Formwork for footings must be…
correctly positioned, level, accurately dimensioned and easy to remove (strip)
Concrete footings must be cast…
directly on an undisturbed bearing surface
Simple Forms consist of…
Form sides (either partial or full) And cleats (which also act as spreaders)
when setting footing forms with a level
always set them a little high. pounding the stakes slightly further into the ground makes the final adjustment
Continuous strip footings
Are footings that support a foundation wall and are normally continuous.
The foundation wall..
Resists the pressure caused by the compacted backfill
The floor joists at the top
and the footing at the bottom support the wall
Keyway
A cut out in the concrete when pouring footings and foundation walls separately.
Normally with a beveled 2x4 or etched in after the pour
Maximum vertical step & minimum horizontal distace to next step