General Flashcards

1
Q

How often do the AIA contracts get revised / updated?

A

Every 10 years on the 7’s (2007, 2017, 2027)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Name 2 consultants the owner typically engages

A

Geotechnical Engineer & Civil Engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Name 3 consultants the architect typically engages.

A

Structural Engineer, Mechanical Engineer & Electrical Engineer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Name 3 Milestone dates

A
  1. Design phase milestones
  2. Construction Commencement
  3. Substantial Completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are 4 implied duties of an Architect?

A
  1. Cooperating with contractors.
  2. Not interfering with the contractors work.
  3. Giving relevant information to contractors.
  4. Assisting the owner in coordinating work.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the three conditions that must be met for an architect to be found negligent?

A
  1. A legal duty must be established between parties.
  2. It must be shown that the architect breached that duty.
  3. It must be shown that the breach of duty was the cause of damage or injury.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are three defense of claims?

A
  1. Betterment
  2. Statute of Limitations.
  3. Statute of Repose
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What insurance does an architect need to carry?

A

Commercial general liability, automobile liability, workers compensation, employers liability & professional liability.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is AIA A201?

A

General Conditions of the Contract for Construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is AIA G702?

A

Application and Certificate for Payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Betterment?

A

If a change order arrived at the fault of the Architects mistake, the architect can claim the owner would have had to pay for the originally intended outcome therefore the architect should only pay for the costs acquired by making the change later.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Statute of Limitations?

A

Sets a time limit within which a claim can be made. Each state has its own statute of limitations.
Typically begins at the date of substantial completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Statute of Repose?

A

A set time limit in which a claim can be made, typically shorter time period than statute of limitation and does not begin until the problem is first discovered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is AIA B101?

A

Standard Form of Agreement Between Owner & Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the Cost of Work?

A

The Cost of Work is the cost of construction only. Does not include architects fee, land fee, lawyers fees etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Vicarious Liability?

A

This is the indirect liability imposed on a party resulting from the acts or omissions of another person or entity (agent of the company) for whose conduct the party is responsible.

17
Q

What size must a firm be before the American’s with Disabilities Act makes it illegal to discriminate on the basis of disabilities?

A

While it is highly unethical for any size firm to discriminate on the basis of disabilities, for firms of 15 people or more, it is illegal to do so base on the American’s with Disabilities Act.