The drain for a pressure relief valve on a water heater should be extended to:
a) the kitchen or washroom b) a basement
c) a waste line
d) the outside of the building
d) the outside of the building
2) What is the MAXIMUM height from which concrete should be poured is:
a) 1 1/2 feet
b) 3 feet
c) 4 feet
d) 6 feet
d) 6 feet
3) When a stairway serves a public building, what is the MINIMUM number of steps for which a handrail is required?
a)1
b)2
c)3
d)4
b)2
4) If unused mortar stiffens due to hydration of cement, what must you do? a) re-temper the mortar
b) wet the cement
c) discard the mortar
d) add more water
c) discard the mortar
5) What is the MINIMUM length of a handrail extension if one is required
for a stairway?
a) 6”
b) 10”
c) 12”
d) 16”
c) 12”
6) Beam type platforms for suspended scaffolds must have stringers of lumber at least _____ set on edge.
a)1” x 2”
b)2” x 4”
c)2” x 6”
d)2” x 8”
c)2” x 6”
7) Cemented soil:
a) contains sand and gravel that are fused by high heat
b) cannot be crushed into individual particles with fingers
c) is distinguished from granular by the presence of clay d) can sometimes be crushed to a powder with the fingers
b) cannot be crushed into individual particles with fingers
8) The wall between a garage and a bedroom must be at least: a) 1/2” green board
b) 1/2” drywall
c) 2 Layers of 5/8” drywall
d) 2 layers of 3/8” drywall
d) 2 layers of 3/8” drywall
9) What minimum time must you wait before caulking or grouting new tiles?
a)1 Day
b)1 to 2 Days
c)2 to 3 Days
d)3 to 4 Days
b)1 to 2 Days
10) What maximum slope is specified by the UBC for a required handicap ramp?
a) 1:8 (12.5%)
b) 1:10 (10.0%)
c) 1:12 ( 8.3%)
d) 1:15 ( 6.7%)
c) 1:12 ( 8.3%)
11) In cold climates, you cover freshly poured concrete to prevent:
a) hydration
b) freezing
c) warping
d) discoloration
b) freezing
12) Which of the following would you use to install roofing tiles?
a) masonry saw
b) any roofing tool
c) roofer’s hatchet
d) masking tape
a) masonry saw
13) Greenboard would be used for?
a) bathroom walls
b) kitchen ceiling
c) under the eaves in a damp climate d) roof sheathing
a) bathroom walls
14) If you are a general contractor, you should call a specialty contractor when:
a) HVAC equipment must be installed
b) you need to work with 240 volts
c) a gas furnace is involved
d) you encounter an unfamiliar trade
d) you encounter an unfamiliar trade
15) Where would be the best place to look for a roof leak?
a) holes in shingles
b) ridge lines
c) valley flashings
d) gutters
c) valley flashings
When do you need bracing for a drywall wall?
a) diagonal bracing is needed every 25’ for any drywall wall.
b) load bearing wall
c) shear wall
d) non- load bearing wall
a) diagonal bracing is needed every 25’ for any drywall wall.
In framing, What is a lookout?
a) an optical leveling telescope
b) a safety watchperson on duty during scaffold construction
c) a cantilevered beam
d) a large upper story window
c) a cantilevered beam
How should you clear the roots from a construction site?
a) there is no need to clear roots
b) clear roots to 12” below grade
c) clear all roots around the building
d) use trencher to cut 6’ deep and 12’ from buildings
b) clear roots to 12” below grade
In a work space, travel distance to a fire extinguisher must not be more than how many feet?
a) 25 c) 50
b) 35
d) 75
d) 75
When nailing roofing, the nail heads:
a) should never be overdriven
b) should be brought almost to the surface of the shingle c) should not exert any pressure on the roofing
d) all of the above
d) all of the above
How long should you wait before sealing new tile work?
a)1 day
b)2 days
c) 3 days
d) 2 weeks
d) 2 weeks
When would you use a 1.5 gpm fixture?
a) you want to conserve water
b) there is a draught
c) there is not enough water pressure
d) none of the above
a) you want to conserve water
Where do you need a fire wall?
a) between a bedroom and a bathroom
b) between a kitchen and any other room
c) between a living room and a bedroom
d) a separation wall between a dwelling and an attachment
d) a separation wall between a dwelling and an attachment
In construction, a hazardous area should be marked with what color
tape?
a) red
b) yellow and black caution tape
c) blue
d) yellow