Fundamentals of BC_ Chap 10 Flashcards

1
Q

minimum recommended
separation between wythes of a cavity
wall

A

2 inches (50 mm).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

where insulation boards are inserted into the cavity, the remaining clear space between the face of the insulation ad the back of the outer whythe should not be reduced to less than x inch?

A

1 inch.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Weep holes should be installed not more than how many inches horizontally in brick?

A

24 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Weep holes should be installed not more than how many inches horizontally in concrete masonry?

A

32 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Weep holes should lie immediately on top of the ashing in the wall to keep the bottom of the cavity as dry as possible.
Min diameter for a weep hole is?

A

1/4nch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Ways to create weep hole:

A
  1. A short piece of rope laid in the mortar joint and later pulled out, with a plastic or metal tube laid in the mortar,
  2. or simply by simply leaving a head joint unmortared.
  3. Plastic and metal weep hole accessories with insect screens are available for installation in unmortated head joints to prevent bees or other insects form taking up residence within the cavity.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When the cavity wall
reaches the bottom of the cavity, it is
caught by a thin, impervious membrane
called?

A

a flashing and drained
through weep holes to the exterior of
the building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

dampproofing

A
may be applied
to the cavity side of the interior
wythe of the wall.
In the event that water
does bridge the cavity, this coating
discourages seepage into the interior
wythe.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The minimum recommended
separation between wythes of a cavity
wall

A

2 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

During construction, the cavity

must be kept free of

A
mortar droppings,
brick chips, and other debris,
which can clog the weep holes or
form bridges that can transport water
across the cavity to the inner wythe
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
inevitably some of the mortar falls into
the cavity. Eventually, enough mortar
may accumulate at the bottom of the
cavity to block drainage holes. One
solution to this problem?
A
Is to place a
strip of wood on the steel ties in the
cavity to catch such mortar droppings,
then to pull out this strip and
scrape the mortar off it before placing
the next row of ties.
An alternative is for the
mason to bevel the bed joint with the
trowel, making it thinner at the cavity
face and thicker at the outside face,
before placing the masonry units in it.
This minimizes the squeezing out of
mortar into the cavity.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

cavity drainage materials

A
in the form of various proprietary
free-draining, woven, or
matted products have come into use.
These materials are inserted within
the cavity, either at the bottom of the
cavity or continuously throughout its
full height, to catch mortar droppings
so that they do not obstruct drainage
(Figure 10.5). 
Such products, though
helpful in keeping weep holes open,
may still permit mortar droppings to
accumulate, creating bridges that can
transfer heat and moisture across the
cavity. For this reason, they should
not be considered a substitute for
good construction practices aimed at
keeping the cavity as free of mortar
droppings as possible.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Two general types of flashing are used in masonry construction

A

External flashings:
prevent moisture from penetrating into the masonry wall at its exposed top or where it intersects the roof.

Internal fl ashings (also known as concealed or through-wall fl ashings)
catch water that has penetrated a masonry wall and drain it through weep holes back to the exterior.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Flashings and Drainage

Two general types of flashing are used in masonry construction:

A

External flashings
prevent moisture from penetrating into the masonry wall at its exposed top or where it intersects the roof.

Internal flashings
(also known as concealed or through-wall flashings) catch water that has penetrated a masonry wall and drain it through weep holes back to the exterior.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The base flashing is normally turned up for a height of at least

A

8 inches (200 mm).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

internal flashing that is placed at

A

the bottom of the wall cavity.

17
Q

Where an internal flashing crosses the wall cavity,

A

it should be turned up 6 to 9 inches (150Ð225 mm) at the back face of the cavity and penetrate the inner wythe by at least 2 inches (50 mm). In this manner, water draining down the cavity is intercepted by the ß flashing and directed toward the exterior of the wall.

18
Q

c. At the outside face of the wall, the ß ashing should be carried at least how many inch?

A

3/4

19
Q

There are three general ways of insulating masonry walls:

A

on the out-side face, within the wall, and on the inside face.

20
Q

EIFS

A

exterior insulation and finish system
which consists of panels of plastic foam that are attached to the masonry and covered with a thin, con-tinuous layer of polymeric stucco rein-forced with glass fiber mesh.

21
Q

Expansion joints

A

inten-tionally created slots that can close slightly to accommodate expansion of surfaces made of brick or stone masonry.
open seams that can close slightly to allow expansion to occur in adjacent areas of material. Expansion joints in brick walls permit the bricks to expand slightly under moist conditions (Figure 10.21). Ex-pansion joints in aluminum curtain wall mullions (Figure 21.14) allow the elements of the wall to increase in size when warmed by sunlight.

22
Q

Control joints

A

are inten-tionally created cracks that can open to accommodate shrinkage in surfaces made of concrete masonry.
deliberately cre-ated lines of weakness along which cracking will occur as a surface of brittle material shrinks, relieving the stresses that would otherwise cause random cracking. The regularly spaced grooves across concrete side-walks are control joints; they serve to channel the cracking tendency of the sidewalk into an orderly pattern of straight lines rather than random jagged cracks. Elsewhere in this book, control joint designs are shown for concrete ß oor slabs (Figure 14.3c), concrete masonry walls (Figure 10.21), and plaster (Figure 23.12).

23
Q

Abutment joints,
sometimes called construction joints
or isolation joints,

A

re placed at junctions be-tween masonry and other materials, or between new masonry and old masonry, to accommodate differences in movement.

24
Q

Efflorescence can usually be avoided

A

by choosing masonry units that have been shown by laboratory testing not to contain water-soluble salts, by using clean ingredients in the mortar, and by minimizing water intrusion into the masonry construction.

25
Q

Below grade, masonry should first be

A

parged (plastered on the outside)
with two coats of Type M mortar to a total thickness of 1/2 inch (13 mm) to seal cracks and pores. After the parg-ing has cured and dried, it can be coated with a bituminous dampproof-ing compound or, if a truly watertight wall is required below grade, it can be covered with a waterprooÞ ng layer, as discussed in Chapter 2.

26
Q

Mortar cannot be allowed to freeze before it has cured; otherwise, its strength and watertightness may be seriously damaged. In cold climates, special precautions are necessary if masonry work is carried on during the winter months. These include such measures as keeping masonry units and sand dry, protecting them from freezing temperatures prior to use, warming the mixing water (and sometimes the sand as well) to produce mortar at an optimum tem-perature for workability and curing, using

A

Type III (high early strength) cement to accelerate the curing of the mortar, and mixing the mortar in smaller quantities so that it does not cool excessively before it is used.

27
Q

The Þ nished masonry must be protected against freezing for at least

A

2 to 3 days after it is laid, and the tops of walls should be protected from rain and snow. Chemical accelerators and so-called ÒantifreezeÓ admixtures are, in general, harmful to mortar and rein-forcing steel and should not be used.