What are the 4 types of Precedence Diagraming Method (PDM)?
A
Finish-to-Start (FS): In this case, task B cannot start until task A has been completed
Start-to-Start (SS): In this case, task B cannot start until task A starts
Finish-to-Finish (FF): In this case, task A cannot be completed until task B is completed
Start-to-Finish (SF): In this case, task B cannot be completed until task A starts
2
Q
Communication complixity
A
n(n-1)/2
Adding each N significantly increases the channels
Ex:
5(5-1)/2
Answer: 10 channels
3
Q
If a team has never worked together before…
A
Collaborate and communicate