AOA)
[Project Schedule Management] a diagramming technique used for sequencing activities by placing the activities on the nodes which are connected by arrows to show dependencies.
Activity-on-Node (AON)
[Project Cost Management] the actual amount of money/cost to date spent on performing the project work.
Actual Cost (AC)
[Project Integration Management] an Agile project management methodology enabling faster response to changes by managing the project in short iterations.
Adaptive Life Cycle
[Project Schedule Management] during project execution, a technique used to bring delayed project activities into alignment with the project plan.
Adjusting Leads and Lags
[Project Quality Management] a business tool to organize ideas and data based on natural relationships used in brainstorming sessions.
Affinity Diagrams
[Project Procurement Management] a written or verbal communication (e.g. contract, memo, email, verbal arrangement…) to indicate preliminary intentions of a project/work.
Agreements
[Project Schedule Management] a technique to identify and analyze the different options to perform the project work most efficiently.
Alternative Analysis
[Project Scope Management] a technique to generate and analyze different options for carrying out the project work for greatest efficiency.
Alternatives Generation
[Project Schedule/Cost Management] a method to estimate the activity/project durations and costs based on available information from similar project performed before. Great for the initial phase of the project but estimates are not very accurate.
Analogous Estimating
[Project Risk/Procurement/Stakeholder Management] methods used to identify possible risks / consequences based on project variables and interactions.
Analytical Techniques
[Project Schedule/Cost Management] used in earned value management (EVM) to measure schedule/cost performances calculated in direct proportion to the progress of another discrete effort(s).
⇔ see also Discrete Efforts and Level of Efforts
Apportioned Effort
[Project Integration Management] a change request that has been submitted through Perform Integrated Change Control process and approved for implementation.
Approved Change Request
[Project Procurement Management] when there is a dispute between the vendor and the client, an effective way for problem resolution by involving a neutral third-party.
Arbitration
[Project Quality Management] is an identifiable and specific cause for the variation in the control chart. Must be investigated and remedied.
Assignable Cause
[Project Quality Management] is a process for internal control by checking for a particular attribute (i.e. either pass or fail)
Attribute Sampling
[Project Risk Management] Use for negative risks (i.e. threats) by incorporating plans to stay clear of / eliminate the risk events and impacts.
⇔ see also Transfer, Mitigate and Accept
Avoid
[Project Scope Management] both sides of a conflicting situation ignore the conflict, which is not considered a good conflict resolution technique
⇔ see also Accommodation, Compromise, Forcing, Collaboration and Confrontation
Avoidance
[Project Scope Management] a documented list of prioritized project tasks, often used in Agile project methodologies.
Backlog
[Project Scope Management] a method for calculating the late start and late finish dates for each activity of the activity schedule diagram from end to start.
⇔ see also Critical Path Method (CPM)
Backward Pass
a type of matrix organization where the project manager has as much control over the budget and resources compared to a functional manager.
Balanced Matrix
[Project Schedule/Cost Management] is the approved version of project plan (scope, cost, schedule) used to compare with actual work performance.
Baseline
additional information outlining the basis for the project estimates.
Basis of Estimates
[Project Quality Management] the practice of measuring existing processes and procedures with similar orgnaizations to establish a basis for comparison for performance improvements.
Benchmarking
[Project Procurement Management] a conference with all bidders for clarification on the contract requirements to ensure all bidders share the same understanding.
Bidder Conference
[Project Schedule/Cost Management] an accurate but time-consuming estimating method by adding up the estimates for individual activity costs/durations.
Bottom-up Estimating