Gantt Chart Flashcards
1
Q
What are the steps to working out the end date
A
- How many days are non working of that month
- How many days in September
- The total days of the month minus the non working days to get how many working days
- Put it into a fraction - number of working days divided by the number of days in the month times by 1
- Duration minus the answer to 4, and keep misusing 1 until you get a number between 0 and 1
- The answer to 5 times the amount of days in the month
- Round up the answer to 6 to get number of days
2
Q
Work out the end date using this example
Start date - 07/01/2023
Duration - 2.86
A
1 - non working days = 6
2 - how many days in jan = 31
3 - 31-6 = 25
4 - 25 / 31 x 1 = 0.81 months
5- 2.86 - 0.81 - 1 - 1 = 0.05
5a - working duration in feb - 1 month
- working duration in March - 1 month
6 - 0.05 x 31 = 1.5
7 - round up to 2 days
ANSWER - END DATE IS 2ND APRIL 2023