Glossary Flashcards

1
Q

[Project Risk Management] one of the risk response strategies for threats/opportunities in which the risk is accepted as it is without any risk mitigation measures and the risk will only be dealt with either actively or passively if it occurs.
⇔ see also Avoid, Transfer, Mitigate, Exploit, Share and Enhance

A

Accept

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

[Project Quality Management] the factors the deliverables must be met before they will be formally accepted.

A

Acceptance Criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

[Project Quality Management] the deliverables (e.g. products, services or capabilities) that are accepted by the client / customer to meet the acceptance criteria.
⇔ see also Verified Deliverables

A

Accepted Deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

[Project Scope Management] both sides of a conflicting situation try to identify points of agreements and play down disagreement
⇔ see also Avoidance, Compromise, Forcing, Collaboration and Confrontation

A

Accommodation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

[Project Quality Management] a measure of correctness.

⇔ see also Precision

A

Accuracy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

[Project Human Resource Management] one of the motivational theories proposing that individuals are motivated by either achievement, power and affiliation.

A

Achievement Theory

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

[Project Resource Management] the process to acquire team members with required competencies to complete the project successfully.

A

Acquire Project Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

[Project Schedule Management] the work package is decomposed into activities. Each activity must have an expected duration.

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

[Project Schedule Management] a document providing additional information to the activities listed in the activity list; additional info include: activity identifier, description, constraints, assumptions, predecessor and successor activities, resources and responsible persons.

A

Activity Attributes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

[Project Schedule Management] one of the activity attributes used to uniquely identify an activity for sequencing and tracking activities.

A

Activity Identifier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

[Project Schedule Management] the time required for the schedule activity between the start and finish dates.

A

Activity Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

[Project Schedule Management] a document listing all the activities of the project with identifiers and brief descriptions.

A

Activity List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

[Project Schedule Management] a diagramming technique used for sequencing activities by placing the activities on arrows and dependencies are indicated by connecting the arrows with nodes.

A

Activity-on-Arrow (AOA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

[Project Schedule Management] a diagramming technique used for sequencing activities by placing the activities on the nodes which are connected by arrows to show dependencies.

A

Activity-on-Node (AON)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

[Project Cost Management] the actual amount of money/cost to date spent on performing the project work.

A

Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

[Project Integration Management] an Agile project management methodology enabling faster response to changes by managing the project in short iterations.

A

Adaptive Life Cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

[Project Schedule Management] during project execution, a technique used to bring delayed project activities into alignment with the project plan.

A

Adjusting Leads and Lags

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

[Project Quality Management] a business tool to organize ideas and data based on natural relationships used in brainstorming sessions.

A

Affinity Diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

[Project Procurement Management] a written or verbal communication (e.g. contract, memo, email, verbal arrangement…) to indicate preliminary intentions of a project/work.

A

Agreements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

[Project Schedule Management] a technique to identify and analyze the different options to perform the project work most efficiently.

A

Alternative Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

[Project Scope Management] a technique to generate and analyze different options for carrying out the project work for greatest efficiency.

A

Alternatives Generation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

[Project Schedule/Cost Management] a method to estimate the activity/project durations and costs based on available information from similar project performed before. Great for the initial phase of the project but estimates are not very accurate.

A

Analogous Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

[Project Risk/Procurement/Stakeholder Management] methods used to identify possible risks / consequences based on project variables and interactions.

A

Analytical Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

[Project Schedule/Cost Management] used in earned value management (EVM) to measure schedule/cost performances calculated in direct proportion to the progress of another discrete effort(s).
⇔ see also Discrete Efforts and Level of Efforts

A

Apportioned Effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

[Project Integration Management] a change request that has been submitted through Perform Integrated Change Control process and approved for implementation.

A

Approved Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

[Project Procurement Management] when there is a dispute between the vendor and the client, an effective way for problem resolution by involving a neutral third-party.

A

Arbitration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

[Project Quality Management] is an identifiable and specific cause for the variation in the control chart. Must be investigated and remedied.

A

Assignable Cause

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

[Project Quality Management] is a process for internal control by checking for a particular attribute (i.e. either pass or fail)

A

Attribute Sampling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

[Project Risk Management] Use for negative risks (i.e. threats) by incorporating plans to stay clear of / eliminate the risk events and impacts.
⇔ see also Transfer, Mitigate and Accept

A

Avoid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

[Project Scope Management] both sides of a conflicting situation ignore the conflict, which is not considered a good conflict resolution technique
⇔ see also Accommodation, Compromise, Forcing, Collaboration and Confrontation

A

Avoidance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

[Project Scope Management] a documented list of prioritized project tasks, often used in Agile project methodologies.

A

Backlog

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

[Project Scope Management] a method for calculating the late start and late finish dates for each activity of the activity schedule diagram from end to start.
⇔ see also Critical Path Method (CPM)

A

Backward Pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

a type of matrix organization where the project manager has as much control over the budget and resources compared to a functional manager.

A

Balanced Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

[Project Schedule/Cost Management] is the approved version of project plan (scope, cost, schedule) used to compare with actual work performance.

A

Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

additional information outlining the basis for the project estimates.

A

Basis of Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

[Project Quality Management] the practice of measuring existing processes and procedures with similar orgnaizations to establish a basis for comparison for performance improvements.

A

Benchmarking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

[Project Procurement Management] a conference with all bidders for clarification on the contract requirements to ensure all bidders share the same understanding.

A

Bidder Conference

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

[Project Schedule/Cost Management] an accurate but time-consuming estimating method by adding up the estimates for individual activity costs/durations.

A

Bottom-up Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

[Project Cost Management] the estimated expenditures for the project for a specific period.

A

Budget

40
Q

[Project Cost Management] often used in earned value management (EVM), it is the total expenditure for the project on finish.

A

Budget at Completion (BAC)

41
Q

[Project Schedule Management] reserve time added to activity durations to reduce the likelihood of missing activity finish dates

A

Buffer

42
Q

[Project Integration Management] used to judge whether a project is feasible and viable, often includes a financial feasibility study, rough budget and justifications for the project

A

Business Case

43
Q

(also known as a fishbone or Ishikawa diagram) [Project Quality Management] a diagramming technique to identify the origin and effect of an issue.

A

Cause and Effect Diagram

44
Q

[Project Integration Management] a group of people responsible for approving / rejecting major change requests (as defined in the Project Management Plan).

A

Change Control Board (CCB)

45
Q

[Project Integration Management] a list consisting of all changes to the project and their impacts.

A

Change Log

46
Q

[Project Integration Management] a formal document for making change(s) to the project.

A

Change Request

47
Q

[Project Procurement Management] when a contract is not fully fulfilled, either side may make a request for compensation/ claim.

A

Claim

48
Q

[Project Scope Management] a numbering system used to identify WBS components.

A

Code of Accounts

49
Q

[Project Scope Management] team members work together in the same physical space to enhance communication and knowledge sharing.

A

Colocation

50
Q

[Project Scope Management] both sides of a conflicting situation work together for mutually consented solution, often considered the best conflict resolution technique
⇔ see also Accommodation, Avoidance, Compromise, Forcing and Confrontation

A

Collaboration

51
Q

[Project Communication Management] the number of lines of communication between individuals involved within a project, calculated by the formula: N (N-1) / 2 where N is the number of people involved.

A

Communication Channels

52
Q

[Project Quality Management] the control chart indicates that the process is within the control limits but outside specification limits which are often usual and natural variations in the system

A

Common Cause

53
Q

[Project Communication Management] techniques used for communication, can be Interactive, Push or Pull.

A

Communication Methods

54
Q

[Project Communication Management] describes how information is exchanged (e.g. Sender-Encode-Message-Decode-Receiver Model).

A

Communication Models

55
Q

[Project Communication Management] software / hardwares used to assist communication.

A

Communication Technology

56
Q

[Project Human Resource Management] one of the conflict resolution technique in which disagreements are settled by making concessions on both sides.
⇔ see also Accommodation, Avoidance, Forcing, Confrontation and Collaboration

A

Compromise

57
Q

[Project Quality Management] manages the assets of the project deliverables by recording the functional or physical characteristics of the deliverables and components; a component of the project management information system.

A

Configuration Management System

58
Q

[Project Quality Management] indicates that the results comply with the quality requirement.

A

Conformance

59
Q

[Project Human Resource Management] a conflict resolution technique to determine a collaborative and workable solution by open discussion
⇔ see also Accommodation, Avoidance, Forcing, Confrontation and Collaboration

A

Confrontation

60
Q

any factors that impose limitations on project.

A

Constraint

61
Q

[Project Risk Management] a strategy describing the measures to tackle documented risks once they arise.

A

Contingency Plan

62
Q

[Project Cost/Schedule Management] the budget set aside to fund contingent responses for identified risks (known unknown) once they arise.
⇔ see also Management Reserve

A

Contingency Reserve

63
Q

[Project Scope Management] strategically placed for grouping work breakdown structure (WBS) components with a view to better managing cost, scope and/or schedule for earned value management measurements.

A

Control Accounts

64
Q

[Project Quality Management] a statistical process tool to monitor process performance and stability over time (whether the process is within control limits).

A

Control Chart

65
Q

[Project Quality Management] the upper and lower limit on the control chart used to determine whether a process is under control by taking normal variations into account.
⇔ see also Specification Limits

A

Control Limits

66
Q

[Project Quality Management] activities performed with a view to realign project performance with what are planned in the project plan.

A

Corrective actions

67
Q

[Project Cost Management] the accumulated cost estimates for all tasks within a work package.

A

Cost Aggregation

68
Q

[Project Cost Management] represents the budget of estimated costs to be disbursed over the duration of the project, apart from any management reserves. The cost baseline can be used to compare actual costs for the project.

A

Cost Baseline

69
Q

[Project Quality Management] includes all costs of conformance (quality assurance/control measures) and costs of non-conformance (rework).

A

Cost of Quality (COQ)

70
Q

[Project Cost Management] an earned value management (EVM) metric for cost efficiency of the project to date (formula: CPI = EV / AC).

A

Cost Performance Index (CPI)

71
Q

[Project Procurement Management] a contract type in which the buyer pays the seller all allowable costs plus extra money awarded for meeting the performance targets specified in the contract as determined by the buyer.

A

Cost Plus Award Fee (CPAF)

72
Q

[Project Procurement Management] a contract type in which the buyer pays the seller all allowable costs plus a fixed amount of money as the seller profit.

A

Cost Plus Fixed Fee (CPFF)

73
Q

[Project Procurement Management] a contract type in which the buyer pays the seller all allowable costs plus incentives and sharing of unused money if under/over contracted amount.

A

Cost Plus Incentive Fee (CPIF)

74
Q

[Project Cost Management] an earned value management (EVM) metric for indicating the difference between the earned value and the actual cost (formula: CV = EV – AC).

A

Cost Variance (CV)

75
Q

a financial analysis tool for determining the costs and benefits of the project and whether the project is worthwhile.

A

Cost-benefit Analysis

76
Q

[Project Procurement Management] a contract type in which all allowable costs are bore by the buyer with additional money awarded to the seller by completing the contract requirements; most of the risks are on the buyer side.

A

Cost Reimbursable Contract

77
Q

[Project Schedule Management] a schedule compression technique used to shorten the schedule by adding extra resources.

A

Crashing

78
Q

[Project Quality Management] factors used to evaluate and decide when the deliverables meet the project requirements.

A

Criteria

79
Q

[Project Schedule Management] a technique for improving accuracy of project schedule by taking into accounts the limited resource availability and uncertainties.

A

Critical Chain Method (CCM)

80
Q

[Project Schedule Management] all the activity on the critical path of a project schedule (using Critical Path Method).

A

Critical Path Activity

81
Q

[Project Schedule Management] a technique for determining the schedule of the project by taking into accounts the sequence of activities for the longest work path.

A

Critical Path Method (CPM)

82
Q

[Project Stakeholder Management] the ones who request and/or pay for the project / deliverables.

A

Customer

83
Q

the time the data is recorded.

A

Data Date

84
Q

[Project Risk Management] a diagramming technique to help visualizing the Expected Monetary Value (EMV) of various options to assist in decision-making.

A

Decision Tree Analysis

85
Q

[Project Scope Management] the project scope is broken down into smaller segments for better estimation.

A

Decomposition

86
Q

[Project Cost Management] the correction action required for deliverables not meeting requirements.

A

Defect Repair

87
Q

[Project Scope Management] the verifiable product, service, result or capability produced by a process, phase or project.

A

Deliverable

88
Q

questionnaires are circulated among subject matter experts (SME) for anonymous feedback and recirculated until a consensus is reached.

A

Delphi Technique

89
Q

[Project Schedule Management] an activity may depend on the execution/finish of other activities; can be mandatory, discretional, external or internal.

A

Dependency

90
Q

[Project Quality Management] a statistical approach allowing simultaneous altering of several variables for comparison in order to find out the lowest cost of quality.

A

Design of Experiments (DOE)

91
Q

various methods employed for representing information and the relationships in a visual way.

A

Diagramming Techniques

92
Q

[Project Human Resource Management] a group decision-making technique in which the leader direct the decision making, best on in case when there are a lot of uncertainties.

A

Dictatorship

93
Q

[Project Cost Management] a technique used to compare the value of the future cash flows of the project with the current value of the dollar by taking inflation into accounts.

A

Discounted Cash Flow

94
Q

[Project Cost/Schedule Management] used in earned value management (EVM) to measure work performance in relation to explicit work efforts that contribute to the completion of the project.
⇔ see also Apportioned Effort and Level of Efforts

A

Discrete Effort

95
Q

[Project Schedule Management] (also known as preferred logic) two activities are considered to be best if carried out in sequence; but the sequence can be altered if needed.
⇔ see also Mandatory Dependency

A

Discretionary Dependency

96
Q

[Project Schedule Management] the amount of time between the start and finish of a schedule activity; often expressed in work days.

A

Duration