General Q's Flashcards
Who authorises work packages within the ‘controlling a stage process?
Project Manager
Who should authorise the stage plan before the project manager authorises their work package?
Project board
Who is responsible for the business case?
Executive
What is the difference between ‘products’ and ‘activities’?
Product = noun or an outcome. (e.g. Album Launch)
Activity = noun + verb (e.g. dig hole, review tender)
What is the purpose of the busniess case?
provides a justifiable reason for starting a project and must be recorded.
What is the principle of “manage by stages” in PRINCE2?
ensures that key decisions are made before the detailed work needed to implement them.
Who is responsible for the supplier’s business case in a project?
The senior supplier is responsible for the supplier’s business case
Who is responsible for providing statements of actual benefit achievements compared to forecast benefits at benefit reviews in a project?
The senior user is responsible for providing statements of actual benefit achievements compared to forecast benefits at benefit reviews in a project.
Who is responsible for specifying the benefits in a project?
Senior User
Who is the right person to undertake the user assurance role in a project?
Someone who can assess whether a product meets the user’s needs
Can the project manager always choose to be the team manager in a project?
The project manager can choose to be the team manager, but the supplier’s staff may also fulfill this role. However, this is not mandatory and can introduce a conflict of interest.
How is the sequence in which the products of a plan will be developed identified in PRINCE2?
A product flow diagram is created to identify the sequence in which the products of the plan will be developed.
What roles can be combined within PRINCE2, and what are the constraints?
The roles of executive and project manager cannot be combined.
There cannot be more than one executive or project manager.
The executive’s accountability for project success cannot be delegated.
The project board should not assign any project assurance roles to the project manager, team manager, or project support.
What should be considered when combining roles in PRINCE2?
Conflicts of responsibilities.
Whether one person has the capacity to undertake the combined responsibilities.
Wether any bottlenecks might be created as a result.
Is it recommended to combine the roles of senior user and senior supplier in PRINCE2?
No, it is not recommended as it can create conflicts of interest for an individual.