General Mix Flashcards
IBC building codes are updated how often?
Building codes are updated every THREE YEARS (3). See the IBC 2006, 2009, 2012, and 2015 for example.
The three critical areas of in-house project management
Time
Fees
Quality
Good project managers set goals with schedules, make sure there are adequate fees and staff to meet the goals, and ensure the work is of the expected quality.
True or False?
The architect shall not be responsible for the acts or omissions of the consultant.
True
According to the AIA C401 says that The consultant is an independent contractor and the architect is not responsible for acts or omissions of the consultant.
true or false?
if a contractor does not specifically submit a submittal schedule, he or she is not entitled to an increase in contract time or sum for any extra time taken by the architect to review submittals?
true-
contractor MUST submit a submittal schedule
Davis Bacon Act
A law that requires workers on federal or federally-assisted construction projects to be paid no less than the local prevailing wage and benefits.
Product and completed operations insurance
Liability insurance for damages caused by installed goods after the transfer of title following construction. Purchased by the contractor.
How should a mechanics lein issue be resolved?
Enter into mediation- this is the only way to enable the responsible party to clear the lien.
Why should the contractor not pay the subcontractor? -The contractor may have already paid the subcontractor; the lien may be invalid.
Why not the owner pay the subcontractor? - this puts the owner at risk; the lien may be unsubstantiated, or the default may be the contractor’s.
Can the contractor be forced to subcontract with a subcontractor?
No.
Refer to AIA A201-2017 Section 5.2.2, which states that the contractor shall not be required to contract with anyone to whom the contractor has made a reasonable objection.
G701
change order-
the change order is a written instrument prepared by the architect and signed by the owner and contractor
The four major categories for an operating budget are:
Soft Costs-permitting, legal fees, insurance, contingencies, testing, and inspections
Hard Costs-the construction and FF&E
Sources- include funding, tax credits, and grants.
Uses-include the cost of the real estate
Break-even rate
The overhead rate plus the unit cost of 1.00 for an hour of salary.
Example: Overhead Rate of 1.30 + 1.00 = 2.30 Break-Even Rate. This means that, for every dollar of salary, the firm must recapture $2.30.
True or False: Each consultant assumes primary responsibility and liability to the owner for the accuracy and completeness of his or her own work.
False.
Per A201, the architect is primarily responsible to the owner for his or her consultants’ work.
Construction Manager as Contractor
CMc
A construction manager constructor advises on constructability and cost estimates during the design of a project then shifts to the responsibilities of contractor builder.
Developer Clients
a type of private client-owner who builds for other people for a profit.
Construction Manager at Risk
CMAR
Architect-Contractor describes a single entity that provides design-build services
true or false?
according to the B101- the cost to design and document alternates are included in the architects basic services
TRUE
Architects Supplemental Instructions
An ASI is a more informal way of issuing changes to the contractor that do not involve a change in time or money.
Scope creep
Scope creep
When the contracted scope of work is stretched or expanded by ambiguities, events, or conduct.
what is one of the most effective and easy ways to improve client communication skills?
read what your clients read
True or False: The contractor pays for all necessary project permits before and after signing the contract.
False.
The contractor pays for all permits only AFTER the contract has been signed.
true or false?
substitutions during bidding should be reviewed by the architect at no additional cost to the owner?
False
“If the Bidding Documents permit substitutions, upon the Owner’s written authorization, the Architect shall, as an Additional Service, consider requests for substitutions and prepare and distribute addenda identifying approved substitutions to all prospective bidders.” -found in the B101.
Who approves the shop drawings?
Contractor then Architect
the contractor reviews all shop drawings for compliance with the contract documents, and submits to the architect for approval.
Two important factors for productivity
- Time management.
- Communication effectiveness.
Note: These factors are also important for job satisfaction.
Earnest money
Money paid by a buyer to a seller (of real estate) to show the buyer’s good faith in the transaction. Typically held in an escrow account.
What is the goal of Construction Documents?
To develop a refined set of drawings that can be permitted and modified later if necessary. To create a set of drawings that can be priced and built from.
architect
is the overall project design coordinator who is responsible for accessibility, life safety, building codes, and consultant coordination
Force majeure clause
A force majeure clause is a contract provision that states that time shall be extended for all parties due to causes beyond reasonable control such as fire, changes in legislation, extreme weather, terrorism, epidemics, and strikes. In French, force majeure means “act of God.”
contract documents
includes all items necessary for the proper execution and completion of the work done by the contractor
In the project delivery method of COST PLUS A FEE, what is the main driving factor for this selection of delivery method?
SCOPE-
is the primary selection factor for cost plus fixed fee.
Life Cycle Costs per year equation
Life Cycle Cost / time = Life Cycle Cost per year
do not include installation
All communications from sub-contractors to architect are through…..
…..the contractor.
AIA 201
square feet to cubic yards equation:
(sq ft x height in ft) / divided by 27
typical schematic design deliverables
structural grid locations
structural systems defined
building areas demarcated
project images and renderings
When reviewing submittals, the architect is responsible for review of what items?
VOC Content-meet codes
materials- meet intent
finishes- meet intent
(not installation, dimensions, or quantities)
BFE
Base
Flood
Elevation
FEMA defines the BFE as “the regulatory requirement for the elevation or flood-proofing of structures. The relationship between the BFE and a structure’s elevation determines the flood insurance premium.” (“base flood” is the same as the 100-year flood.)
IRMI
International
Risk
Management
Institute;
publishes information about insurance and risk management.
the AIA advocates and promotes the development and adoption of model building codes that do what?
Is the product of informed education and research.
Includes participation by the architect and the public in a consensus process.
Is cost effective in relation to the public benefit.
True or False: The architect has no responsibility for the quality of his or her consultants’ drawings.
False.
The architect is responsible for quality control of his or her consultants’ work when the consultant is contracted under the architect.
AIA A295
General Conditions of the Contract for Integrated Project Delivery.
Owner, Contractor, and Architect are required signatories.
ANSI
ANSI contains technical criteria.
Who handles Violations of accessibility requirements?
The Americans with Disabilities Act is federal law enacted in 1990 requiring public facilities to be accessible to persons with disabilities. The law is enforced by the court system.
the four phases of a project life cycle
initiation
planning
execution
closure
Who determines when a project has been substantially completed?
the contractor
according to the AIA A201 - submittals
true or false?
The architect is required to coordinate with all of the owners consultants?
True
According to AIA B101
What is the goal of Design Development?
To refine the schematic design such that every design decision necessary to build the project is considered. At the end of Design Development you should be able to go off and produce a set of Construction Documents and never have to consult the owner after DD.
Construction Manager as Agent
CMa
A construction manager agent is brought on board early in a project to advise the owner on constructability aspects and can stay further into the project coordinating construction for a fixed price.
Spearin doctrine
Named after a 1918 Supreme Court landmark construction decision. It means the contractor is not liable for errors resulting from following defective plans or specifications.
AIA G801
Notice of Additional Services-
is intended to be used by an architect when notifying an owner of additional services pursuant to the AIA’s owner/architect agreements.
The greatest factor of a project in determining staffing and scheduling needs is?
COMPLEXITY-
is a word that denotes many interrelated parts that follow different rules and some level of uncertainty, making a complex project the most demanding on resources.
To accurately and persuasively defend against a claim, it is suggested that architects keep the following documents:
change order logs
meeting minutes
photographs
daily log and site observation reports
PMI
Project
Management
Institute,
a nonprofit, private, professional organization that offers tools, resources, and certifications for project management.
What authority verifies compliance with ADA requirements?
The Building Department will review accessibility compliance based on the International Building Code and adopted local and state guidelines. Violations of the law are resolved in the court system.
he ADA’s mandates, including the accessibility standards, are enforced through investigations of complaints filed with federal agencies, or through litigation brought by private individuals or the federal government. There is no plan review or permitting process under the ADA. Nor are building departments required or authorized by the ADA to enforce the ADA Standards (some building departments even include a disclaimer on their plan checks indicating that ADA compliance is not part of their approval process). Entities covered by the law ultimately are responsible for ensuring compliance with the ADA Standards in new construction and alterations.
Per AIA C401, what are consultants required to provide?
A project representative.
Drawings in the format requested by the architect.
E&O insurance (professional liability).
A cost estimate for the work.
In preparing for any disputes that might arise during the project, the architect should maintain what form of communication between all parties as a top priority?
Email correspondence-
considered legal evidence of communications. Phone calls, text messages, video and tele-conferences should always be followed up by an email confirming communications or mailed correspondence.
Type of Loan with the highest interest rate?
CONSTRUCTION LOANS-
have higher interest rates because of the increased risk to the lender. Construction loans are later converted to permanent, or mortgage, loans.
Loss of use insurance
Insurance purchased by the owner that protects against financial loss that occurs due to delays in construction stemming from events such as accidents, fire, and hazards.
who issues a certificate of occupancy?
building official.
NOT building inspectors
NOT fire marshals
Triple Constraints
Cost
Quality
Time
Used for prioritization in decision-making. Pick two; you often can’t have all three.
Architectural Barriers Act
The Architectural Barriers Act applies to buildings funded with federal funds.
In the project delivery method of NEGOTIATED SELECTED TEAM, what is the main driving factor for this selection of delivery method?
QUALITY-
is the primary selection factor for a negotiated select team.
Typical architects consultants:
Civil Engineer Structural Engineer Mechanical Engineer Electrical Engineer Plumbing Engineer Equipment Specialists Interior Designer
Overhead rate
The ratio of total indirect expenses to total direct labor.
quality management actions during programming
Consensus reviews- a second series of interviews or work sessions is held to confirm that the knowledge was accurately communicated to the design team.
Phasing- includes setting priorities for detailed client information and assembly of information.
Teaming- two or more people should convene to gather information through client interviews, work sessions, and direct observation.
Benchmarking Tours- benchmarking includes the direct observation of state-of-the-art facilities similar to that being programmed.
Performance Bond
provides for the event a contractor cannot complete the work he or she is contracted for.
AIA G807
Project Team Directory-
lists basic information about project team members.
Components of a project management work plan
- Project description and client requirements
- Statement of deliverables
- Team organization
- Responsibility matrix
- Preliminary project schedule
- Preliminary staffing needs
- Project directory
- Internal project budget and profit plan
- Code information (optional)