G2 - Select Concrete Forming Systems Flashcards

1
Q

If the allowable deflection is 1/400, how much deflection can there be over a span of 1.6 metres?

A

4.0 mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What effect does rapid concrete placement have on forms?

A

It may cause them to fail

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which of the following are used to create a three-dimensional pattern on the face on a concrete wall?

A

Rustication strips

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are three main objectives in concrete formwork construction?

A

Safety, architectural design and efficiency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the correct shape and placement of a rustication strip?

A

Bevel the stock and place the wide side to the form

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What determines the amount of deflection in formwork sheathing?

A

The spacing of studs or supports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What loads are false work designed to take for suspended slabs / beams / girders?

A

Previously placed concrete, workers and equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When placing concrete, why can the form pressures at the bottom of column forms be very high?

A

Because they are usually filled to the top in one placement and fully vibrated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which of the answers below is a major factor that effects the pressure on formwork?

A

Rate of placement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a main disadvantage of molds and liners used in formwork?

A

To strip the formwork the molds will most likely be destroyed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the purpose of a test block?

A

To show the quality and finished surface of the concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why is bush hammering rarely done for a finished concrete surface?
Question 12

A

It is very labour intensive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why are gap-graded aggregates used for exposed aggregate?

A

It makes an even, pebbled look

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you expose the aggregate when making an exposed aggregate finish?

A

By removing the cement paste shortly after the concrete has set.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

For architectural concrete, the location of ties is very important.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly