General Study Notes Flashcards

1
Q

Histogram (Bar Chart)

A

Items on the bottom with a value on the side.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Flowchart

A

illustrates the flow of a process through a system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Pareto

A

This is a histogram (bar chart) that show categories of defects from largest to smallest.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Pareto Principle

A

80/20 rule is when 80% of your business will come from 20% of your customers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Scatter diagram

A

Points on a graph, Can be a positive correlation, can be a negative correlation, or can be no correlation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If it is good, what should the SPI and CPI be?

A

Above 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If it is good, what should the CV and SV be?

A

Above 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Lag Time

A

is positive time. Take the start of the activity and move it away from the start time. Also known as waiting time. Such as waiting for materials to cure such as paint to dry, or concrete to dry.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Lead Time

A

negative time. Subtract the time in order to move it closer to the project. For example, Procurement takes 30 days from the start of the order to completion. You need cabinets for your project on 45 days. On day 15 you order the cabinets; ready to use on day 45.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Analogous Estimating (top-down estimating)

A

This relies on historical information to predict estimates. Often used when there is limited amount of information available.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Bottom-Up Estimating

A

The work has to be very detailed for this type of estimation to take place. Takes a very long time to complete, but highly accurate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Parametric Estimation

A

A technique that uses a statistical relationship between historical data and other variables (for example, square footage in construction, lines of code in software development) to calculate an estimate for activity parameters, such as scope, cost, budget, and duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

PERT Estimate

A

Also called Beta distribution Calculates an expected duration using a weighted average of 3 estimated, Optimistic, Pessimistic, Most Likely. (O+P+4M)/6.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Three-Point Estimate

A

Finds an average of Optimistic, MostLikley, and Pessimistic, Also called a triangular distribution. (O+ML+P)/3 = Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Explicit Knowledge

A

Knowledge that can be quickly and easily expressed through conversations, documentation, figures or numbers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Tacit Knowledge

A

Knowledge that is more difficult to express. This knowledge is gained through years of experience.

17
Q
A